LAND DIVISION PLAT
PRE-SUBMITTAL CHECKLIST
Partition
Project Name: Thurston Crossing / Amigos III Partition
Project Proposal: Partition a commercial lot into three parcels
Case Number: PRE2009-00001
Project Address: 5815 A Street
Assessors Map and Tax Lot Number(s): 17-02-34A2, TL 202
Zoning: General Office (GO)
Overlay District(s): Drinking Water Protection (DWP)
Applicable Refinement Plan:
Refinement Plan Designation:
Metro Plan Designation: Commercial
Tentative Decision Date: March 18, 2008
Pre-Submittal Meeting Date: January 13, 2009
Application Submittal Deadline: July 12, 2009
Associated Applications: SUB2008-00007
-.Cl:;f;:t-'()filse;JUI'iI.~~XE~,DE-V;ELOJ>>Ji"'1'ENJr'J{l:~i[EW'Tl:1lM .. .,--.g., ;>N!:1~Ej.:';!;;"..':.':':1:;;rr:';;1tl:2', ':<<0,y:t/~:. ..~\,,,. .
';.;.;\e> ,....... >'T;~."
POSITION REVIEW OF NAME PHONE
Project Planner Land Use Planninq Andy Limbird 726-3784
Transportation EIT Transportation Jon Driscoll 726-3679
Public Works Engineer in Traininq Util ities Richard Perry 744-4155
Public Works Enqineer in Traininq Sanitary & Storm Sewer Richard Perrv 744-4155.
Deputy Fire Marshal Fire and Life Safety Gilbert Gordon 726-2293
Communitv Services Manaqer Buildinq Dave Puent 726-3668
;Ae;pILXC~N~~Si'QEN1.EL~e;MENT::iiR-E)'n:EW'tE~M"'i'..-;1;;!!';'-.>1". ;...'-.;;;1,.;.... .....f:..7Ij;-q..p;. .....
Engineer Applicant
Renee Clough Roger Langeliers
Branch Engineering Inc. Amigos III
310 Fifth Street 23021 Brushing Ct.
Sorinqfield, OR 97477 Bend, OR 97701
-
"'T;;,"':
0JtBiiai:
"I
::;;,~'t.
1/13/2009
Dat€l Received: /)3/.:Moj
Planner: AL / /
1 of 6
The items needed to make!e application complete for re!w are incorporated below.
'.
NOTE:
. Conditions of Approval - taken from Notice of Decision dated: 3/18/2008
. Applicant Response - taken from: written statement submitted with application 1/5/2009
Condition #1: Prior to plat approval, Parcels I, 2, and 3 shall be serviced with private
sanitary sewer laterals from the IS-inch sanitary sewer main in the north of the
subject property as depicted on the tentative plan in accordance with SDC 4.3-105 A.
NOTE: Plumbing permits are required to install these private sanitary sewer laterals.
Applicant Response: A copy of the building permit status report is included with this submittal
as evidence of compliance with this condition.
Staff Finding: Pending. These installations were done through an Encroachment Permit and
verification is not provided on the Building Permit status report. Staff will confirm acceptability.
of the sanitary sewer connections with the Public Works inspector prior to final plat.
Condition #2: Prior to plat approval, Parcell shall be serviced with a private
stormwater lateral from the existing stormwater lateral that extends through the
subject property as depicted on the tentative plan in accordance with SDC 4.3-110 B.
NOTE: Plumbing permits are required to install this private stormwater lateral.
Applicant Response: A copy of the building permit status report is included with this submittal
as evidence of compliance with this condition.
Staff Finding: Satisfied.
Condition #3: Prior to plat approval, the applicant shall document on the plat and
record a private stormwater easement over the existing six-inch stormwater lateral
that runs through the north of the subject property and is intended to serve both
Parcels 1 and 2.
Applicant Response: The easement is granted on the plat.
Staff Finding: Satisfied.
