DAILY FIELD REPORT
Date Performed: July 17, 2008. Report Number: 722-70168-28
Client: Hexion Specialty Chemicals Project Name: Hexion Specialty Chemicals
PO Box 1310
Columbus, OH 43216 Project Location: 470 S 2nd
Springfield, OR
P.O. No.: Permit No.: COM2007 -00418
Type of Structure: Weather: Clear
Type of Inspection: Reinforced Concrete
Field Observations and Comments
. Performed visual inspection of reinforcing steel inspected reinforcement at #3 tank pad. Reinforcing steel was checked
for grade, size, lap, placement and clearances where applicable. Reinforcing steel. was secured using tie wire and
suppored on spreader bar. Reinforcino steel was placed in accoradance with the latest.revisions dated 3-20-08.
Inspector: Glenn Meeks, ICC#5021538-49
CCB# 176269
If you have any questions regarding this report, please feel free to contact us at 541-746-9649.
Respectfully Subm tied,
U~::i e In~ Its, Inc.
David Smith .
Branch Manager
c: Hexion Specialty Chemicals - greg.wilberger@hexion.com
John M Pearson .
Advanced Mechanical
JHI Engineering - Mike Smith
. i
'" ,; '.
<.
THIS REPORT IS PROVIDED FOR THE INFORMA TION OF THE CLIENT ONL Y. THE REPRODUCTION OF THIS REPORT, BY ANY METHOD, AND ITS TRANSMITTAL TO A THIRD
PARTY, BY ANY MEANS, EXCEPT IN FULL, WITHOUT THE WRITTEN PERMISSION OF PROFESSIONAL SERVICE INDUSTRIES, /5 PROHIBITED
Professional Service Industries, Inc.. 1040-A Shelley Street. Springfield, OR 97477. Phone 541/746-9649 . Fax 541/746-7163
l ~~;lInformation
fI~. ,To Build On
Engineering . Consulting . Testinll.
uA!L Y FIELD REPORT
"
Date Performed: July 21,2008 Report Number: 722-70168-31
Client: Hexion Specialty Chemicals Project Name: Hexion Specialty Chemicals
POBox1310
Columbus,OH 43216 Project Location: 470 S 2nd
Springfield, OR
P.O. No.: Permit No.:
Type of Structure: Weather: Clear
Type of Inspection: Reinforced Concrete
Field Observations and Comments
Specific placement locations: phase 3 tank pad. Concrete was placed by pump and mechanically consolidated. Cast
one (1) set of four (4).(4x8) concrete test cylinders. Contractor was asked to notify our office when addiction services
are needed. To the best of our knowledge, the work inspected above was in accordance with the building,departmenl
approved design drawings, specifications and applicable workmanship provisions of the International Building Code.
Tvne of Material
Supplier
Mix#
Slump
Air Content
Ambient Temperature
Material Temperature
Time Placed
Design Strength (psi)
Number of Samples
Total Yardaqe Placed
Inspector: Pete Furlong
CCB# 176269
Set #1
ES&G
314045
43/4"
4.5%
87Z
80Z
1 :25 PM
4,000
4
38
If you have any questions regarding this report, please feel free to contact us at 541-746-9649.
Respectfully Submitted,
(iofeSSional t!rvic~ustries" Inc.
~
Branch Manager
c: Hexion Specialty Chemicals - greg.wilberger@hexion.com
John M Pearson
Advanced Mechanical
JHI Engineering - Mike Smith
~HIS REPORT IS PROVIDED FOR THE INFORMA nON OF THE CLIENT ONL Y. THE REPRODUCTfON OF THIS REPORT, BY ANY METHOD, AND ITS TRANSMITTAL TO A THIRD
PARTY, BY ANY MEANS, EXCEPT IN FULL. WITHOUT THE WRITTEN PERMISSION OF PROFESSIONAL SERVICE INDUSTRIES, IS PROHIBITED.
Professional Service Industries, Inc.. 1040-A Shelley Street. Springfield, OR 97477 . Phone 541f746-9649 . Fax 541/746c7163
1'..ii.~;lInformation
"""~.. To Build On
li!!ngh ",,' "., . ~ . ~...
