HomeMy WebLinkAboutCorrespondence ENG 6/20/2007
.
.
Goebel Engineering & Surveying, Inc.
Engineering Surveying Planning
310 Garfield Street Eugene, Oregon 97402
Phone: (541) 687-0542 Fax: (541) 687-0739 E-mail: ooebel(1ilooebeleno.com
20 June 2007
Via Facsimile 726-3689
(Hard copy to be delivered today)
Mr. James Donovan
City of Springfield
225 Fifth Street
Springfield, OR 97477
Re: Legacy Estates Subdivision
City No. SUB2005-00047
GES No. 02414-2004-C
Dear Jim:
Pursuant my telephone conversations today with Jon Driscoll, I hereby request (on behalf of my
client, David Corey) that you grant a 30-day extension to the 180-day time line.
It is our intent to submit the Final Plat Mylars and associated paper copies before the cutTent
deadline of 4 July 2007. The monumentation of the rear lot pins on Lots 3-14 were delayed due
to lot fill. Additionally, the project has been delayed due to the city's issuance of construction
permits on the sanitary pump station. The applicant/developer (David Corey) was unable to
purchase the property until these issues had been resolved (per his agreement with the owner),
causing further delays.
SJG/ms
cc: David Corey, 338-337
Although we intend to submit the Final Plat Application packet next week, before the deadline, \ (\
we are requesting this extension to allow for any unforseen delays. \6' 0
Please call if you have questions or require additional information. \\) . ~ \-" ~ C\\
~ J k'~ VI r'" S IN'1I/t:.
Gr'-x> M 'V'^'~JJlc/')Y V
I gO '!P 'J tw' \
tJv pJ "
~{)1j rPV 'II ~
~.~~d\~\D;
v~
~~tl 1
0~~~\?\,1
Sincerely,
d:;~oJ1!is.
M:\CHentsIA - C\COHW\1 ACT1VE\Legf-Jcy EstatHs (0.: ~1\Lelters~D()novan. Time Exl itrOd-20n-'.;prj
06/21/07 THU 14:06 FAX 5417263689
CITY OF SPRINGFIELD
19J00l
.
*********************
..* TX REPORT *.*
*********************
.
,
, \..
TRANSMISSION OK
TX/RX NO
CONNECTION TEL
CONNECTION ID
ST. TIME
USAGE T
PGS. SENT
RESULT
4662
915416870739
GOEBEL ENGINEERI
06/21 14: 06
00'33
1
OK
Goebel Engineering & Surveying, In4:.
Engineering Surveying . Planning
310 Garfield Streel Eugene, Oregon :97402
Phone: (541) 667-0542 Fax: (541) 687-0739 E-mail: coebell!llcoebelenq.com
20 Jun.e 2007
Via Facsimile 726-3689
(Hard copy to be delivered today)
.____'___n....'. . -.. .,-",,--.-', ,_. -'. _....-
I
,
I
.. +-
Mr. James Donovan
City of Springfield
225 Fifth Street
Springfield, OR 97477
~
~L<J"< 01
[plY
.1
Re: Legacy Estates Subdivision
City No. SUB200S-00047
GES No. 02414-2004-C
Dear Jim:
Pursuant my telephone conversations today with Jon Driscoll, I hereby request (on ~ehalf of my
client, David Corey) that you grant a 3D-day extension 10 the ISO-day time line. ;
It is 01l1" intent to sUbmit the Final Plat Mylars and associated paper copies before the cunent
deadl~e of 4 July 200i The monumentation of.the rear lot pins on Lots 3-14 wen~ delayed due
to lot flU. Additionally, the project has been delayed due to the city's iSSllallce of cpnstnJction
permits on the sanitary pump station. The applicantJdeveloper (David Corey) was unable to
purchase the property until these issues had been resolved (per his agreem.ent "\>.lith the oVl!ler),
. I
causing further delays. !
: . !
08/30/07 THU 09:11 FAX 5417263689
CITY OF SPRINGFIELD
~001
.
*********************
... TX REPORT ...
*********************
.
.
.
, ~,
TRANSMISSION OK
TX/RX NO
CONNECTION TEL
CONNECTION ID
ST. TIME
USAGE T
PGS. SENT
RESULT
4885
915416870739
GOEBEL ENGINEER I
08/30 09:10
00'34
1
OK
Goebel Engineering & Surveying, Inl~.
Engineering Surveying Planning
310 Gar1ield Street Eugene, Oregon 97402
Phone: (541) 687-0542 Fax; (541) 687-0739 E-mail: ooebel@ooebeleno.com
20 June 2007
, Via Facsimile 726-3689
(Hard copy to be delivered today)
Mr. James Donovan
City of Springfield
225 Fifth Street
Springfield, OR 97477
Re: Legacy Estates Subdivision
City No. SUB2005-00047
GES No. 02414-2004-C
~'
~y
Dc:ar Jim:
Pursuant my telephone conversations today with Jon Driscoll, r hereby request (on behalf of my
client, David Corey) that you grant a 3D-day extension to the l80-day time line,
It is our intent to submit the Final Plat Mylars and associated paper copies before the current
deadline of4 July 2007, The momunentation of the rear lot pins on Lots 3-14 were delayed due'
to lot fill. Additionally, the project has been delayed due to the city's issuance of constntction
permits on the sanitarY pump station. The applicant/developer (David Corey) was unable to
purchase the property until these issues had been resolved (per his agreement with the o\'mer),
causing further delays. .