Condition #4: Prior to plat approval, the applicant shall verify the location of existing
power lines in A Street, as well as the location of electric facilities that have been
extended to all parcels. In addition, if it does not already exist, electric service shall
be provided to Parcels I, 2, and 3 via the existing private joint utility easement
running north/south in the center of the subject property in accordance with SDC 4.3-
120. Placement of such facilities shall be underground as conditioned in the
Underground Placement of Utilities section below.
Applicant Response: During construction of the other utilities, it was determined that all the
parcels for this partition already have access to 2-]" and ]-2" power conduits that come from a
]-phase power line in 58th Street.
Staff Finding: Not satisfied. SUB Electric advises that the conduit has been installed along
the A Street frontage, but no underground electrical lines have been extended to the three
parcels. Additionally, Parcel 3 is isolated from the electrical system and a utility easement may
be required to extend service to this site.
Co'ndition #S: Prior to plat approval, all required utility lines to serve Parcels I, 2, and
3 shall be installed underground.
1/13/2009
Dat~ f~6ceived:
Planner: AL
if J /,;.ad?
/ /
2of6
"
. .
Applicant Response: During construction of the other utilities, it was determined that all the
parcels for this partition already have access to 1-4" phone conduit, 1-2" cable conduit and 1-4"
gas conduit that come from 58th Street.
Staff Finding: Not satisfied. Although the conduits have been pre-installed, the utility lines
have not been inserted.
Condition #6: Prior to plat approval, the applicant shall verify the location of the
existing water main in A Street, as well as the location of water facilities that have
been extended to all parcels. In addition, if it does not already exist, water service
shall be provided to Parcels 1, 2, and 3 via the existing private joint utility easement
running north/south in the center of the subject property in accordance with SOC 4.3-
130. All water service facilities shall be installed per SUB Water standards. NOTE:
Plumbing permits are required to install private water laterals.
Applicant Response: During preparation of the tentative mapping, SUB provided our office
with a map showing an 8" water main in the PUE on the south side of A Street. A copy of this
map is included in this submittal. Connection to this water main can be made by future
construction on Parcels 1 and 2 without disturbance to private or public facilities; therefore no
connection needs to be made at this time for these parcels. A copy of the building permit status
report is included with this submittal as evidence that Parcel 3 is supplied with a connection to
the water main.
Staff Finding: Not satisfied. The building permit status report does not indicate that water
lines have been installed to serve Parcel 3. SUB Water advises that water lines have .not been
connected to service the subject parcels. Water service to all parcels will be required prior to
final plat.
Condition #7: Prior to plat approval, the applicant shall provide a copy of a new
approved OOOT access permit for the Main Street access.
Applicant Response: A copy of ODOT's conditional approval letter is included with this
submittal.
Staff Finding: Partially satisfied. Although the ODOT access permit has been obtained, it
appears the applicant has not yet complied with the conditions of the permit. Among the
conditions of compliance, the driveway at the south end of Parcel 3 is to be physically restricted
to a right-in/right-out turning movement. However, as present there is no signage, painted
arrows, divider island or similar mechanism to physically restrict the turning movements.
Condition #8: Vision clearance areas shall be maintained at each access to a public
street as per SOC 4.2-130.
Applicant Response: A note with this restriction is included on the plat.
Staff Finding: Satisfied.
,
Heads Up Comments:
1. The existing bioswale at the south edge of Parcel 3 is in poor condition due to neglected
landscaping, accumulated trash, and sediment infiltration. Maintenance and re-planting of
this feature will likely be required to ensure it functions as intended.
2. SUB Electric may require an easement to provide electrical service to the parcels.. There
is an existing transformer at the northeast corner of Parcel 2 that could provide t.':'';l"phase
service. However, depending upon the needs of the site development, an alternate
service location may be required.
1/13/2009
Date Heceived: ,j'J/<Jd1J1
Planner: AL 'I
30f7
THIS APPLICATION IS:
.
.
D COMPLETE FOR PROCESSING
~ INCOMPLETE AND NEEDS MISSING INFORMATION NOTED ABOVE
THIS IS NOT A DECISION ON THE PLAT. The plat pre-submittal meeting shall be held within
one year of the date of the Land Division Tentative approval. A complete Land Division Plat
application shall be submitted within 180 days of the pre-submittal meeting. If the applicant has
not submitted the Land Division Plat application within these time frames, the Land Division
Tentative approval shall become null and void and re-submittal of the Land Division Tentative
application shall be required per SDC 5.2-140.
