HomeMy WebLinkAboutPermit Field Test & Inspection Report 1997-7-1
.
NEW WAY ELECTRIC
4202 w. 6th
P.O. Box 21503
Eugene. Oregon 97402
.
CCB #51088
COMMERCIALJINDUSTRIAL
DESIGN. BUILD
ESTABLISHED IN 1979
(541) 686-2365
(541) 686.2715 FAA
TRANSMITTAL
//: '.
To: {~f-r 2 +~r.#~~ Date: /h/ ~ 97
dd,j- ~Jd r-/~/ . JOB:' kt--~dd
~A-/~fht(/;'/~f< Re:~~/J.7hnd' ,-h././L~
Attn: ,:/th-tl!/- 0 /~I"Z<r~4l'/~.
WE ARE SENDING:
~ATTACHED 0 UNDER SEPARATE COVER VIA
o FOR APPROVAL 0 FOR REVIEW & COMMENT 0 RETURNED FOR APPROVAL
o FOR YOUR INFORMATION 0 APPROVED 0 RETURNED FOR CORRECTIONS
d;'FOR YOUR USE 0 APPROVED AS NOTED 0
o PLEASE RETURN
APPROVED COPIES
COPIES
~
DESCRIPTION
_~/J7///?d' >-Jw/~/I.&Ar~ P4d.
C\h ~ f ~".r7 dV/,L
- 7 ',.
REMARKS:
~,.,o:// 7- 7~ "/ ,./
~--
PLEASE RESPO, ~Y I,
COpy TO ~
BY
7JUu~
. .
C"l(>drSt i'
.
PORTLAND AREA OFFICE
. I
()t~;-
4099 SE INTERNATIONAL WAY
SUITE 201
MILWAUKIE, OREGON 97222
(503) 653-6781
FAX (503) 659-9733
Independent Testing & Engineering Services for Electrical Power Systems
June 3,1997
eti Reference No.:357 5042
New Way Electric
4202 W. 6th
Eugene, Oregon 97402
Attention: Mr. Mike Gowins
Subject: Ground Fault System Acceptance Test Report
Waremart Foods. Springfield, Oregon
Dear Mr. Gowins:
Please find enclosed two copies of the subject test report. It was our pleasure to be of
service to you on this project. If you have any questions, or if we can be of further
assistance, do not hesitate to call.
Sincerely,
6(~ >t4
Larry Newby
Area Manager
LN:lk
Enclosure
. .
.. .J
.
.
~l~ct(o - t~ft inco(po(at~d
PORTLAND AREA OFFICE
Independent Testing & Engineering Services for Electrical Power Systems
4099 SE INTERNATIONAL WAY
SUITE 201
MILWAUKIE, OREGON 97222
GROUND FAULT SYSTEM TEST REPORT
(503) 653-6781
FAX (503) 659-9733
ETI REFERENCE NUMBER: 357 5042
DATE:
June 4, 1997
CLIENT:
New Way Electric
4202 W. 6th
Eugene, Oregon 97402
SITE:
Waremart Foods
1920 Olympic Street
Springfield, Oregon 97477
ATTENTION: Mr. Mike Gowins
P.O. NUMBER: 1920
1.0 PURPOSE
Performance tests of the ground fault protective equipment are conducted to
verify proper installation and operation. Section 230-95(c) of the current
National Electrical Code requires an on-site test of all newly installed ground fault
systems, as well as the appropriate documentation of such tests and inspections.
2.0 SUMMARY
This project was initiated at the request of Mr. Mike Gowins of New Way Electric.
All work was performed by Electro Test, Inc. field engineer,
Mr. Vernon Habedank on 15 May 1997.
The professional and helpful assistance of Mr. Steve Schoonover of
New Way Electric was appreciated and assisted in the timely completion of this
project.
The ground fault protection components were tested and found to be correctly
installed. The neutral system is grounded downstream of the neutral disconnect
link. Also, relay settings were temporarily made for service energization. The
design engineer should be consulted for the final settings. The "as left" settings
are 600 amps, with a 0.1 second time delay.
Please refer to Section 5 for the results and recommendations relative to this
project.
. .
.
.