COMPRESSION REPORT
Client:
Address:
Hexion Specialty Chemicals
PO Box 1310
Columbus, OH 43216
Project No.: 722-70168-34
Proj. Name: .Hexion Specialty Chemicals
location:
Placement Data:
Phase 3 tank pad
Material: Concrete
Location Sampled At:
Southwest corner
Date Cast: 07/21/0B
'Ticket No.: IMiX No.:
600005474 2,14045
. .
Date'Rec'd: 07/22/OB
Weather:
-I '.--Ya-rdage
JLoad: 1
Total: g 1/2
--- -- ---
Supplier:
Eugene Sand & Gravel
Clear
Springfield, OR
--Slump (in.): ASTM C143
,Max. Aggr. Size:
Air Content: ASTM C231
Air Temperature (F):
Material Temp. (F): A~TM C1064
Max Temp (F):
Min'Temo IF}:
-. --..-
Specimen Siz.e:
Unit Weight (pet): ASTM C138
Time Cast: . 1 :25 PM
---
Additives:
Results Reported To:
SPRINGFIELD OFFICE
1040 - A Shelley Street
Springfield, Oregon 97477
. (541)746-9649 - (541)746-7163 fax
August 18, 2008 CCB #176269
. Date:
B.P. No.:
P.O. No.:
Cast By:
Pete Furlong
Field Test Data
43/4'"
1/2"
4.5%
B7.2"
80.20
75.90
64.90
4x8
Curing Conditions:
ASTM
Contractor
~
Compressive Strength Data ASTM C39
Desi!=ln Stren!=lth (psi): required 4,000 placed 4.000
Field Cure Lab Cure Diameter or Cross Sect. Area Cylinder WT. Comp.,Strength Capping'Method
Cylinder No. TestDate Age (days) Dimensions Max. Load (Ibs:) Fracture Type *. Test Time
(days) (days) (inches) (s.i.) (Ib5.) (pSi)
C617-03 I C1231-03
OB.1705 I 7/28/2008 7 6 4.00 12.57 8A 36,995 2,940 2 9:32 AM X
.. I -
0~-1706 8/18/2008 28 27 4.00 12.57 8.5 57,095 4,540 3 11:00AM X
08-1707 I 8/18/2008 28 1 27 3.99 12.51 BA 56,605 4,520 3 11:05AM X
I - - - .,-:c-
08-1708 H H H
h 1 - Cone -(both ends) 2 ~'coneiveiiicai Cracks (one end). 3 - Columnar 4 - b'iagori::lI wIno cracking at ends
Remarks: . . .
c:
.Hexion Specialty Chemicals - greg.wilberger@hexion:com
John M Pearson .
Advanced Mechanical
JHI Engineering -Mike Smith
5 - Side fractu~es (attop of bottom)
6- ---Top fractur~esame ~~ _.1.5 but end of cylinder is pointed)
Re:t~~u.'IY SU~itted'
Pro ~~ ices Industries, Inc.
. St n E. Wilder
Laboratory Supervisor
THIS REPORT IS PROVIDED FOR THE INFORMATION OF THE CLIENT ONL Y. THE REPROOUCTlON OF THIS REPORTBY ANY METHOD, AND ITS TRANSMITTAL TO A THIRD PARTY BY ANY MEANS EXCEPT IN FULL, IS PROHIBITED
WITHOUT THE WRITTEN
PERMISSION OF PROFESSIONAL SERVICE INDUSTRIES.
Ij}SllfonfJf:::;::tnn
1I!!Itg_~I" . .~" "I ',JI 0 ~ . 'If.. .",,,(, ,.~~
SPRINGFIELD OFFICE
COMPRESSION REPORT
Client:
Address:
Hexion Specialty Chemicals
PO Box 1310
Columbus,OH 43216
'Project No.: 722-70168-33
Proj. Name: Hexion Specialty Chemicals
Location:
1040 - A Shelley Street
Springfield, Oregon 97477
(541)746-9649 - (541)746-7163fax
August 17, 2008 CCB #176269
Springfield, OR
Date:
B.P. No.:
P.O. No.:
Cast By:
Devon Hovis
Load:
Total:
Supplier:
Euaene Sand & Gravel
Yardage
2
22
'Slump (in.): ASTM C143
Max. Aggr. Size:
'Air Content: ASTM C231
Air Temperature (F):
'Material Temp. (F): ASTM Cl064
Max Temp (F):
Min Temp (F):
Specimen Size:
Unit Weight (pcf): ASTM C138
Time Cast: 5:45 AM
Additives:
Results Reported To:.
