HomeMy WebLinkAboutCorrespondence SUB 1/2/2007
.~- .~
\
.~-
'.
SPRINGFIELD UTILITY BOARD
WATER SERVICE CEi\'TEI{ 202 South 18th Street Springfield, OR 97477-5240 Tel 541.726.2396 Fax 541.747,7348 www.subutiJ.com
December 29, 2006
Andy Limbird
City of Springfield
225N, 5th Street
Springfield, OR 97477
Dear Andy:
SUBJECT:
PARTITION TENT A TIVE #SUB2006-00069 FISCHER
Tax Map 17-02-31-42, Tax Lot 7800, 285 South 37"' Street
Listed below are our comments for the above referenced development proposal:
I. The proposed development is within the Springfield city limits and will receive water service from
the Springfield Utility Board (SUB).
":-.;' <;'J~;. :':. ',.".,;'
2, All neW, wa(ersystem, [acilities and modifications to wat~r syst~m facilities,both irs(de al:Jq .". .
adjacent to.the proposedAevelopme~t ,shall. be plac~d in st.ree!Jight~of,~a{a.(,\l. fciSa.ti09,an'd.depth
of bury that meets the standards of the SUB Water Division. ,- ,". ..
. ...~ .. _ '5. ;)".
~, ~
"
3. All water facility materials shall be to a standard that must meet SUB Water Division
specifications.
4. All workmanship shall be performed to meet or exceed SUB Water Division construction
standards.
5. Size of waterline and other facilities, including water meters, inust meet the needs of the SUB
Water Division and the long-range needs of the City. These needs include, but are not limited to,
met'er-Iocat:on and acces-s, sizes of water distribution- and transmission lines, pumping facilities,
and conununication,lines.
6. Please ask the developer to contact the SUB Water Division for detailed inf~rmation on the
materials and construction standards, detailed costs for installing SUB water facilities, and a
schedule of construction. Construction expenses may be reduced with good planning of required
water facilities, good timing of facilities installation, and joint trench opportunities.
,'..-
7. All water l11eters will be placed in public right-of-way at a location identif1ed \,y the developer.
Each lot or parcel must have its own water service. " .
vI , , . , .,
8. Watenservigefacilities ,will be,installed uponcollectjon ofge."~I5'Pl1!.ent,cqa~ge~;,.-geyeI9pment .
policies andcharges.identified in t,his letter are subject to;.C~a.J;,1g9. -AC!u31;cb%ge~,:r'W g,e :ifiose in'
effect at the time water service is requested. .
,j-;.
;'-
Date t{6ceived: //.z/.,lO07
Planner: AL I
.... '.j
Site Plan #SUB 2006-00069
285 S. 37th Street
December 29, 2006
Page 2 of2
9. Springfield has several wellhead protection areas. Ninety percent of Springfield's drinking water
comes from wells. In every instance, care shall be taken to prevent groundwater contamination.
Contractors/developers/owners shall be responsible for the safe handling and storage of chemicals,
petroleum products, fertilizers, and the prevention of groundwater and storm water runoff
contamination.
Special requirements may be necessary for groundwater protection at this development. Contact
Amy Chinitz at Springfield Utility Board Water Division for details at 726-2396.
PLEASE NOTE:
SUB development charges are paid directly to SUB Water Division and
SUB Electric Division.
Sincerely,
Ztw- ~~
Rebecca Temp)in, P.E.
Civil Engineer - Water Division
RAT:mkm
cc: Daniel Fischer, 325 South 43" Place, Springfield, Oregon 97478
Scott Morris, Olson & Morris, 380 Q Street, Suite 200, Springfield, Oregon 97477
\\svr-data\WSCEngnr\SITEPLAN\285 S 37th Street Partition Tentative 12-29-06.doc
Oat.. i'<eceived: 1/2 /:Z<>07
Planner: AL 7 /