HomeMy WebLinkAboutBuilding Field Test & Inspection Report 2010-1-11
~.
.mjl8lr
No. 400ate
Permit # 09-C8-1082
Inspector mike mackessy_
I . Type of Inspections Performed
~Reinforcing Steel OStructural Steel Fabrication
o Reinforced Concrete 0 Structural Steel Erection
"Dconcrete Forms DExpansion Bolts
OStructural Masonry OGeotech Observations
o Shotcrele 0 Structural Fills
~Epoxy Anchors DSub-grade (footings/slabs)
DFire Proofing DPile Driving
DOtner:
A/4l?nnq Buil~illg~ .tl_o1ef _
Period periodic
No. fi j Date
Permit # 09-CB-1082
Inspector Dave Tilton
Type of Inspections Performed
~Reinforcing Steel DSlructural Steel Fabrication
DReinforced Concrete DStructural Steel Erection
DConcrete Fonns DExpansion Bolts
DStructural Masonry DGeotech Observations
DShotcrete . DStructural Fills
o Epoxy Anchors DSub-grade (footings/slabs)
DFire Proofing DPile Driving
Dathec
A/1fi/?nolt. Building ~ntpl
Period
c~ / (O~ 2--
/
Non-Compliance Report
.
CCI Project #1266-001
Rev Date: 1-11-2010
Covering Issued Daily Field
Report Through #78
Specific Placement Locations
A) Columns@18/A.C, E.25. H; 16/A,.
<5, E.2S; 21/H.'
B) Shearwall @ A-C/23
C) Epoxy@ column N/B.75.
1) 2nd level deck A-H/ll.5-24
2) 2nd level deck A-R/l-ll.5
Page 1 of2
Description of Problem
Observed epoxyofrebarin footing: dO'v\lels,for columns. Epoxy-was HilkHit RE
500 with expo Date 10/09. Work reflects "as-built" condition. Need RFI approved.
Embed depth of 8" into column. Holes were drilled with 5/8" diameter carbide tip
bit in rota hammer and are ANSI approved. Embed on (2) western holes was 8"
and 8-112" on north side 8-1/4" and 8". Holes were cleaned by wire brush and
compressed air. Holes were filled and rebar inserted with a twist. Columns and
shearwall appear complete, in place and have proper clearances and are ready to
close up and pour. Work appears to comply with manufacturers recommendations
(epoxy), approved plans and job specs. except as noted.
Reference Documents:. Epoxy ESR2322, S2.1
1) On site for in progress inspection of reinforcing steel placement for above
noted deck. Contractor placing misc. trim steel and tying tendons. Received copy
of structural observation report by Babrak Amiri dated 9/14/09, including revised
details for column steel hooks and add steel at'elevator for conflict INith
penetrations.
2) It has been determined that the stud rails for the type 2 columns were shipped ~.
in two pieces. At the columns of pour#l (1-11.5 line) only (1) of the pieces was -(-.
installed, so (g) ,rails with (18) studs each is installed. "As-built" condition, is being
reviewed by EaR.
f=~La,r
"!..L_,iiillBI13
/
525 NW Second Strp.€t. CDivnllis,OrRgofl97330
tf 800.383.8055 ph 541.758-13U2 Ix 541.753.2254
www.claircompany.com
Daily Field Report
Date: -1/4/2010 Time Arrived: 930 AM Project # : 1266-1)01 No. : 78
Project Name: Hilton Garden Inn I
Address: 3328 Gateway, Springfield, OR ---1
~~~l~.~..~!!.:,__"_ Hotel I
Permit#: C81082 Client Name: Associated Consultant i
Special Inspection: ~ Period: continuous Weather Conditions: rain 60F --1
Type of Inspections Performed
2J Reinforcing Steel, D Structural Steel Fabrication
~ Reinforced Concrete
o Concrete Forms
D
Equipment
D Structurai Steel Erection
Type Serial Number
_I
Structural Masonr~'
D Shotcrcte
D Epoxy Anchors
o Expansion Bolts
o Geotcch Observations
D Structu'ral Fills
o Sub.grade (footings/slabs)
D Pile Driving
Type of Material:
Supplier
D
D
Fire Proofing
Other:
Mlx#
Specific PlaCement Locations
Light pole bases. Locations (12) marked on landscaping plan.
Siu mplFiow (in.)
Material Temp. (oF)
Ambient Temp. fF)
Time Placed
No. of Samples
Design Strength (PSI)
Total Cubic Yds.
Note:
II
Concrete Grout Mortar
Jl II
II 11
" II
II II
II II
" II
II II
II II
II II
D Previously listed un~orrected Items
D Changes to approved plans andfor specifications by Architect,or Engineer
D Corrections of previously listed items
D Items requiring correction
D Materials.and methods of construction
D Equipment used (i.e. what was used to proof roll or obtain compaction)
FiI'JrJ.Oh~l'rv.ations and'C:omnll'nh
~ Reinforci~g steel w~._c~e_cked in locations listed above, for grade, size, lap, placement and clearances where applicable.
