HomeMy WebLinkAboutPermit Building 2002-5-10
Job# 02-00350-01
Page 1 of 5
225 Fifth Street
Springfield, OR 97477
RESIDENTIAL PERMIT
City Of Springfield
Community Services Division
Building Safety
Job Number: 02-00350-01
Office: 726-3759
Inspection Line: 726-3769
Location Of Proposed Site: 6719 Aaron Ln Spr
Assessors Map#: 17023411
Lot: 98 Block: Addition: 2nd
Owner:
Address:
Tax Lot #: 13200
Subdivision: Levi Landing
Tom Wirfs Enterprises Inc
Po Box 237
Phone Number: 541-747-8704
City/State/Zip: Springfield, OR 97477
New Value: $164,389
Scope Of Work: Single Family Residence
SFR same as 6695 Jacob Lane with bonus room finished
Contractor Type Contractor Registration # Expiration Date Phone
General Contr Tom Wirfs Enterprises Inc 32947 6/28/2004 541-747-8704
Po Box 237, Springfield, OR 97477
Electrical Contr Bills Electric 21351 4/28/2002 541-687-1851
3170 West 11th Street, Eugene, OR
Mechanical Contr Home Comfort Heating & Air Conditioning 184164 6/25/2003 541-345-2838
Po Box 24205, Eugene, OR 97402
Plumbing Contr Home Comfort Heating & Air Conditioning 184164 6/25/2003 541-345-2838
Po Box 24205, Eugene, OR 97402
Quad Area:
# Of Units:
Constr. Type:
Water Heater:
4RNE
1
(VN) Wood Frame
Gas
Office Use
Land Use: Single Family Dwelling
Zoning Code: LDR
Bedrooms: 3
Range: Gas
# Of Buildings: 1
Occupancy Group: Dwelling
Heat Source: Forced Air Gas
Sq. Footage: 2088
To request an inspection call the 24 hour recording at 726-3769. All inspections requested before 7:00
a.m. will be made the same working day, inspections requested after 7:00 a.m. will be made the following
working day.
Site
Verify Ground Rod
Footing
Foundation
Post and Beam
Floor Insulation
Ceiling Insulation
Shear Wall Nailing
Framing
Required Inspections
I Building I
- To be made after excavation but prior to setting forms.
-Install ground rod at footing, and call for inspection in conjuction with footing and/or foundation ir
-After trenches are excavated.
-After forms are erected but prior to concrete placement. '
- Prior to floor insulation or decking.
- Prior to decking.
- Prior to cover.
- Before covering sheathing with finish materials.
- Prior to cover.
Wall Insulation
Drywall
Final Building
Temporary Power
Verify Ground Rod
Rough Electrical
Electrical Service
Final Electrical
Underfloor Plumbing
Underfloor Drain
Rough Plumbing
Water Line
Sanitary Sewer Line
Storm Sewer Line
Final Plumbing
Underfloor Mechanical
Rough Gas
Rough Mechanical
Gas Service
Final Gas
Final Mechanical
SW-Curbside
CC-Standard
Street Improvement:
Curb Cut?~
San Sewer Depth (Ft):
Storm Sewer Available?
Special Req.:
Security Required:
Bond Begin DateTime:
Special Instructions:
Other Utilities:
Project Supervisor:
Job# 02-00350-01
Required Inspections
Buildin~
Page 2 of 5
- Prior to Cover
- Prior to taping.
- When all required inspections have been approved and the building is complete.
I Electrical I
-Approval required prior to SUB energizing pole.
,-Install ground rod at footing, and call for inspection in conjuction with footing andlor foundation ir
- Prior to cover.
-Must be approved to obtain permanent power.
- When all electrical work is complete.
I Plumbing
-Prior to insulation or decking.
- Prior to cover or placement of concrete.
- Prior to cover.
-Prior to filling trench.
- Prior to filling trench.
- Prior to filling trench.
-When all plumbing work is complete.
I Mechanical
- Prior to insulation or decking'.
~After line is installed and capped if not attached to an appliance.
- Prior to cover.
-After line is installed and line has been connected to a minimum of one appliance. Pressure tes
-When all gas work is complete.
-When all mechanical work is complete.
I Public Works J
-After forms are erected but prior to placement of concrete
-After forms are erected but prior to placement of concrete
Fully Improved
Improvement Agr.?D
6 4
D
Sidewalk Type:
Additional ROW?
Size Of Line (in):
DownspoutslDrains:
Enchroachment Permit:
San Sewer Tee (in):
Bond End DateTime:
0010010000 00:00:00 '
Curbside - 5'
D
8
To Curb and Gutter
4
0010010000 00:00:00 .
Types Of Warning Devices Reqd.
