Frorn:Rosboro
7467224
12/02/2009 16:39
#256 P.001/002
Rosboro
Growing Today, Building Tomorrow.@
12/02/2009
Job Number:
Location:
-~----- - ~ ,
,
,C0M2009-00246
- .-----,
2509'MAIN.S'P
- .---- --
Project:
Refeed and Replace 1000KV A Transfonner and SwitchGear with
1500KV A Transfonner/Switch Gear
Lisa Hopper
r
Please accept this as our application for an extension to the pennit listed above.
Due to staff reductions and scheduling conflicts we have been unable to complete
this installation, We anticipate finalizing this project during the first quarter of 20 10.
and appreciate your understanding regarding this matter.
Thank you.
Jon Wheeler
Electrical and Control Systems Supervisor
Rosboro Lumber
54]-736.2]]8 Direct
541.501-2307 Cell
541-746-7224 Fax
jonwheeler@rosboro,com