DAILY FIELD REPORT
Date Performed: March 13, 2009 Report Number: 722-90008-25
Client: Ms, Lauretta Davies Project Name: Jerry's-Warehouse Renovations
Jerry's Home Impro'vement
P,O, Box 2611 Project Location: 2525 Olympic Street
Eugene, Oregon 97402 Springfield, Oregon
P,O, No,: Z4175LD Building Permit No,: COM2008-01595
Type of Inspection: Welding Weather: Inside
Field Observations and Comments
Performed periodic visual inspection of the following items: single pass fil,let welds for 26 fe,of exterior roll-up door -onl
eastside of existing buildirig (Wilco building), welds were in accordance with, detail AlS20f the project plans and
documents: Weldments were inspected ,for size, le~gth, profil.e and 19cations, To ihe best of our knowledge, the work
inspected is in conformance with the approved drawings;' specifications 'and applicable AWS D1,1 codes, Contractor
was asked to ~otify our office when additional services are needed, ' ..,
Inspector: Raymond Aliperti, Certification #1017075-85
CCB #176269
If you have any questions regarding this report, please feel free to contact us at 541-746-9649,
Respectfully Submitted,
Professional Service Industries, Inc,
3::lY.~
Project Manager
c: City of Springfield
Chambers Construction - David Bakke
Robertson Sherwood Architects - Scott Stolarczyk
Metzler Engineering - Scott Metzler
THIS REPORT IS PROVIDED FOR THE INFORMATION OF THE CLlENTONL Y. THE REPRODUCTION OF THIS REPORT, BY ANY M8'HOD, AND ITS TRANSMITTAL TO A THIRD
PARTY, BY ANY MEANS. EXCEPT IN FULL, WITHOUT THE WRITTEN PERMISSION OF PROFESSIONAL SERVICE INDUSTRIES, IS PROHIBITED.
Professional Service Industries, Inc.. 1040A Shelley St.. Springfield, OR 97477. Phone 541n46-9649. Fax 541n46.7163
IP~11iorif;::!l:~n
li?nglna":'",_' . ~ . "IlMUng
Client:
Address:
Ms, Lauretta Davies
Jerry's Home Improvement
P,O, Box 2611
Eugene, Oregon 97402
:Location Sampled At:
G.9 to D at 7,5 to 9
Da{e Cast: 02/11/09
Ticket No.: IMIX No
3352837 50V~~200
'Piacemen-t Data: iiiraterlcil:--Concrete Slump'{in.): ASTi:i Cf43
Slab on grade at"pour back at truck ramp gridlirie C,,1).ltT5 to,9"C,9 to D at 7,5 to 9 and C,1 Max, Aggr. Size:
toD at 7.;5.to 7.8' AkContent: "ASTMC231
~
Air Temperature (F):
Material Temp. (F):ASTM C1064
Max Temp "(F): =
Min Temp (F):
Specimen Size:
Unit Weight (pel): ASTM 6138
Time Cast: 9:20 AM
Additives: AEA
Results; Reported To:
"Desiqn Strenqth (psi):
~ ""
Cylinder No.