On site-to monitor concrete pour of (12) light polibases/footings to ensure proper placement of anchor bolts and clearance ofrebar cage.
Concrete placed b{tailgating\vith mechanical consolidation. Po~ha1ted after concrete reached three hours since batch time. Temperature of
Wncrete at 67F. within allowable range. or tile (1in~~~i: only(-lO) were poured.
,
Reference Documcn!~: RFI pending per engine~~d d~~~~~~~,! E5Q~> ("'1'
As a mutual protection to clients. the public, aud ourselves, all reports are submitted as confidential property of clienrs and are in fended for the use of aUf dierlts or
No other person or entity may utilize the repon or any portion thereof without our written pennission.
ITO the best afmy kn~wledge, the work inspected was'in accordance with the building department approved design drawings, specifications
and applicable workrpanship provisions of the I.B.C. except as noted:
Inspector Name: Mike Mackcssy
I'
Reviewed by: Dave Tilton
/
l-n;Lalr
.Ii
525 NW Second Street. COlvallis, Orp.gnn 97330
d 800.383.1IlI55 ph 541}51l1302 Ix 541}53.2264
www.cleircompany.com
Daily Field Report
Date:
12/30/2009
Time Arrived: 8:30 AM
Project #: 1266-001
No. :
77
Project Name: Hi,ltoD Garden (nn
Address: 3528 Gateway, Springfield, OR
Building: Hotel
Permit # :
C81082
Client Name: Associated Consultant
Speciallnspectio'n:
~
Period:
Weather Conditions:
rain
Type of Inspections Performed
~ Reinforcing Steel 0 Structural Steel Fabrication
D Reinforced Concrete 0 Structural Steel ErecUon
Equipment
Type
Serial Number
o Concrete Forms
o Structural Masonry
o Shotcrde
o Epoxy Anchors
D Fire Proofing
o Other:
o Expansion Bolts
D Geotech Observations
o Structural Fills
o Sub.grade (rootings/slabs)
o Pile D.-ivlng
II
Specific Placement Locations
"(12) lamp/light pole footings. Locations marked on landscaping plan.
Type of Mate.-ial:
Supplier
Mix#
Slump/Flow (In.)
Concrete
Grout
Mortar
Material Temp. (OF)
Ambient Temp. r'F)
Time Placed
II II
II II
11_...J1
II II
II II
II "
II II
II-.__JI
II II
Note:
No. of Samples
Design Strength (PSI)
Total Cubic Yds.
o Pre,,'Iously listed uncorrected items
o Changes to approved plans and/or specifications by Architect,or Engineer
o Corrections of previously listed items
o Items requiring correction
D Materials and methods of construction
o Equipment used (I.e. what was used to proof roll or obtain compaction)
Fipld Ohsl"n'JJtions and (:omml"nh
~Reinforcing steel was checked in locations listed above, for grade, slze,lap, placement and clearances where applicable.
On site to monitorconcrcte pour of (12) light pole bases/footings to ensure proper placement of anchor bolts and clearance on rehar cage.
Footings are tilled with various levels afrain watef\and pour was cancelled. Footings need to be pumped out and concrete pour re-scheduled.
Reference Documents: RFI pending, engineered detail E502.
As a mutual protection to clients, the public, and ourselves, all repons are submitted as confidential property ofdients and are intended for the use ofourcliellls or
No other person or entity may utilize the report or any portion thereof without our written pennission.
ITa the best of my knowledge, the work inspected was in accordance with the building department approved design drawings, specifications
and applicable workmanship provisions of the I.B.C. ex.cept as noted:
Inspector Name: mike mackessy
Reviewed by: Dave Tilton
D!iL8Ir
/
525 NW Second Street COlvallj~. Oregon 97330
d 800.383.8855 ph 541.758.1302 Ix 541.7S3.2264
www.claircompony.com
Date:
12/29/2009
Time Arrived: 10:00 AM
Daily Field Report
No. :
Project Name: Hilton Garden Inn
Address: 3528 Gateway. Springfield, OR
Building: Hotel
Project # : 1266-001
76
Special Inspection:
Period: periodic
Client Name: Associated Consultant
cold 36F
Permit#:
C81082
~
Type of Inspections Performed
~ Reinforcing Steel 0 Structural Steel Fabrication
o Reinforced Concrete D Structural Steel Erection
o Concrete Forms 0 Expansion Bolts
D Structural Masonry 0 Geotech Observations
D Shotcrete 0 Structural Fills
D Epoxy Anchors 0 Sub-grade (footings/slabs)
D }<"lr1.' Proofing 0 Pile Dri,,'ing
D Other:
Specine Placement Locations
- Light pole bases (12) - marked on landscaping plan
Weather Conditions:
Equipment
Type
Serial Number
IJ
Type of Material: Concrete Grout Mortar
Supplier 'I 'I
Mix # 'I II
SlumpfFlow (in.) IJ "
Material Temp. eF) II II J
Ambient Temp. (OF) II II I
Time Placed II II I
No. of Samples II II I
Design Strength (PSI) II II I
Total Cubic Yds. IJ II I
Note:
o Previously listed uncorrected Items
~ Changes to approv~d plans and/or specifications by Architect,or Engineer
o Corrections of previously listed Items
o Items requiring correction
o Materials and meth~ds of construction
o Equipment used (i.e. what was used to proof roll or obtain compaction)
Field Ohu.rvation.. and Comments
~Reinforcing steel was checked in locations listed abo,,'e, for grade, size, lap, placement and clearances where applicable.
