HomeMy WebLinkAboutNotes, Meeting PLANNER 12/2/2009 ZON2009-00024 Development Issues Meeting - Lane Transit District Proposed hlterim Connection for EmX Bus Route- St. Joseph Place to Baldy View Lane NE Corner of PeaceHealth Hospital Site (Map 17-03-22-00, TL 100) Q1. L TD proposed use of swales with infiltration for stormwater. Is this satisfactory to the City? Has the City ever considered use of bio-slopes (ODOT BMP) for stormwater treatment and if so would that be an acceptable BMP application here? When infiltrating the water, other than DEQ injection well registration, what other permits would be required (i.e. drinking water protection, " landldrainage alteration permit)? A: See response from SUB Water Quality Protection. PW Engineering to comment. " Q2. The project is within the McKenzie River floodplain. Previous floodplain analysis by Peace Health indicates very little impact to the McKenzie River as a result of full buildout of the campus or even the urban growth boundary to current zoning standards. It is assumed construction of the roadway and associated stormwater facilities would not be considered an impact to the floodplain. Would the City require a Floodplain Overlay development" permit application, given that the proposal would not affect flood flows or the capacity of the floodplain? Please confirm. A: The City will not require a Floodplain Overlay District (FPO) application for the project. However, in accordance with SDC 3.3-420.5, the proposed street construction must provide for full accessibility during a 100 year flood and the surface of the street cannot be more than 1 foot below the base flood elevation (BFE). The road also should not be elevated such that it creates an impediment to possible flood flows. Construction plans shall include the calculated base flood elevation and proposed street surface elevations to demonstrate conformity. The 2003 McKenzie River Floodplain Assessment by David Evans & Associates should be used as the baseline for calculating flood elevations in this area, unless more contemporary data is available. Q3. Baldy View Lane, in places is failing or failed. L TD plans to remediate the roadway for ride comfort of the EmX vehicle with a 2" overlay, but does not plan to structurally reinforce the roadway. Depending on the duration of EmX on this route it is possible the buses could further damage the structure of the road. L TD proposes to evaluate the road after it is no longer used for EmX service and rehabilitate at that time if required by the City. Is this proposal acceptable and what agreements, if any, need to be prepared between the agencies? Note a similar agreement will be reached between L TD and Peace Health for impacts to St. Joseph Place east of Riverbend Drive. . A' PW Engineering andlor Transportation to comment. Q4. We understand that an amendment to the approved RiverBend MasterPlan is not required to accommodate the interim improvements proposed. Are there any other permits, land use approvals, or processes needed to accommodate this project (e.g. Public Improvement Plans), and if so, what specifically are the processes, costs and timelines that would be required? A: There are no anticipated land use approvals required for the interim road.connection. However, the applicant will need to demonstrate" that the road connection can be accommodated within existing rights-of-way or dedicated easements. Work that is being done within the public right-of-way will "require an approved PIP and Land Drainage Alteration Permit (LDAP), etc. PW Engineering andlor Transportation to comment. A~~-f-.}.. U-i.J~ -p~ p. I.P. ) ru>f S+~~. Date Received: I. ~/4n' Planner: AL 1/'