Field Test Data
'43/4" ..
1/2"
.-.,-..
.._.__..._ .::1:1,"
'Pia-cement Data:
Southem half of containment pad
M.i"terial: Concrete
Location Sampled At:
Dc 13' norht of south edge 9' - 19' east of wesl edge
Date Cast: 07/18/08 Date Rec'd: 07/19/nR
:c1k;~:80~: IMIX 3~:~45 Weether: --:~:
51.40
78.40
71.7"
.58.40
4x8
Curing Conditions:
1 day F.e., remainder ASTM
Contractor
Desi!=ln Stren!=lth (psi):
----
required 4,000
Compressive Strength Data ASTM C39
Dlaced 4,000
Cylinder No.
Test Date
Age (days)
Field Cure
(days)
Lab Cure Diameter or Cross Sect. Area CylinderWT. Compo Strength Capping Method
Dimensions Max. Load (Ibs.) Fracture Type *' Test Time
(days) (inches) (s.!.) (Ibs.) (psi)
C617-03 C1231-03
6 3.99 12.51 8.4 36,880 2,950 5 11:46 AM X
27. 3.99 12.51' 8.5 56,930 I 4,550 3 9:35 AM X
27 3.99 12.51 8.5 56,215 4,490 3 9:41AM X
08-1685
08-1686
7/25/2008
8/15/2008
7
28
08-1687 I 8/15/2008
08-1688 I
"::"j - Cone (both ends) 2 ~ ConelVerticaf C'racks (one end)
Remarks:
c:
28
H
H
H
3-- Columnar 4 - ~iagoncil w no cracking a-t en9s .5 -Side fra( cures (at lop pf bottom)
6 - Top fracfures (same as.- #5- but enc{ofcylin'de-r -is-p.oin-ted)
R l;t~;tfully,,~bmitted, .
p pJ.J.:itXH~es Industries, Inc.
. Steven E. Wilder
Laboratory Supervisor
Hexion Specialty Chemicals - greg.wilberger@hexion.com
John M Pearson
Advanced Mechanical
JHI Engineering - Mike Smith
THIS REPORT IS PROVIDED FORTHE INFORMA TlON OF THE CLIENT ONL Y. THE REPRODUCTION OF THIS REPORT BY ANY METHOD, AND ITS TRANSMITTAL TO A THIRD PARTY BY ANY MEANS EXCEPT IN FULL, IS PROHIBITED
WITHOUT mE WRITTEN
. . PERMISSION OF PROFESSIONAL SERVICE INDUSTRIES
l ra ~ "IIrifonnation
~~. ToBuildOn
1i!nfl1ne., "".J .~.~
Client:
Address:
Hexion Specialty Chemicals
PO Box 1310
Columbus,OH 43216
Placement Data:
Phase 3 tank pad
COMPRESSION REPORT
Project No,: :722-70168-34
Proj. Name: Hexion Specialty Chemicals
Location:
Springfield, OR
Material: Concrete
Location Sampled At:
Southwest corner
Oate Cast: 07/21/08
;Ticket No.: Mix No.:
Date Rec'd: 07/22/08
Weather:
600005474
314045
Clear.
Desiqn Strength (psil:
reauired 4,000
Cylinder No. Test Date Age (days) Field Cure
(days)
08.1705 7/28/2008 I 7
08-1706 8/18/2008 I 28
-. - I
08-1707 8/18/2008 28
08.1708 H I H
Lab Cure
(days)
Compressive Strength Data ASTM C39
olaced.4.000
Diameter or Cross Sect. Area Cylinder WT. Compo Strength
Dimensions Max. Load (tbs.) Fracture Type .. Test Time
(inches) (s.i.) (lb..) (psi)
4.00 12.57 8.4 36,995 2,940 2 9:32 AM
4.00 12.57 8.5 57,095 4,540 3 11:00AM
3.99 12.51 8.4 56,605 4,520 3 11:05AM
k~a~:
Total:
Supplier:
Eugene Sand & Gravel
Slump (in.): ASTM C143
Max. Aggr. Size:
'Air Content: ASTM C231
Air Temperature (F):
Material Temp. (F): ASTM C1064
Max Temp (F):
Min Temo IF):
Specimen Size:
Unit Weight (pet): ASTM C138
Time Cast: 1 :25 PM
Additives:
Results Reported To:
Yardage
1
91/2
6
27
27
H
.* 1 --Cone (both ends) 2 - ConeNerUcal Crack.s (one end)
Remarks:
c:
..J - Columnar
_\ , .
