TYPE n TENTATIVE SITE PLAN REVIEW. REPLY TO STAFF
REPORT AND DECISION
January 18, 2007
Project Name: Parkway Center Site Plan Tentative Review
Project Proposal: Construct a 24,838 square foot commercial center to include 3 separate
buildings, including a Walgreens and a credit union.
Case Number: DRC2006-00085
Project Location: 104 W, 'Q' Street, 17-03-27-10 TL3300
Owner/Applicant:
Skyview, LLC and South Plaza II LLC
Thomas Fox Properties
515 West Picket Circle, #400
Salt Lake City, UT 84117
o
Civil Engineer:
Ga ry Reed
Weber Elliott Engineers P.c.
PO Box 10145
Eugene, OR 97440
/1jo
Conditions of Approval:
L Prior to approval of the Final Site Plan, the applicant shall obtain written approval from
the SpTingfield Utility Board (SUB) for all proposed utilities shown.
We have obtained the approval of SUB for all the proposed utilities,
We have consulted with SUB on the points of connection to the power'
lines and water main in Pioneer Parkway. We will endeavor to have
SUB submit an email to David Reesor of The City of Springfield,
indicating their approval in written form,
2. Prior to Final Site Plan approval, all new easements shall be recorded and evidence thereof
provided to the City, The Final Site Plan shall show the location of all utility easements,
Weber Elliott Engineers, P.C. - Partners in Quality and Commitment wB
2
)
, "
The only new ~asement will be the seven foot wide public utility
easement on the West boundary of Pioneer Parkway, North of the
existing ten foot storm easement, The owner has no objection to the
granting of this easement to the City of Springfield, The engineer will
prep(jre the easement documents and submit them to the owner for
signature and recording,
3. All utility lines to serve the development site shall be placed underground. .
All utility lines on the project site will be placed underground,
~
4. To ensure a fully functioning water quality system and meet obj~tives of Springfield's MS4
permit, the Springfield Development Code and the EDSPM, the proposed private vegetative
water quality swale shall be fully vegetated with all vegetation species established prior to
approval of Final' Plat, while the grassy swaleldetention pond shall be fully vegetated with
all vegetation species established prior to City acceptance of the Public Improvement
Project. Alternatively, if this condition cannot be met, the applicant shall provide and
maintain additional interim erosion controVwater quality measures acceptable to the Public
Works Department that will suffice until such time as the swale vegetation becomes fully
established.
,
. \
The applicant/owner will endeavor to' ensure that the water quality
swale is fully vegetated prior to occupancy or will provide water
quality measures acceptable to the Public Works Department until
such time as the swale vegetation is fully established,
5, Prior to approval ofthe Final Site Plan, the applicant shall re-Iocate the proposed water
quality swale shown on the westerly property line to comply with code, Plans shall be
submitted showing swale designs in complete conformance with the City of Portland's
Storm Water Management Manual, specifically the requirement for a minimum of 5'
sepaTation from all property lines (pg 2-71), Also, a structural evaluation will be required
prior to fmal site plan approval for any structure being proposed that may impact or
influence existing building foundations on adjoining properties,
l
The proposed water quality swale as located along the property line
will be lined with an impermeable membrane to protect the adjacent
footings of the existing buildings, Permission has been granted by the
Public Works Department in accordance with the City of Portland's
Storm Water Management Manual which allows for zero setback
provided that the swale is constructed with an .impermeable barrier to
water migration in order to protect adjacent building footings. The
impermeable barrier for the western bioswale only, has been shown
on the engineering detail drawings,
Also, prior to issuance of a building permit for the northern
commercial building, the owner will proVide a structural evaluation of
'\
(
Weber Efliott'Engineer:-, P.C. - Partners in Quality and Commitment w&!
3
the existing building where adjacent footings for the new building are
to be constructed,
6. Proposed designs for street and traffic signal modifications are approved in concept only.
Design and construction details for these public facilities shall be established during a
Public Improvement Project (pIP) process under permit from the City Springfield Public
Works Department's Engineering Division,
The owner/applicant understands that design and details of the street'
and signal modifications shall be established during a Public
Improvement Project process,
7, Developer shall mitigate impacts due to street removals in accordance with SDC 32.050.
The owner/applicant will mitigate impacts of the tree removal on
Pioneer Parkway in order to maintain conformance with street tree
standards in accordance with SDC 32,050,
8, The proposed site driveway onto 'Q' Street shall be restricted to 'right-in-right-out
movements only, Prior to Final Site Plan approval, a revised driveway design shall be
approved by the City Traffic Engineer. .
The owner/applicant agrees to limit the driveway onto Q Street to
right-in-right-out movements only, Revised driveway designs have
been submitted to the City Traffic Engineer with size revisions and
lateral relocation in order to accommodate Walgreens large service
-truck traffic, The City Traffic Engineer is considering these revisions
and has indicated that approval will. be granted in the very near
futu re,
As of January 18, 2007, the City Traffic Engineer has stated that he is
satisfied with the revisions proposed,
9, All fire apparatus access routes shall be paved, all-weather surfaces and support an
80,000 lb, imposed load in accordance with the 2004 Springfield Fire Code (SFC) 503.2,3
and SFC Appendix D 102.1.
The pavement design has been submitted to the City Engineer and is
capable of supporting the design load in accordance with the 2004
Springfield Fire Code 503.2.3 and Appendix D102.1.
10, All new uses on the site shall be a permitted use'in the Mixed Use LMI/CC Zone,
All uses on the site will be permitted uses in the Mixed Use Zone',
II. All proposed landscaping shall be installed prior to Final Site Plan Inspection or issuance
of Final Occupancy Permit on the site, All plant nursery tags identifYing species and
Webel EUioff Engineers, p, C. - Partners in Quality and Commitment 'Wfi
4
variety of trees and shrubs shall remain on plant specimens until the [mal site plan ,
inspection. All seed containers shall be retained for inspection during ~inal Site Plan
Inspection:
The owner agrees that all landscaping shall be installed prior to Final
Site Plan inspection or issuance of the Final Occupancy Permit on the
site,
Five copies of the revised site plans will be submitted to the Planning
Division along with the fee of $1,460,03 to complete this process and
begin preparation of the Development Agreement, (This fee amount
was confirmed by David Reesor)
prepared by Gary Reed, Weber Elliott Engineers, PC
~