Inspection ofrebar cages in light pole base/footings. As per phoneconversation between engineer and Mitch (Express Concrete), length of
rebar cages at approx. 84" is acceptable. (3) extra ties have been added_~f.?~op ofcages'""ilsper dwg l1E502. Verts (10) #5 with #3 ties@ 12" OC.
24" diameter of so no tube. Anchor bolts to be wet-set." Top th tie to be witliin'3" of top of form. RFI to reflect changes pending and to be
forwarded.
Reference Documents: RFI pendine:. engineered detail E502.
As a mutual protection to climlS. the public. and ourselves, all reports are submitted as confidential property ofclienlS and are intended for the use of our clielllS or
No olherperson or entity may utilize the rcport or any portion thereorwilhoul our written pernlission.
ITO the best of my knowledge, the work inspected was in accordance with thc building department approved design drawings, specifications
and applicable workmanship provisions of the I.B.C. except as notcd:
Inspector Name: mikc mackessy
Reviewed by: Dave Tilton
l-piLa I r
.11
Dale:
12/21/2009
Daily Field Report
Time Arrived: 8:00 AM
Project II: 1266-001
Project Name: Hilton Garden Inn
Address: .~,~;_~g~_t:.~'_~y,_~'p.~_i.~_~_field, OR'
Building: Hotel
Permit#:
C81082
Special Inspection:
Client Name:
Associated Consultant
~
Period:
Weather Conditions:
Type of Inspections Performed
D Reinforcing Steel
o Reinforced Concrete
o Concrete Forms
D Structural Masonry
D Shotcrete
o Epoxy Anchors
o Fire Proofing
o Other: nailing
Specific Placement Locations
5th floor deck nailing
Note:
o Structural Steel Fabrication
o Structural Steel Erection
D Expansion Bolts
o Geotech Observations
o Stl'"uctural Fills
o Sub-grade (footings/slabs)
D Pile Driving
Type
Type of Material:
Supplier
Mix#
Slump/Flow (in.)
Material Temp. (OF)
Ambient Temp. fF)
Time Placed
No. of Samples
Design Strength (PSI)
Total Cubic Yds.
o Pre,,'iously listed uncol'"Tected items
~ Changes to approved plans and/or specifications by Architect,or Engineer
o COl'"Tections of pre,,'iousl)' listed items
D Items requiring cOl'"Tection
o Materials and metho'ds of construction
o Equipment used (i.e. what was used to proof roll or obtain compaction)
Field Oh..("rv:ltion.. and ('nmml'nt..
I
525 NW Second Street. CQrv(llli~, DrAgon 97330
d 800.383.9955 ph 541.758.1302 Ix 541.753.216~
www.cI8ircompeny.com
No. :-
overcast
Equipment
Serial Number
II
Concrete Grout Mortar
'I II
II II
II II
'I II
II IJ
II II
II II
II II
II II
ORcinforcing steel was checked in locations listed above, for grade, size, lap, placement and clearances where applicable.
Inspected nailing for above noted floor. 3/4" OSB sheathing installed with IOd nails per S2.5 Rev. 6. Nailing found to be in general
confonnance with plans.
One CMSTI6 strap installed@82-5,atcorridorframingon 0 & Eline. CSl4 straps installed at bathroom walls only, not at closet walls.
75
I
I
--I
I
I
As a mutual protection to clients, the public, and ourselves, all reports are submitted as confideDlial propeny ofcJients and are iDlended for the use of our clients or
No olller person or elllity may utilize the repon or any portion thereof without our written pemlissioll.
ITO the best of my knowledge, the work inspected was in accordance with the building department approved design drawings, specifications
and applicable workmanship provisions of the I.B.C. except as noted:
Inspector Name: Dave Tilton
Reviewed by: Ron Tiland