4 - Diagonal wIno cracking at em 5
5 - Side fractures (at top of bOll~m)
. Hexion Specially Chemicals - greg.wilberger@hexion.com
John M Pearson
Advanced Mechanical
JHI Engineering - Mike Smith
SPRINGFIELD OFFICE
1040 - A Shelley Street
Springfield, Oregon 97477
(541)746-9649 - (541)746-7163 fax
August 18, 2008 CCB #176269
Date:
B.P. No.:
P.O. No.:
Cast By:
Pele Furlong
Field Test Data
4.3/4"
1/2"
4.5%
87.2"
80.2"
75,9"
64.9"
4x8
,
Curing Conditions:
ASTM
Contractor
-
Capping'Method
C617c03
C12J1-0J
x
x
X
6- - Top frac'ture~same as #5 but end of cylinder is pO.lnted)
. Re :t~~~IY SU~itted'
Pro "fit;~ ices Industries, Inc.
St n E. Wilder
Laboratory Supervisor
THIS REPORT IS PROVIDED FOR THE INFOR~1A TlON OF THE CLIENT ONL Y. THE REPRODUCTION OF THIS REPORT BY ANY METHOD, AND ITS TRANSMITTAL TO A THIRD PARTY BY ANY MEANS EXCEPT IN FULL, IS
PROHIBITED WITHOUT THE WRITTEN
PERMISSION OF PROFESSIONAL SERVICE INDUSTRIES. '
l ~~;lInformation
fI~. ,To Build On
Engineering . Consulting . Testing
DAIL Y FIELD REPORT
Date Performed: July 18, 2008 Report Number: 722-70168-29
Client: Hexion Specialty Chemicals Project Name: Hexion Specialty Chemicals
PO Box 1310
Columbus, OH 43216 Project Location: 470 S 2nd
Springfield, OR
P.O. No.: Permit No.:
Type of Structure: Weather: Clear
Type of Inspection: Reinforced Concrete
Field Observations and Comments
Performed visual inspection during placement of concrete on south half of containment pad. Reinforcing steel was
secured using tie wire and supported on 90" bent rebar rods. Performed visual inspection during placement of concrete
in the locations listed above. As directed by client, continuous inspection during .placement of concrete was required.
Concrete was placed by line pump and mechanically consolidated on edges (approximately 5'). Cast 1 set (s) of 4 (4x8)
concrete test cylinders. Contractor was asked to notify our office when addiction services are needed. To the best of our
knowiedge, the work inspected above is in accordance with the buliding department approved 'design drawings,
specifications and applicable workmanship provisions of the International Building Codes..
Tvn.. of Mat..riaj Set #1
Supplier ES&G
Mix # 314045
Slump' 4 3/4'"
Air Content
Ambient Temperature
Material Temperature
Time Placed
Design Strength (psi)
Number of Samples
Total Yarda!:je Placed
Inspector: Devon Hovis, ICC#01116960
CCB# 176269
51.4"
78.4"
5:45 AM
4,000
4
22.0
If you have any questions regarding this report, please feel free to contact us at 541-746-9649.
Respectfully
D~/l
David Smitt '
Branch Manager
slries, Inc.
c: Hexion Specialty Chemicals" greg.wliberger@hexion:com
John M Pearson .
Advanced Mechanical
JHI Engineering - .Mike Smith .'
.i
.' 'I
THIS REPORT IS PROVIDED FOR THE INFORMA TION OF THE CLIENT ONLY. THE REPRODUCTION OF THIS REPORT, BY ANY METHOD, AND ITS TRANSMITTAL TO A THIRD
PARTY, BY ANY MEANS, EXCEPT IN FULL, WITHOUT THE WRITTEN PERMISSION OF PROFESSIONAL SERVICE INDUSTRIES, IS PROHIBITED.
Professional Service Industries, Inc. . 1040-A Shelley Street. Springfield, OR 97477 . Phone 54117 46-9649 . Fax 541/746-7163
l ri'~l1illnjonnation
I'!!:~~. .70 Build On
ll!ItfI.r" , ,;..1,.1. ~ . 111, ..1 ',I'.