I, the owner/applicant, intend to submit all missing items indicated herein to the City
within the ISO-day timeline.
;;?;;;;,? 'e~ ()Cj
wnerjApplicant's Sign ture
Date
1/13/2009
Date. Received: //J/~tJf
/ /
Planner: AL
40f6
Land Division Plat APPIi!ion Process (see next page for a d!am of this process)
;
1. Applicant Submits a Land Division Plat Application for Pre-Submittal
. The application must conform to the Land Division Plat Pre-Submittal Requirements
Checklist on pages 5 & 6 of this application packet.
. The purpose of pre-submittal is to ensure the applicant has all items necessary for a
complete submittal.
. A pre-submittal meeting to discuss completeness is mandatory.
. Pre-submittal meetings are conducted every Tuesday and Friday, from 10:00am -
noon.
. We strive to conduct the pre-submittal meetings within five to seven working days of
receiving the application.
2. Applicant and the City Conduct the Pre-Submittal Meeting
. The applicant, owner, and design team are strongly encouraged to attend the pre-
submittal meeting.
. The meeting is held with representatives from Public Works Engineering and
Transportation, Community Services (Building), Fire Marshall's office, and the Planning
Division.
. The meeting is scheduled for 30 to 60 minutes.
. The Planner provides the applicant with a Pre-Submittal Checklist at the end of the
meeting specifying the items required to make the application complete if it is not
already complete.
. The applicant will then have 180 days to make the application complete for submittal
and acceptance by the City.
3. Applicant Submits a Complete Land Division Plat Application
. When the applicant has addressed all items on the Pre-Submittal Checklist and the
City Surveying Section has notified the applicant's surveyor that the plat and other
documents are sufficiently refined, the applicant can submit a complete application to
the City Survey Section located in the NW Quad of City Hall.
. The application must conform to the Land Division Plat Submittal Requirements
Checklist on page 6 of this application packet.
. If the submittal is deemed complete, the City Survey Section will sign-off on the City
Survey approval sheet and send the applicant to the Development Services
Department for application submittal and fee collection.
. Planning staff checks and signs the mylars.
4. Applicant Records Plat at Lane County & Submits Plat and Documents to City
. After Planning staff checks and signs the mylars, the plat may then be recorded by the
applicant's surveyor at Lane County.
. After plat has been recorded at Lane County, applicant submits five (5) recorded,
rolled paper copies of the plat and three (3) copies of required documents to the
Development Services Department prior to the issuance of building permits.
Dat~ Received:
Planner: AL
>/;;/#(11
/
. .
LAND DIVISION PLAT APPLICATION PROCESS
'i
Applicant submits land division plat application for pre-submittal
(See Land Division Plat Pre-Submittal Requirements Checklist)
City departments review application for completeness and hold pre-submittal meeting to
discuss completeness issues with applicant and applicant's representatives.
~ ~
Applicant addresses incomplete items. City Surveyor checks application and returns
comments to applicant's surveyor.
Applicant's surveyor corrects plat City Surveyor conducts field check and
and returns to City Surveyor. returns comments to applicant's surveyor
~ /
Applicant's surveyor sets new monuments
and flags existing ones.
Once no errors appear on the plat and a current title report is submitted, applicant's
surveyor is given ok to submit complete land division plat application.
After ok given from City Surveyor and applicant has addressed all incomplete items from
--- pre-submittal, applicant submits complete application to the City Survey Section
(See Land Division Plat Submittal Requirements Checklist)
City Survey Section signs-off on City Survey approval sheet and sends the applicant to the
Development Services Department for application submittal and fee collection.
Planning staff checks and signs mylars and notifies applicant's surveyor of approval.
I Applicant takes plat and accompanying documents to Lane County for recording.
I Applicant brings copies of recorded plat and documents to Development Services Department.