Job# 02-00350-01
Zoning: LDR
FloodPlain? 0 Wetlands? 0
Journal numbers
1: 1997-06-0142 2: 2002-03-0093 3:
Comments:City Engineer determined floodplain - FEMA Elevation Cert. Require(
Overlay District: Floodplain Overlay
# of Street Trees: 2
Page 3 of 5
Land Use: Single Family Dwelling
Pave Driveway? 0 '
Additional Requirements: LDAP Required
Glenwood Area? 0 Required Attachments:
Source Locn:
Material:
Planner:
Urban Growth Boundary?D
Quantity Of Fill:
Supplier:
Drainage:
Floodway FEMA: See Above
Construction Types:(VN) Wood Frame
Occupancy Groups: Dwelling
# Of Buildings: 1
# Of Bedrooms: 3
Handicap Access? 0
-Area (Sq. Feet)
Main: 2088 Accessory:440
Fee
Same As Plan Review
Hourly Plan Review
Total Plan Check
Building Permit
State Surcharge For Building Permit
8% Building Administrative Fee
Total Building
Minimum Electrical Permit Fee
Wiring Footage 1,000 Sq Ft or Less
Wiring Footage Each Add'l 500 Sq Ft
Temporary: 200 Amps or Less
State Surcharge - Electrical
8% Admin Fee - Electrical
Total Electrical
Minimum Plumbing Permit Fee
Two Bathrooms
State Surcharge - Plumbing
8% Administrative Fee - Plumbing
Total Plumbing
Hood and Exhaust
One to Four Outlets
Minimum Mechanical Permit
8% Administrative Fee - Mechanical
Less than 100,000 BTU
Flood Plain FEMA:
Private Garage/Carp/Stor
# Of Stories: 2 Height (feet): 23
Current Units: Proposed Units:1
Census Code: New SF - detached
Total:2528
Paid On Receipt#
Plan Check
03/28/2002 8434
05/10/2002 8962
Building
05/10/2002 8962
05/10/2002 8962
05/10/2002 8962
Electrical
05/10/2002 8962
05/10/2002 8962
05/10/2002 8962
05/10/2002 8962
05/10/2002 8962
05/10/2002 8962
Plumbing
05/10/2002 8962
05/10/2002 8962
05/10/2002 8962
05/10/2002 8962
Mechanical
05/10/2002 8962
05/10/2002 8962
05/10/2002 8962
05/10/2002 8962
05/10/2002 8962
Value/Quantity
Fee Amount
1
5
$100,00
$202.50
$302.50
164,389
$776.90
$54.38
$62.15
$893.43
1
4
1
$.00
$106.00
$76.00
$50.00
$16,24
$18.56
$266.80
$.00
$254.00
$17.78
$20.32
$292.10
1
1
$9,00
$4.00
$.00
$5.36
$12.00
Fee
Vent Fan to One Duct
ApplianceVent (Not Covered in Schedule
Gas Fireplace
Dryer Vent
Mechanical Issuance
State Surcharge - Mechanical
Total Mechanical
New Sidewalk
New Curbcut
Multiple Permit Discount - 2nd Permit
Total Public Works
Residential - Single Family - Storm
Residential Improvement MWMC
MWMC Administrative Fee
SDC Administrative Fee
Residential Sanitary MWMC
Residential - Improvement
Residential - Reimbursement
Sanitary Sewer SDC Reimbursement
Sanitary Sewer SDC Improvement
Total System Development
S.F. Residence - Willamalane
Total Willamalane SDC
,
Planning Plan Review
Total Planning
Address Assignment
Total Permits w/o Srchg
Grand Total
Plan Check Type
Checked By
Initial Review-Res
Lisa Hopper
Bob Kettwig
Liz Miller
Engineering-Res
Planning-Res
Structural-Res
Don Moore
job# 02-00350-01
Paid On Receipt#
Mechanical
05/10/2002 8962
05/10/2002 8962
05/10/2002 8962
05/10/2002 8962
05/10/2002 8962
05/10/2002 8962
Public Works
05/10/2002 8962
05/10/2002 8962
05/10/2002 8962
, , I System Development
05/10/2002 8962
05/10/2002 ,,8962
05/10/2002 8962
05/10/2002 ' 8962
05/10/2002 8962
05/10/2002 8962
05/10/2002 8962
05/10/2002 8962
05/10/2002 8962
Willamalane SDC I
05/10/2002 8962
Planning
05/10/2002 8962
Permits w/o Srchg
05/10/2002 8962
Date Completed
Comment
04/02/2002
04/10/2002
04/07/2002
Page 4 of 5
Value/Quantity Fee Amount
3 $18.00
1 $9.00
1 $9.00
1 $6.00
$10.00
$4.69
$87.05
50 $75.00
1 $75.00
1 $-30.00
$120.00
3,666 '$1,000.68
1 $34.83
1 $10.00
, $149.15
1 $332.86
1 $659.76
1 $155.13
21 $448.77
21 $341.04
$3,132.22
1 $1,000.00
$1,000.00
1 $55.00
$55.00
1 $8.00
$8.00
$6,157.10
Needs to pick up LDAP. FEMA Elevation Cert.
Required.
04/17/2002
Job# 02-00350-01 Page 5 of 5
By signature, I state and agree, that I have carefully examined the completed application and do
hereby certify that all information hereon is true and correct, and I further certify that any and all work
performed shall be done in accordance with the Ordinances of the City bf Springfield and the Laws of
the State of Oregon pertaining to the work described herein, and that NO OCCUPANCY will be made
of any structure without permission of the Community Services Division, Building Safety. I further
certify that only contractors and employees who are in compliance with ORS 701.055 will be used on
this project.
I further agree to ensure that all required inspections are requested at the proper time, that each
address is readable from the street, that the permit card is located at the front of the property, and the
approved set of plans will remain on the site at all times during construction.
Signature
Date