Client:
Address:
Hexion Specialty,:Chemicals
PO Box 1310
COlumbus,OH '43216
'Placement Data:
.Slab for tank'#4 in phase 3
COMPRESSION REPORT
Project No.:. 722-70168-30
Proj. Nam,e: 'Hexion Specialty Chemicals
Location:
Maier!af Concrete
Location Sampled At:
1 Q'north of southwest corner west side
'DateCast: 07/16/08 Dale Rec'd: 07/17108
.Ticket No.: IMiX No.: Weather:
, 58003782 314045 Clear
Desi!1n Stren!1th (psi):
reauited 4.000
Cylinder No. . 'Test Date
Field Cure
(days)
Lab Cure
(days)
Age (days)
08-1637 7/23/2008 '. 7
08-1638 8/13/2008 28
08-1639 81'13/2008 28
08-1640 H H
Yardage
2
11/ 21.25
load:
Total:
Supplier:
Eugene Sand & Gravel
6
Springfield, OR
:Slump (in.): ASTM C143
.Ma-x, Aggr. Size:
Air Content: ASTM C231
A.ir Temperature (F):
:Material Temp. (F): ASTM C1D64
Max Temp (F):
Min Temo IF):
Specimen Size:
Unit Weight (pet): ASTM C138
'Time Casl: 6:45 AM
Additives:
Results Reported To:
SPRINGFIELD OFFICE
1040 - A Shelley Street
Springfield, Oregon 97477
(541)746-9649 - (541)746-7163 fax
August 14, 2008 CCB #176269
Date:
B.P. No.:
P.O. No.:
Cast By:
Verlyn Bearden
Field Test Data
5 1/2"
1/2"
530
750
4x8
Contractor
Curing Conditions:
1 day F.e., remainder ASTM
27
27
1. H
3- Cdumnar 4 - Oiagonafw no cracking"";rt er,js- 5 ~ Side fraciu-res (at top of bottom)
."--f~ Cone (both ends) 2 ~ ConeNertical CracKs (one end)
Remarks:
c:
Compressive Strength Data ASTM C39
Dlaced 4,000
Diameter or Cross Sect Area Cylinder WT. Camp. Strength
Dimensions Max.,Load (Ibs.) Fracture Type .. Test Time
(inches) (s.i.) (Ibs:) (psi)
3.99 12.51 8.3 32,300 2,580 5 8:35 AM
."--.
3.99 12.51 8.3 50,725 . 4,050 3 2:'19 PM
3.99 12.51 8.3 51,320 4,100 3 2:32 PM
Hexion Specialty Chemicals - greg.wilberger@hexion.com
John M Pearson
Advanced Mechanical
JHI Engineering _ Mike Smith
'"
Capping Method
C617-0J
C12J1-0J
x
X
X
6- Top fractures (same a.s.ttS.but end 6i"cylinder-is.pointed)
Rej~~~:;UIIY Submitted,
Pr }J.tf~s Indus/ries, Inc.
Steven E. Wilder
Laboratory Supervisor
THIS REPORT IS P'ROVIQE.QF.OR THE INI70R~1ATlON OF THE CLlENTONL Y. THE REPRODUCTION OF THIS REPORT BY ANY METHOO, AND ITS TRANSMITTAL TO A THIRD PARTY BY ANY MEANS EXCEPT IN FULL. IS
PROHIBITED WITHOUT T/-IE WRITTEN
II;? PERMISSION OF PROFESSIONAL SERVICE INDUSTRIES,
l~~;lInformation
fI~. .To Build On
Engineering . Consulting. Testing
DAILY FIELD REPORT
Date Performed: July 21, 2008 Report Number: 722-70168-35
Client: Hexion Specialty Chemicals Project Name: Hexion Specialty Chemicals
PO Box 1310
Columbus,OH 43216 Project Location: 470 S 2nd
Springfield, OR
P.O. No.: Permit No.:
Type of Structure: Weather: Clear
Type of Inspection: Reinforced Concrete
Field Observations and Comments
Performed visual inspection of reinforcing steel at the following locations: 8" containment wall at the west, east and south
sides excluding an area 20' in length at the south east side of the wall. This area is to be built at a later date.
Reinforcing steel was checked for grade, size, lap, placement and clearances where applicable. Reinforcing steel was
secured using tie wire .and supported on plastic chairs. Reinforcing steel was placed in accordance with last revisions
dated 3/20/07. Contractor was asked to notify our office when additional services are needed.
