HomeMy WebLinkAboutRecommendation Sheet PLANNER 9/3/2008
.
.
JUSTICE CENTER SITE PLAN MODIFICATION
DRC2008-00024 - APPROVED MAY 9, 2008
CONDITIONS OF APPROVAL:
1. The Final Site Plan shall accurately depict the locations of all existing and proposed public water
lines serving the development site.
2. The Final Site Plan shall depict the locations of electrical and telecommunication systems connections
required to serve the development area.
3. To ensure a fully functioning water quality system and meet objectives of Springfield's MS4 permit,
the Springfield Development Code and the EDSPM, the vegetative water quality swales shall be fully
vegetated with all vegetation species established prior to issuance of building occupancy.
Alternatively, if this condition cannot be met, the applicant shall provide and maintain additional
interim. erosion control/water quality measures acceptable to the Public Works Department that will
suffice until such time as the swale vegetation becomes fully established.
4. Prior to construction of Pioneer Parkway East improvements, the applicant shall obtain ODOT
permits required for the new driveway entrance and related work in the Pioneer Parkway East right-
of-way.
5. The Final Site Plan shall contain design details acceptable to the City Engineer for the street
intersections affected by the site plan (B Street and 4th Street; and B Street and Pioneer Parkway
East). .
6. The Final Site Plan shall provide for Knox Box keyed gate switches at the east"and west entrance
driveways to the secure parking lot.
7. In accordance with the provisions of SFC 508.5.5 and SFC 912.3, immediate access and at least three
(3) feet of clear space in all directions shall be maintained for all Fire Department connections.
8. Prior to or concurrent with approval of the Final Site Plan, a suitable PUE for the electrical
transmission line running along the northern edge of the site shall be executed and recorded. The
PUE alignment and dimensions shall be satisfactory to SUB Electric.
9. Prior to or concurrent with approval of the Final Site Plan, a suitable PUE for the underground
electrical lines installed to serve the development site shall be executed and recorded. The PUE
alignments and dimensions shall be satisfactory to SUB Electric.
10. Prior to initiation of any tree felling activities on the site, the applicant shall obtain a Tree Felling
Permit pursuant to Planning Action DRC2008-00028. . .
11. The Final Site Plan shall provide for street trees and site landscaping trees that are minimum 2-inch
caliper in accordance with SDC 4.4-I05.E & F.
12. The Final Site Plan shall provide a fencing detail for the metal panel fence around the secure parking
lot. The fence style shall be consistent with provisions of SDC 4.4-1 IO.B.3.b.
13. Light fixtures located within 43 feet of the northern boundary of the site shall be placed no higher
than 12 feet in accordance with SDC 4.5-1 IO.B.2.b.
Date r~eceived:
Planner: AL
91/dmt'
/
.
.
14. The Final Site Plan shall provide a site and building lighting plan that is consistent with provisions of
SDC 4.5-110. All lighting fixtures used on the site shall be shielded and full cut-off lenses to prevent
light trespass onto adjacent properties.
15. The Final Site Plan shall provide a design detail that confirms the parking lot and driveway
configuration will adequately accommodate turning movements for all Springfield Police Department
vehicles expected to use the secure parking lot.