HomeMy WebLinkAboutPermit Building 2000-2-11
,.
Job# 99-01568-01
Page 1 of 3
TRANS#=Ol-0000579
DATE:FEB 11 2000
AMT RECD:2 $ 14987.54
CHANGE:
CASHIER: 059
COMMERCIAL PERMIT
City Of Springfield
Community Services Division
Building Safety
Job Number: 99-01568-01
225 North Fifth Street
Springfield, OR 97477
Office: 726-3759
Inspection Line: 726-3769
Location Of Proposed Site: 860 Beltline Rd Spr
Assessors Map#: 17031500
Lot: Block: Addition:
Tax Lot #: 02400
Subdivision:
Owner: Advance Imaging Center
Address: 1200 Hilyard Street
Scope Of Work: Office
Phone Number: 541-687-7134
City/State/Zip: Eugene, OR
New Value: $398,000
Tenant Improvement
Contractor
Dorman Construction Inc
32986 Roberts Ct, Coburg, OR
97408-9495
L.A. Kersh
X,X,X
Electrical Contr Jb Electric Inc 104929
4065 West 11 th Avenue, #18, Eugene,
OR 97402
Contractor Type
General Contr
Registration #
68801
Expiration Date
8/31/00
Phone
541-984-0012
Designer
3/14/00
541-687 -5770
Mechanical Contr Atr Air Inc 121444
3762 W 11th Ave #250, Eugene, OR
97402
Plumbing Contr Harvey & Price Co 77
Po Box 1910, Eugene, OR 97440-1910
3/26/01
541-935-5414
10/31/00
541-746-1621
Quad Area:
# Of Units:
, Constr. Type:
Water Heater:
Office Us'e
Land Use:
Zoning Code:
Bedrooms:
Range:
# Of Buildings:
Occupancy Group:
, Heat Source:
Sq. Footage:
To request an inspection call the 24 hour recording at 726-3769. All inspections requested before 7:00
a.m. will be made the same working day, inspections requested after 7:00 a.m. will be made the following
working day.
Required Inspections
Building
Framing
Drywall
Ceiling Grid
SUB - Final
- Prior to cover.
- Prior to taping.
Final Fire
Final Building
Rough Electrical
Electrical Service
Final Electrical
Underfloor Plumbing
Rough Plumbing
Backflow Device
Final Plumbing
Rough Gas
Rough Mechanical
SUB - Mechanical
Final Gas
Final Mechanical
Fee
Plan Check Fee
Total Transfered Records
Additional Plan Check
Total Plan Check
I Job# 99-01568-01 I Page 2 of 3
Required Inspections
I Building I
- When all Fire Department requirements have been met.
- When all required inspections have been approved and the building is complete.
Electrical
- Prior to cover.
- Must be approved to obtain permanent power.
-When all electrical work is complete.
I Plumbing
-Prior to insulation or decking.
- Prior to cover.
-After device is installed but before backfilling trench.
- When all plumbing work is complete.
I Mechanical I
-After line is installed and capped if not attached to an appliance.
- Prior to cover.
-Following City Rough Mechanical inspection approval and prior to cover:
- When all gas work is complete.
- When all mechanical work is complete.
# Of Stories:
Current Units:
Census Code: Does not apply
Height (feet):
Proposed Units:
Construction Types:
Occupancy Groups:
# Of Buildings:
# Of Bedrooms:
Handicap Access? D
-Area (Sq. Feet)
Main: Accessory:
Total:
Paid On Receipt#
Transfered Records
11/16/1999 36199
Value/Quantity
Plan Check
02/11/2000 579
Building Permit
State Surcharge For Building Permit
Building Administrative Fee
Total Building
Building
02/11/2000 579
02/11/2000 579
02/11/2000 579
Permanent: 200 Amps or Less
Permanent: 401 to 600 Amps
Branch Circuits With Feeder or Service
State Surcharge For Electrical Permit
Electric Administrative Fee
Total Electrical
E'lectrical
02/11/2000 579
02/11/2000 579
02/11/2000 579
02/11/2000 579
02/11/2000 579
457
260
398,000
5
1
135
Fee Amount
$456.95
$456.95
$260.33
$260.33
$1,103.50
$77.25 '
$33.11
$1,213.86
$250.00
$100.00
$270.00
$43.40
$18.60
$682.00
Job# 99-01568-01 I , Page 3 of 3
Fee Paid On Receipt# Value/Quantity Fee Amount
Plumbing
Minimum Plumbing Permit Fee 02/11/2000 579 $.00
Number of Fixtures 02/11/2000 579 14 $140.00
State Surcharge For Plumbing Permit 02/11/2000 579 $10.50
Backflow Prevention Device 02/11/2000 579 $10.00
, Plumbing Administrative Fee . 02/11/2000 579 $4.50
Total Plumbing $165.00
Mechanical
One to Four Outlets 02/11/2000 579 $2.00
Minimum Mechanical Permit 02/11/2000 579 $.00
Mechanical Administrative Fee 02/11/2000 579 $2.36
Less than 100,000 BTU 02/11/2000 579 8 $48.00
Evaporative Cooler/Fan 02/11/2000 579 4 . $18.00
Miscellaneous Mechanical', 02/11/2000 579 11 $10.50
Mechanical Issuance 02/11/2000 579 $10.00
State Surcharge For Mechanical Permit 02/11/2000 579 $5.50
Total Mechanical $96.36
I System Development
Sanitary Sewer 02/11/2000 579 25 $1,206.75
MWMC Administrative Fee- 02/11/2000 579 1 $10.00
SDC Administrative Fee 02/11/2000 579 $598.57
Property Annexed 1979 or Before 02/11/2000 579 135 $-601 .44
Medical Office - Vetinarian Services 02/11/2000 579 5 $1,649.09
Medical Office - Transportation 02/11/2000 579 5 $9,707.02
Total System Development $12,569.99
, Grand Total $15,444.49
By signature, I state and agree, that I have carefully examined the completed application and do
hereby certify that all information hereon is true and correct, and I further certify that any and all work
performed shall be done in accordance with the Ordinances of the City of Springfield and the Laws of
the State of Oregon pertaining to the work described herein, and that NO OCCUPANCY will be made
of any structure without permission of the Community Services Division, Building Safety. I further
certify that only contracto~s and employees who are in 'compliance with ORS 701.055 will be used on
this project.
I further agree to ensure that all required inspections are requested at the proper time, that each ,
,address is readable from the street, that-the permit card is located at the front of the property, and the
approved set of plans will remain on the site at all times during construction.
--r;::: ~~. ' Z ' /J '00
Signature .>v Date