HomeMy WebLinkAboutPermit Building 2004-3-8
.
. CITY OF SPRINGFIELD
Building/Combination Permit
PERMIT NO: COM2004-0020I
ISSUED: 03/08/2004
APPLIED: 02/19/2004
EXPIRES: 10/08/2004
VALUE: $ 161,766.00
Status
Issued
225 Fifth Street, Springfield, OR
541-726-3753 Phone
541-726-3676 Fax
541-726-3769 Inspection Line
SITE ADDRESS: 4044 S Redwood Dr
ASSESSOR'S PARCEL NO.: 1802061110400
Springfield TYPE OF WORK: Single Family Residence
TYPE OF USE:
New
Residential
PROJECT DESCRIPTION: SFR-Iot 5 shady creek
Owner: BRUCE WIECHERT
Address: 3375 PARK HILLS EUGENE OR 97405
Phone Number: 541-686-9458
Contractor Type
General
Electrical
Mechanical
Plumbing
Contractor
BRUCE WIECHERT CUSTOM HOMES INC
L & E ELECTRIC INc
COMFORT FLOW
STEVE R JOHNSON
ATTENTION:Oregon law reqUires you Iv
follow rules adoptea oy me 1.", \::\ju.. U\lII\Y
I CONTRACTOR INFORM.An~I'!l,tlm Center. Those rules are set for'
n OAR 952-001-0010 through OAR 952-0C
M~!tJ!S~ou rT~pjrl!!I9,n:I)"~~3 oPhllneJles
10l(?"'~ing the ce!!?tW~QQJie: the Ml:~8~..9.4$8
lq~e7tiber for theO~~9(t!!9.4Utility M!t:!~k~~_5~
460 r~"'",, 0~/~7/~00~~<1?_::>::5MT?26-0100
65065 03/12/2004 541-342-3765
BUILDING INFORMATION'
3
# of Stories: 1
Height of Structure 24.00
Type of Heat: Forced Air Gas
Water Type: Gas
Range Type: Electric
Energy Path: Path 1
Lot Size:
Sq Ft I st Floor:
Sq Ft 2nd Floor:
Sq Ft Basement:
Sq Ft Garage/Carport
Sq Ft Other:
Impervious Surface Area:
5,915
1,635
# of Units:
Primary Occupancy Group:
Secondary Occupancy Group:
Primary Construction Type
Secondary Construction Type:
# of Bedrooms:
1
R-3
U-I
VN
440
Front yard Setback:
Side 1 Setback:
Side 2 Setback:
Rearyard Sethack:
Solar Setbacks:
18.00
8.00
5.00
22.00
30.00
NnTII'I=.
I DEVELOPMENT HSROm.N'ElWfilIALL EXPIRE IF THE WOBl<
AU I HUHllED UNDER THIS PER~PfSI~1J'r' PARKING
Overlay Dist~OMMENCED OR IS ABANDONfJI9tlil3R 2
# Street Tre~R~ctl80 DAY PERIOD.2 Handicapped:
Paved Drive Rqd: Yes Compact:
% of Lot Coverage: 35.20
SETBACKS
I PUBLIC IMPROVEMENTS I
Street Improvements:
Storm Sewer Available:
Special Instruction:
Fully Improved
Yes
Sidewalk Type:
DownspoutslDrains:
Curhside 5'
Curb and Gutter
Notes:
Paee 1 of4
Status
Issued
225 Fifth Street, Springfield, OR
541-726-3753 Phone
541-726-3676 Fax
541-726-3769 Inspection Line
Description
Type of Construction
V Wood Frame
Garaee
Dwellines
Garaee
Fee Description
Plan Review Residential
-Mechanical Issuance Fee-
+ 10% Administrative Fee
+ 7% State Surcharge
2 Baths One or Two Family
Addressing Assignment
Building Permit
Curbcut - Overwidth Appl
Curbcut Permit
Dryer V cnt
Exhaust Hoods
Furnace - up to 100,000 btu
Gas Fireplace
Gas Outlets 1-4
Heat Pump
Plan Review - Planning
PW Mult Disc - 2nd Permit
Residence Wiring 1000 Sq Ft
Residence Wiring Ea Addt1 500
Sanitary Sewer - Improvement
Sanitary Sewer - Reimbursement
SDc MWMC Administration
SDc MWMC Improvement
SDC MWMC Reimbursement
SDC Sanitary/Storm Admin
SDc Transpo Admin
SDc Transpo Improvement
SDc Transpo Reimbursement
Sidewalk Permit
Storm Drainage Impervious Area
Temp Power 200 amps or less
Vent Fan
Wmama1ane Single Family
Total Amount Paid
.
