BREWSTER Bryan [BryanB@subutil.com]
Thursday, March 26, 2009 8:06 AM
MARKARIAN Molly
RE: 1082 Main Street Assignment
Good morning Molly. There is not a 3 phase pad mount in the area. The new transformer could be placed behind the
sidewalk in front of parking space 1, at the north end of the project.
Any more questions, feel free to call or email.
Bryan Brewster
Springfield Utility Board
Engineering
S41.744.3784
brvanb{alsubutil.com
From: MARKARIAN Molly [mailto:mmarkarian@ci.springfield,or,us]
Sent: Wednesday, March 25, 2009 4:33 PM
To: BREWSTER Bryan
Subject: RE: 1082 Main Street Assignment
Brian,
I followed up with the applicant, and it seems that the second part of the second question is asking ifthere is a
transformer in the area that can support the development, and if not, if a new pad-mount transformer will be required.
If so, where would it be requested to be located? Looking forward to your response. Thanks.
Molly Markarian
Planner II
City of Springfield - Development Services Department
541.726.4611
m markarian(cj)ci. sDri nofield" or, us
From: BREWSTER Bryan [mailto:BryanB@subutil.com]
. Sent: Monday, March 23, 2009 11:34 AM
To: MARKARIAN Molly
Subject: RE: 1082 Main Street Assignment
There is 3 phase available for this site.
If you mean the short pole in the center of the site, yes it can be removed. It's a lift pole for the existing service.
Bryan
From: MARKARIAN Molly [mailto:mmarkarian@cLspringfield.or.us]
Sent: Friday, March 20, 2009 4:43 PM
To: BREWSTER Bryan
Subject: FW: 1082 Main Street Assignment
~
Bryan,
lJ'=ll0 H8CE:.JiVeO:~
Planner: MEM
"1
I understand that you are the SUB representative who will be attending the Development Issues Meeting for the Afiya
Apartments project at 1082 Main Street. Since this is a complex project, I'm looking for the answers to their questions
prior to the meeting if at all possible. Please let me know if you can provide your answers to me via email by March
30th. The two SUB,specific questions in the packet are:
Question 111:
The building will require 3-phase power far the elevator. Please verify it is available to the site.
Question 112:
There is a power pole located on the site where the new building is praposed. May this pale be removed? Is a new pad,
mount transformer required? Since power comes from the alley, wauld it be located at the alley?
Thanks!!
Molly Markarian
Planner II
City of Springfield - Development Services Department
541.726.4611
mmarkarian(1j)ci. sprinqfield. or. us
From: MATYSZAK Guenter [mailto:guenterm@subutil.com]
Sent: Thursday, March 19, 2009 1:27 PM
-To: MARKARIAN Molly
Subject: 1082 Main Street Assignment
Hi Molly,
Bryan Brewster has been assigned this project. You can contact him at 744-3784 or brvanb{cilsubutil.com.
Good to hear from you again.
Regards,
Guenter
..... - ...-
. I....:. ....q , .
, -'\ ,
ll.':il: .i~\: ;1~,.'i~';";:.
2