3.0 EQUIPMENT TESTED AND INSPECTED
3.1 One (1) Instrument Transformers Incorporated, Zero-Sequence Ground
Fault System consisting of a Catalogue Number BGFL-159-1200 ground
fault relay with adjustable current range from 100 to 1,200 amperes and
an adjustable time delay from instantaneous to 1 second, utilized in
conjunction with an ITI zero-sequence current sensor for the Main,
Electrical Disconnect Switch for this building.
4.0 TEST PROCEDURES
4.1 Ground-Fault Protection Systems
4.1.1 Visual and Mechanical Inspection
.01 Visually inspected the components for damage and
errors in polarity or conductor routing.
. Verified the ground connection was made ahead of
the neutral disconnect link and on the line side of any
. ground fault system current sensor.
. Verified proper neutral sensor polarity to the ground
fault system sensing circuitry.
. Verified that all phase and neutral system conductors
were routed through the sensor in the same direction
for zero sequence systems.
. Verified that grounding conductors did not pass
through the current sensor on zero sequence-type
systems.
. Verified the grounded conductor was solidly
grounded.
.02 Verified correct operation of all functions of the self-test
panel.
.03 Verified adequate capacity of the control power
transformer, as it was utilized in this system.
.04 The appropriate written records were compiled relating to
the operation and test sequences required by Article
230-95 (c) of the current National Electrical Code.
eti Reference No: 357 5042 PAGE 2
. .
.
.
4.1.2 Electrical Tests
.
Measured the system neutral-to-ground insulation
resistance with the neutral disconnect link temporarily
removed. The neutral disconnect link was replaced after
testing..
.02 Performed the following pickup tests using primary
injection:
.01
. Verified the ground fault system did not operate at
ninety (90%) percent of the pickup setting.
. Verified that ground fault pickup was less than one-
hundred and twenty-five (125%) percent of setting or
1200 amperes, whichever is smaller.
.03 Measured the time delay of the relay at a value greater
than the current setting pickup value.
.04 Verified proper operation of the ground fault relay during
a reduced voltage condition of fifty-five (55%) percent of
rated voltage.
4.1.3 Test Values
.01 System neutral-to-ground insulation shall be a minimum
of one megohm.
.02 Relay timing shall be in accordance with manufacturer's
specifications, but must be no longer than one second at
3000 amperes.
5.0 RESULTS AND RECOMMENDATIONS
The following is a list of problems discovered during this testing project along
with any corrective action that was made by etL Those corrections beyond the
scope of the project that require your additional corrective action are in bolded
text immediately below the discussion of the issue.
5.1 The ground fault protection components were tested and found to be
correctly installed and operating satisfactorily. The neutral system is
grounded downstream of the neutral disconnect link. Neutral grounds will
desensitize the operation of the ground fault system and may cause
nuisance tripping. The neutral system ground was traced to the neutral
conductor for Circuits #30 and #32 in Panel HB 1.
These grounds should be cleared by the contractor, prior to
completion of this job. No retest or reinspection by eti is required.
eti Reference No: 357 5042
PAGE 3
. .
.
.
5.2 In the absence of engineering settings, the current pickup setting was left
at 600 Amps, as found, and the time delay reduced from the as found
setting of 0.6 seconds to 0.1 second, for service energization. ETI
accepts no liability for these settings.
The design engineer should be consulted for final settings.
SUBMITTED BY:
Vernon Habedank
Field Engineer
REVIEWED BY:
~~_L
Larry Ne~;-7
Area Manager
eti Reference No: 357 5042
PAGE 4
8J~
'" .
~l~ct(o
~ t~Jt
GROUND aL T SYSTEM
TEST REPORT
CLIENT: N&..J U A-I( k/....&L:r7'<. / C
LOCATION:, I
W4ef:.Jo~'tPr.f?r 1=ooDS
SWITCHGEAR DESIGNATION:
Ur-! \ F1W I<'JAI,J
5j)r",.",({< IJ all{
./ .
S w rtUl g o'A'R.d.