I Valuation Descrintion I
$ Per Sq Ft
or multiplier
$92.40
$24.30
Square Footage
or Bid Amount
1,635.00
440.00
Total Value of Project
Fppt tiJiIJ
Amount Paid
$498.65
$10.00
$129.12
$90.38
$254.00
$31.00
$767.15
$35.00
$75.00
$6.00
$9.00
$12.00
$15.00
$4.00
$12.00
$71.00
$-30.00
$106.00
$38.00
$344.20
$452.80
$10.00
$214.23
$314.63
$1l0.29
$53.41
$727.42
$164.89
$75.00
$1,045.74
$50.00
$18.00
$1,000.00
$6,713.91
Date Paid
2/19/04
3/8/04
3/8/04
3/8/04
3/8/04
3/8/04
3/8/04
3/8/04
3/8/04
3/8/04
3/8/04
3/8/04
3/8/04
3/8/04
3/8/04
3/8/04
3/8/04
3/8/04
3/8/04
3/8/04
3/8/04
3/8/04
3/8/04
3/8/04
3/8/04
3/8/04
3/8/04
3/8/04
3/8/04
3/8/04
3/8/04
3/8/04
3/8/04
Paee 2 of 4
. CITY OF SPRINGFIELD
Building/Combination Permit
PERMIT NO: COM2004-00201
ISSUED: 03/08/2004
APPLIED: 02/19/2004
EXPIRES: 10/08/2004
VALUE: $ 161,766.00
Value
Date Calculated
$151,074.00
$10,692.00
$161,766.00
02119/2004
02119/2004
Receipt Numbcr
2200400000000000160
1200400000000000285
1200400000000000285
1200400000000000285
1200400000000000285
1200400000000000285
1200400000000000285
1200400000000000285
1200400000000000285
1200400000000000285
1200400000000000285
1200400000000000285
1200400000000000285
1200400000000000285
1200400000000000285
1200400000000000285
1200400000000000285
1200400000000000285
1200400000000000285
1200400000000000285
1200400000000000285
1200400000000000285
1200400000000000285
1200400000000000285
1200400000000000285
1200400000000000285
1200400000000000285
1200400000000000285
1200400000000000285
1200400000000000285
1200400000000000285
1200400000000000285
1200400000000000285
.
. \...111" OF ~YKll'\iuNJ!.,L1J
Building/Combination Permit
PERMIT NO: COM2004-00201
ISSUED: 03/0812004
APPLIED: 02/19/2004
EXPIRES: 10/08/2004
VALUE: $ 161,766.00
Issued
225 Fifth Street, Springfield, OR
541-726-3753 Phone
541-726-3676 Fax
541-726-3769 Inspection Line
I Plan Reviews I
Initial Review 02/1912004 02/19/2004 APP RJB
Plan nine Review 02/19/2004 03/03/2004 APP TAJ
Public Works Review 02/19/2004 02/21/2004 APP VRJ Applicant has submitted for an
overwidlh driveway 2/21/04, PW's is
waiting for approval from Traffic.
Public Works Review 02/23/2004 02/23/2004 APP VRJ 30' driveway throat approved
2/23/04.
Structural Review 02/19/2004 03/01/2004 APP RJB
To Request an inspection call the 24 hour recording at 726-3769. All inspection requested before 7:00 a.m.
will be made the same working day, inspections requested after 7:00 a.m. will be made the following work
day.
I Rpnnirptl Tn~nprti'lli.l
2 Sidewalk - Setback: After forms are erected hut prior to placement of concrete.
1 Curbcut - Overwidth: After forms are erected but prior to placement of concrete.
27 Final Mechanical: When all mechanical work is complete.
28 Final Gas: When all gas work is complete.
29 Rough Electric: Prior to Cover
30 Electric Service: Approval required prior to utility company energizing service.
31 Final Electric: When all electrical work is complete:
3 Erosion/Grading Inspection: After all erosion measures are in place.
4 Ufer Electrical Ground: Install ground rod at footing and call for inspection in conjunction with footing and/or
foundation inspection.
5 Footing: After trenches are excavated.
6 Foundation: After forms are erected but prior to concrete placement.
7 Post and Beam: Prior to tloor insulation or decking.
8 Floor Insulation: Prior to decking.
9 Shear Wall Nailing: Before covering sheathing with finish materials.
10 Framing Inspection: Prior to cover and after all rough in inspections have been approved.
11 Wall Insulation: Prior to cover.
12 Ceiling Insulation: Prior to cover.
13 Drywall: Prior to taping.
14 Hold Downs Installed: Specia11nspection performed prior to placement of concrete. Provide report to City
Building Inspector.
15 Undertloor Plumbing: Prior to insulation or decking.
16 Undertloor Drain: Prior to cover or placement of concrete.
17 Rough Plumbing: Prior to cover and including required testing.
18 Water Line: Prior to filling trench and including required testing.
19 Sanitary Sewer Line: Prior to filling trench and including required testing.
20 Storm Sewer Line: Prior to filling trench.
21 Final Plumbing: When all plumbing work is complete.
22 Undertloor Mechanical. Prior to insulation or decking and including required testing.
23 Undertloor Gas: After line is installed and required testing and capped if not attached to an appliance.
24 Rough Gas: After line is installed and required testing and capped if not attached to an appliance.
Paee30f4
.
. CITY OF SPRINGFIELD
Building/Combination Permit
PERMIT NO: COM2004-00201
ISSUED: 03/08/2004
APPLIED: 02/1912004
EXPIRES: 10/08/2004
VALUE: $ 161,766.00
Status
Issued
225 Fifth Street, Springfield, OR
541-726-3753 Phone
54]-726-3676 Fax
541-726-3769 Inspection Line
25 Gas Service: After line is installed and line has been connected to a minimum of one appliance including required
testing. Presure test done at this point.
26 Rough Mechanical: Prior to Cover
By signature, I state and agree, that I have carefully examined the completed application and do hereby certify that all
information hcreon is true and correct, and 1 further certify that any and all work performed shall be done in accordance with
the Ordinances of the City of Springfield and the Laws of the State of Oregon pertaining to the work described hercin, and
that NO OCCUPANCY will be made of any structure without permission of the Community Services Division, Building Safety.
I further certify that only contractors and employees who are in compliance with ORS 701.005 will be used on this project.
I further agree to ensure that all required inspections are requested at the proper time, that each address is readable from the
street, that the permit card is located at the front of the property, and the approved set of plans will remain on the site at all
times during construction.
~~
/:. - j'
Owner or Contractors Signature
-------
5/8~7"
Date
Pa2e40f4