Inspector: Glenn Meeks Jr., ICC# 5071538-49
CCB# 176269
If you have any questions regarding this report, please feel free to contact us at 541-746-9649.
Respectfully Submitted,
15;~(~\e tQtries, Inc.
David Smith .
Branch Manager
c: Hexion Specialty Chemicals - greg.wilberger@hexion.com
John M Pearson
Advanced Mechanical
JHI Engineering - Mike Smith
'..
, :'
THIS REPORT IS PROVIDED FOR THE fNFORMATlON OF THE CUENT ONL Y. THE REPRODUCTION OF THIS REPORT, BY ANY METHOD, AND ITS TRANSMITTAL TO A THIRD
PARTY, BY ANY MEANS, EXCEPT IN FULL, WITHOUT THE WRITTEN PERMISSION OF PROFESSIONAL SERVICE INDUSTRIES, IS PROHIBITED.
Professional Service Industries, Inc.. 104Q-A Shelley Street. ~pringfield, OR 97477. Phone 541/746-9649. Fax 541/746-7163
t...~.. . ;11njonnation
IAN.., /I .
11_ .To Build On
. I!nglneerlng. eo.-.nJng . _ng
FIELD DENSITY REPORT
SOIL AND SOIL-AGGREGATE
Client:
Address:
Hexion Specialty Chemicals
PO Box 1310
Columbus,OH 43216
Project No.:
Pn)j.€ct:
Project.
Location:
. Equipment:
722-70168-1
Hexion Specialty Chemicals
470 S 2nd.
Springfield, OR
Troxler: 3430 SN: 30016
Date Performed:
P.O. No.:
B.P. No.:
Technician:
Michael Wright
. ,
1040 - A Shelley Street
Springfield, Oregon 97477
(541)746-9649 - (541)746.7163 fax
June 19,2007
Laboratory Soil / Aggregate Data:
Moisture Density Relationship of 136 lbs.lcu.ft., at 9 % moisture, was furnis~ed by contractor for 3/4"-0 from Morse Bros.
Field Density Tests: Nuclear Method (ASTM D2922)(ASTM D3017)(Standard Cou.nt: MS 691 OS 2706)
Test No..
Approximate"Test
Elev.
Approximate Test Location
East side of trench I 2' BFF
2 Center of trench I 2' BFF
3 West side of trench I 2' BFF
Tests performed at finished grade of trench'backfill at listed locations above.
Tests were reported to Leon with Advanced Mechanical.
c:
Hexion Specialty Chemicals - 9re9.wilberger@hexion.com
John M Pearson
Advanced lVIechanical.
JHI En9ineering - Mike Smith
Probe Wet Density Dry Density Percent Percent Required Comments
Depth LBS/CU.FT. LBS/CU.FT. Moisture Compaction Compaction
10" 135,2 130.4 3.6 95.9 95%
10" 135.6 129.5 4.6 95.2 95%
10" 136.7 132.2 3.4 97.2 95%
Respectfully Submitted
Professional SelVice Industries, Inc.
~~
Joseph Vardner, E.I.T.
Department Manager
THIS REPORT.lS PROVIDED FOR THE INFORMA TlONOF THE CLIENT ONL Y. THE REPRODUCTION OF THIS REPORT BY,ANY METHOD, AND ITS TRANSMITTAL TO A THIRD PARTY BY ANY MEANS EXCEPT IN FULL IS PROHIBITED
WITHOUT THE WRITTEN PERMISSION
OF PROFESSIONAL SERVICE INDUSTRIES. i' .
.l ~~;lInformation
fI~. ,To Build On
Engineering. Consulting. Testing
,
DAILY FIELD REPORT
Date Performed:
Client:
,
July 15, 2008
Hexion Specialty Chemicals
,
PO Box 1310
Columbus, OH 43216
Report Number:
722-70168-26
Project Name:
Hexion Specialty Chemicals
470 S 2nd
Springfield, OR
Project Location:
P.O. No.:
Type of Structure:
Type of Inspection:
Permit No.:
Weather:
Clear
Reinforcing Steel
Field Observations and Comments
Periormed visual inspection of t'einforci~g steel at the following locations: Inspected reinforcing at footing/slab on' grade
at phase #3; Formaldehyde Tank Farms. Reinforcing. steel was checked for grade, size,. lap, placement, and clearance
where applicable. ReinforCing,1 steel was secured using tie wire and supported on concrete dobie blocks. Contractor
was asked to notify our office when additional services are needed. To the best of our knowledge the work .inspected
above was in accordance with the buiiding department approved design drawings, specifications and applicable
workmanship provisions of the International BuildinCl Codes.
