HomeMy WebLinkAboutPermit Building 2000-2-29
i_
Job# 99-01568-01
,
Page 1 of 3
TRANS#:01-0000764
DATE:FEB 29 2000
AMT RECD:2 $ 39.60
CHANGE:
CASHIER: 003
COMMERCIAL PERMIT
City Of Springfield
Community Services Division
Building Safety
Job Number: 99-01568-01
225 North Fifth Street
Springfield, OR 97477
Office: 726-3759
Inspection Line: 726-3769
Location Of Proposed Site: 860 Beltline Rd Spr
Assessors Map#: 17031500
Lot: Block: ' Addition:
Tax Lot #: 02400
Subdivision:
Owner: Advance Imaging Center
Address: 1200 Hilyard Street
Scope Of Work: Office
Phone Number: 541-687-7134
City/State/Zip: Eugene, OR
New Value: $398,000
Tenant Improvement
Contractor Type
General Contr
Contractor
Dorman Construction Inc
32986 Roberts Ct, Coburg, OR
97408-9495
L.A Kersh
X,X,X
Electrical Contr Jb Electric Inc 104929
4065 West 11 th Avenue, #18, Eugene,
OR 97402
Registration # Expiration Date
68801 8/31/2000
Phone
541-984-0012
Designer
3/14/2000
541-687 -5770
Mechanical Contr Atr Air Inc 121444
3762 W 11th Ave #250, Eugene, OR
97402
Plumbing Contr Harvey & Price Co 77
Po Box 1910, Eugene, OR 97440-1910
3/26/2001
541-935-5414
10/31/2000
541-746-1621
Quad Area:
# Of Units:
Constr. Type:
Water Heater:
Office Use
Land Use:
Zoning Code:
Bedrooms:
Range:
# Of Buildings:
Occupancy Group:
Heat Source:
Sq. Footage:
To request an inspection call the 24 hour recording at 726-3769. All inspections requested before 7:00 '
a.m. will be made the same working day, inspections requested after 7:00 a.m. will be made the following
working day.
Framing
Drywall
Ceiling Grid
SUB - Final
Required Inspections
Building I'
- Prior to cover.
- Prior to taping.
Construction Types:
Occupancy Groups:
# Of Buildings:
# Of Bedrooms:
Handicap Access? D
-Area (Sq. Feet)
Main: Accessory:
~
Final Fire
Final Building
Underground Electrical
Rough Electrical
Electrical Service
Low Voltage
Final Electrical
Underground Plumbing
Underfloor Plumbing
Rough Plumbing
Backflow Device
Final Plumbing
Rough Gas
Rough Mechanical
SUB - Mechanical
Final Gas
Final Mechanical
Fee
Plan Check Fee
Total Transfered Records
Additional Plan Check
Total Plan Check
I Job# 99-01568-01 I Page 2 of 3
Required Inspections
I Building I
-When all Fire Department requirements have been met.
-When all required inspections have been approved and the building is complete.
Electrical
- Prior to cover.
- Prior to cover.
-Must be approved to obtain permanent power.
- When all electrical work is complete.
I Plumbing
-Prior to filling the trench.
- Prior to insulation or decking,
- Prior to cover.
-After device is installed but before backfilling trench.
-When all plumbing work is complete.
I Mechanical I
-After line is installed and capped if not attached to an appliance.
- Prior to cover.
- Following City Rough Mechanical inspection approval and prior to cover.
- When all gas work is complete.
- When all mechanical work is complete.
# Of Stories:
Current Units:
Census Code: Does not apply
Height (feet):
Proposed Units:
Total:
Paid On Receipt#
Transfered Records
11/16/1999 36199
Value/Quantity
457
Plan Check
02/11/2000 579
260
Building Permit
State Surcharge For Building Permit
Building Administrative Fee
Total Building
Building
02/11/2000 579
02/11/2000 579
02/11/2000 579
398,000
Electrical
02/11/2000 579
02/11/2000 579
02/11/2000 579
02/29/2000
02/11/2000 579
Permanent: 200 Amps or Less
Permanent: 401 to 600 Amps
Branch Circuits With Feeder or Service
Restricted Energy
State Surcharge For Electrical Permit
5
1
135
1
Fee Amount
$456.95
$456.95
$260,33
$260.33
$1,103.50
$77.25
$33.11
$1,213.86
$250.00
$100.00
$270.00
$36.00
$43.40
By signature, I state and agree, that I have carefully examined the completed application and do
hereby certify that all information hereon is true and correct, and I further certify that any and all work
performed shall be done in accordance with the Ordinances of the City of Springfield and the Laws of
, the State of Oregon pertaining to the work described herein, and that NO OCCUPANCY will be made
of any structure without permission of the Community Services Division, Building Safety. I further
certify that only contractors and employees who are in compliance with ORS 701.055 will be used on
this project.
I further agree to ensure that all required inspections are requested at the proper time, that each
address is readable from the street, that the permit card is located at the front of the property, and the
approved set of plans will remain on the site at all times during construction.
Signature
Date