IT"'"
r_.}-t~LL8l-!6Gt. G..C." \lPO OS3'Z.."l ~O
MAIN QVERCURRENT DEVICE Yr1f'l..U:"LtS lMFGRo
o CIRCUIT BREAKER (2g FUSED SWITCH '17""'\,..[ 4>LG:
T~~_1-0~~J"~:;~~:~/,9 ICURR~~AG ISYS4ro/~;':'
GROUND FAULT SYSTEM I MFGA.
o NEUTRAL.GROUNO STRAP I2Sl ZERO -SEOUENCE I ~;r>euM~I1i?~F<>tl-le,eS iN C
MODEL ICAT. NO. lPICK-UP RANGE I TIME RANGE ISENSOR/CoT.
66R-lsq f3Gn-IS'1-IUlO lOO/I'WO .l See:... -l.se.e.... _ I T I .
AS FOUND SETTING AS LEFT SETTING ..I SETTINGS SUPPLIED BY ,,~ ~J"-Cjt...J' ~3
~m:<'\':N.,l"OO TIMf. /"S ~l'i~I/:NT /,00 TlME.1.- seL.- ~ l=<>1.A.ND """"re.<r W H.,,J"I"'<Uf .:/ /
7-o~</.
!VOL:j;V RiJ'NG
(ITl)
.
SERVICE ENTRANCE CONDUCTORS r-'I MAIN BONDING JUMPER GROUND ELECTRODE CONDUCTORS
LtOOtoA<-foI\x ~ C<..A. url,l--E'J\ P'HASE 1-";{ '/~';( I Z-3/0 c.u ~ AWG n
INEUTRAL-GROUND LOCATION I CONTROL POWER TRANSFORMER
IA:)CORRECT 0 INCORRECT 0 CORRECTED BY CONTRACTOR 3oc> VA
MONITOR/TEST PANEL OPERATION OTHER
o INCORRECT
MCM
B -! "'R!SW1TCH REACTION TIME (RT) REDUCED VOLTAGE TEST (55% RATED VOLTAGE)
IXJ SECONDS D CYCLES 0- CORRECT 0 INCORRECT
I PICK.UP CU RRENT MINUS 25% I ~()AMPS)
1000 AMPS .0' NO TRIP (COR RECTI D TRIP (INCORRECT)
I SYSTEM NE"t!TRAL INSULATION RESISTANCE TO GROUND I OTHER
o ohM";> - See. V"\o\1:;- "'1 MEGOHMS 4CoI'I>'\/Kt&() NI'.4<Tl'I'\-<..-S
I PRIMARY CURRENT
AMPERE~TURNS
I
I
I
PERCENT
PICK.UP
TOTAL
TIME
REACTION
TIME
RELAY
TiME
MFGR.
TOLERANCE
TIME-CURRENT
CALIBRATION
TESTS
~l{i.b.t?tZZ5
I
I
\-50
.1..3
Lf X 300
-z.oo
. L. 7-
. \ I
. II
. I z..
. I l
:t JO%
t
REMARKS
(i) Neu.~ G,,,,,o.vo.lO ,...J>.<..#) Tn "'I'Z.. AWG. IJ,I'1.'"- F"<>K. c.~T"'. 30 ~ 32.. IN P/>JL
1+ & 1. II\l ~ <U.Wr1-011. 12 "'-Sf Sf11->c.) U2" "" ~ I DOH. &1- vJ "r<. ~ g Tl'l-1":> E-il W I n-I
'(e,r-lt'\:>iaA-/l.I....y
mf~ WI"'/! L,r::rW. ntl> W,re 'DENnF'~O ~'rr1 BLue< pH'€:. C'A<.c.<,t:'c 01='
(~""u."',.I "HP~"f?) R I=-
~ G rouND ~IWL;r-
I
I W ~E:. ~6M.ClJW.
~ bK{,ltJ~ ~l\O\oU"D ?<>~ G>N.S~ ~~
GFSTR/90
Cl990 ETI
T')~.-n:-e.M IIJ ~Dl AI'J'D 'i?1YM)}P,/
lEST:
~
s'fs-rB-A IS REA-D9
(.....,P"II t=,N. TS. OPERI><'{l;() 5 A,I S FA.croRlL ~ J)u,...,v\.6,
10 BE: GNGRGtIee-D. Nec.d.(~l G,,-ou.l1J... I'luJ!S
FINAL 'S &rr1/'J1G.s
PAGE_OF_