August 13, 2010
Mr. Bryan Richardson
Electrical Inspector
Springfield Community Services Division
City of Springfield
225 Fifth Street
Springfield OR 97477
SUBJECT:
Hilton Garden Inn - Electrical Drawings Supplemental Information
Dear Mr. Richardson:.
Please incorporate the following revisions, additions, and/or clarifications to the plan set dated 4
August 2010.
1. Panels "2A", "2B", "3A", and "3B" are to be located in the south east wing, not the
north end room as indicated.
2. Panel "1 P" is to be located in the Electrical Room, adjacent to Panel "1 H".
3. The feeder from the generator and the MDP Breaker "E" to the transfer switch and
from the transfer switch to Panel "E" is to be (1) 1" c., (3) #3 XHHW Cu., (1) #8
XHHW Cu. ground.
4. The ground conductor is to be removed from Feeder #1, per NEC 250. 142-(A)(1).
We hope this is of assistance to you in resolving this issue. If you have any questions, please do not
hesitate to call me.
Sincerely,
f~ d WelxA
Patricia J. Weber, PE
Electrical Engineer
10-502 brichardson 08-13-1 a.doc
'. ,-," .,.
,....
'. ','
"' '.,
;. ':.,
," ;.
,.,,'