Inspector: . Glenn Meek Jr" ICC#: 5071538-49
CCB# 176269
If you have any questionsregaiding this report, please feel free to contact us at 541-746-9649.
. . ,
Respectfully Sfjmitted' ,
~~Si~S ic:wtries: inc.
JJ>>~r \ I
David Smitli '
Branch Manager
c: Hexion Specialty Chemicals - greg.wilberger@hexion.com
John M Pearson
Advanced Mechanical
JHI Engineering - Mike Smith
,
. .
.,
, ~; :-.,'. '-I.,....:: _ ^, ,"~:' .
"..';;
"'';'".
" ;; c .'.':: ~.-!:
," -;, ~~.,: f'"'.
. r. -'.'
,.
"
".
'I'
I.
. ""1' -"~.
'" '1:-'
THIS REPORT IS PROVIDED FOR THE INFORMATION OF THE CLIENT QNL Y. THE REPRODUCTION OF THIS REPORT, BY ANY METHOD, AND iTS TRANSMITTAL TO A ~HIRD
~ I . ' .. .
PARTY, BY ANY MEANS. EXCEPT IN FULL, WITHOUT THE WRITTEN PERMISSION OF PROFESSIONAL SERVICE INDUSTRIES, IS PROHIBITED.
I . ..
Professional Service Industries, Inc. . 1 040-A Shelley Street. Springfield, OR 97477 . Phone 541fl46-9649. Fax 541(746-7163
I ' .
l ~~;lInformation
fI~. .To Build On
Engineering. Consulting. Testin'bAIL Y FIELD REPORT
I
Date Performed:
July 161 2008
,
Report Number:
722-70168-27
Client:
Hexion iSpecialty Chemicals
PO Box 1310
Columbus, OH 43216
i
Project Name:
Hexion Specialty Chemicals
470 S 2nd
Springfield, OR
Project Location:
P.O. No.:
Type of Structure:
Type of Inspection:
Permit No.:
Weather:
Clear
Reinforced Concrete
I
,
Field Observations and Comments
Performed visual inspection during placement of concrete in the following locations: slab for tank #4 in phase 3.'
. Reinforcing steel was previous'ly inspected on 07/15/08. Concrete was placed by pump and mechanically consolidated.
Cast one (1) set of four (4) (4x8) concrete test cylinders. Contractor was asked to notify our office when additional'
.~ervices are needed. Tothe1tiest of our knowledge the work. inspected above was in accordance. with. the building
. department approved 'design! drawings, . specifications and applicable workmanship. provisions of the International
Building Codes." i' .. .
I
. Tvoe of N\.ateri.aI
Supplier
Mix.#
Slump
Air Content
Ambient Tempe'rature
Material Temperature'
Time Placed
Design Strength (psi)
I
Number of Samples
Total Yardage Placed
Inspector: Verlyn Bearden; ICC# 01080077
CCB# 176269 i
Set #1
ES&G
314045
51/2"
53'
75'
6:45 AM
4,000
4
82
i
If you have any questions regarding this report, please feel free to contact us at 541-746-9649.
Respectfully ~~~~~;
l ofessiona/ ~dustries, Inc.
David Smith
Branch Manager
c: Hexion Specialty Chemicals - greg.wilberger@hexion.com
John'M Pearson
Advanced Mechanical
JHI Engineering c Mike Srriith
,
THIS REPORT IS PROVIDED FOR THE INF(;!RMATION OF THE CLIENT ONLY. THE REPRODUCTION OF THIS REPORT, B'(ANY METHOD, AND ITS TRANSMITTAL TO A THIRD
PARTY, BY ANY MEANS, ~CEPT IN FULL, WITHOUT THE WRITTEN PERMISSION OF PROFESSIONAL SERVICE INDUSTRIES, IS PROHIBITED.
. Professional Service industries, Inc.. 1040-A Shelley Street. Springfield, OR'97477. Phone 541(146-9649. Fax 541n46-7163
I
I