09-0485
09-0486
09-0487
09-0488
Test Date
2/24/2009
3/17/2009
3/17/2009
4/8/2009
Date Ree'd: 02/12/09
Weather:
. Overcast
required 5,000
Age (days)
Field Cure
(days)
Lab Cure
(days)
7
28
28
56
6
27
27
55
.... --- -- ---, -
"'1 - Cone (both ends) 2 - ConeNertical Cracks (one end)
Remarks:
c:
-3 - Columnar
COMPRESSION R~PORT
r~'Ne~h5~i1
I-~~
Project No,: 722-90008-18
SPRINGFIELD OFFICE
1040 - A Shelley Street
Springfield, Oregon 97477
(541)746-9649 - (541)746-7163 fax
March 12, 2009 CCB#176269
Location:
Date:
B,P, No,:
P,O, No,: Z4175LD
2525 Olympic Street Cast By: Glenn Meek Jr
Springfi'eTd~OrE!gon 'C- / <.-&f~
- -- - c.. 0 - -'FielCl Test Data
Proj, Name: Jerry's-Warehouse Renovation
6"
11/2"
5.5%
380
5W
Yardage
2
9/27
6x12
Load:
Total:
Supplier:
Knife River
Curing Conditions:
ASTM
Contractor
Compressive Strength Data ASTM C39
Dlaced 5,000
Diameter or Cross Sect. Area Cylinder WT. Compo Strength Capping Method
Dimensions Max. Load (Ibs.) Fracture Type .. Test Time
(inches) (5.1.) (Ibs.) (psi) _
C617 C12Jl
6,00 28,27 28,3 121,895 4,310 ,3 3:50 PM X
-
5,99 28,21 28:3 133,745 4,740 2 10:26 AM X
6,01 28,37 28,2 135,690 4,780 6 10:32 AM X
4 - Diagonal w no cracking at ends
5 - Side fraclures(at top of bottom) '6 - Top fuctures (same as #5 but end or cylinder is pointed)
R",.m~~~:IY Sub itted,
Pr ~~~ ice Industries, Inc,
, Sieve Wilder
Laboratory Supervisor
Ciiy 01 Springfield
Chambers Construction ~,David Bakke
,Robertson Sherwood Architects _ Scott Stolarczyk
Metzler Engineering - Scott Metzler
These results relate only to the specific samples tested and may not be indicative of other locations, This report cannot be reproduced, except in full,
without written permission by Professional Service Industries, Inc,
l"S'J Infonnation
~" ,.wlToBuildOn
...', " .. ,:;~ Consuftt.isr . 11IGffnsI
FIELD DENSITY REPORT
SOIL AND SOIL-AGGREGATE
Client: Ms, Lauretta Davies
Address: Jerry's Home Improvement
P,O, Box 2611 ,
Eugene, Oregon 97402
Project No,: 722-80276-61
Project: Jerry~s-McKenzie Field Improvments
Project 2525 Olympic Street
Location: Springfield, O-regon
Equipment: Troxler: 3430 SN:
Date Performed:
P,O, No,:
B,P, No,:
Technician:
Laboratory Soil / Aggregate Data:
3001~ <0 - I '5' 1)'
Moisture Density Relationship of 135Ibs.lcuJt., at 8% moisture, was supplied by'supplier for Egge Sand and Gravel 3/4"-0 modified.
Test No.-
Approximate Test location
Slab on grade
Field Density Tests: Nuclear Method (ASTM D2922)(ASTM D3017)(Standard Count: MS646 DS 2291)
Approximate Test
Elev.
Probe
Depth
Wet Density Dry Density
LBSfCU,FT, LBSfCU,FT,
Percent
Moisture
NE im'pact slab, north side
2 NE impact slab, soufh side
Tests performed at finished grade of base rock at listed locations above,
Tests were reported to Jason with Chambers Construction,
FRG,
FRG
6"
139,0 -
137,8
6"
c: City of Springfield
Chambers Construction - David Bakke
Robertson Sherw()od Architects - Scott Stolargzyk
Metzler Engineering - Scott Metzler
131,0
132.2
~ctive~
3-Z.~ -0'1
-
1040 - A Shelley Street
Springfield, Oregon 97471
(541)746-9649 - (541)746'7163 fax
March 12, 2009
Z4175LD
Raymo~d Aliperti
Percent Required
Compaction Compaction
Comments
6,1
4.2
97,0 95%
97,9 95%
Professiona Service Induslcles, Inc,
R:;~2~
Raymond V, Aliperti
Project Manager
THIS REPORT IS PROVIDED FOR THE INFORMA nON OF TH . CLIENT ONL Y. THE REPRODUCTION OF THIS REPORT BY ANY METHOD, AND ITS TRANSMITTAL TO A THIRD PARTY BY ANY MEANS EXCEPT IN FULL IS PROHIBITED
WITHOUT THE WRITTEN
PERMIS~/ON o.F...PROFESSIONAL _SERVICE INDUSTRIES. .