Loading...
HomeMy WebLinkAboutMeeting Packet Planner 9/5/2023DEVELOPMENT ISSUES MEETING FORM APPLICANT: Peacehealth MEETING DATE/TIME: Tuesday, September 26, 2023 11:00 a.m. PLACE: DPW Conference Room 615/616 and Virtual via Zoom CONTACT PERSON: Andy Limbird 726-3784 Current Planning Staff: L Miller, A Limbird, M Rust, K Notary, T Sievers Stan Petroff, City Engineer – DPW Kristi Krueger, AIC Managing Civil Engineer – DPW Ken Vogeney, Emergency Manager – DPW Clayton McEachern, Civil Engineer, Development & Public Works Matt Stouder, Environmental Services Div. Manager/MWMC General Manager Kristi Krueger, Capital Engineering Manager, Development & Public Works Michael Liebler, Transportation Planning, Civil Engineer, Development & Public Works Gilbert Gordon, Deputy Fire Marshal 2, Fire & Life Safety Department Ben Gibson, Maintenance Supervisor, Development & Public Works Eric Adams, Planning, Willamalane Park and Recreation District Ladd Boyce, Keoki Lapina, Springfield Utility Board (Water) Greg Miller, Springfield Utility Board (Water) Sanjeev King, Nick Amann, Springfield Utility Board (Electric) Amy Chinitz, Springfield Utility Board (DWP) Thomas Jeffreys, (EPUD) Emerald Peoples Utility District Michael Wargo, Willamalane Park and Recreation District Matt Caswell, Planning & Development Manager, ODOT, State Highway Division (odotr2planmgr@odot.state.or.us) Brad Rudler, (Electric) Eugene Water and Electric Board Tyler Lindley, Eugene Water and Electric Board Wallace McCullough, (Water), Eugene Water and Electric Board Brett Yancey, Chief Operations Officer; Springfield Public Schools Chris Reiersgaard, Asst. Director of Facilities & Operations; Springfield Public Schools Safe Routes to School, Springfield Public Schools Chris Carpenter, DPW Building Official Andrew Shearer, Police Chief, Police Department Tom Schwetz, LTD, Planning and Development Director Luke Pilon, CenturyLink Jeff Paschall, Community Development Manager – DPW Jeremy Sherer, City Surveyor – DPW Meghan Murphy, Program Coordinator, Environmental Services Sasha Vartanian, (Steve Gallup, cc only) Lane County Transportation - send to LCPWTPReferrals@lanecounty.gov ONLY Marie Longworth, Central Lane Communications 911 Monte Brown, Northwest Natural Gas Jason McDonald, Comcast Cable Water Resource Coordinator, ESD Jamie Porter, Rainbow Water District Kristina Kraaz, City Attorney (Mary Bridget Smith upon specific request) Allie Camp, Economic Development Sarah Weaver, Administrative Specialist (DIM Annexations) Haley Campbell, Senior Planner - Comprehensive Planning Chelsea Hartman, Senior Planner - Comprehensive Planning Please mark who you would like to attend this meeting and return form and file to Shannon. Thanks! Revised: 06/08/2020 DEVELOPMENT INITIATION MEETING DEVELOPMENT AND PUBLIC WORKS DEPARTMENT SPRINGFIELD CITY HALL 225 FIFTH STREET DPW Conference Room 615/616 + Zoom Meeting Date: Tuesday, September 26, 2023 11:00 – 12:00 1. DEVELOPMENT INITIATION MTG #811-23-000200-PRE 811-23-000203-PROJ PeaceHealth Assessor’s Map: 17-03-15-40 TL: 800, 900, 1000, 1100 Address: International Way & Maple Island Way Existing Use: vacant portion of RB annex Applicant has submitted proposal for a 3-lot residential partition Planner: Andy Limbird The Development Issues Meeting informational packet for this meeting is available on-line for you to review or print out @ Laserfiche website: www.springfield-or.gov/weblink8/browse.aspx SITE VICINITY MAP 811-23-000200-TYP4 Development Initiation Meeting 17-03-15-40 TL 800, 900, 1000, 1100 Maple Island Way & International Way Peacehealth Revised 07/20/22 sm1 of 4 City of Springfield Development & Public Works 225 Fifth Street Springfield, OR 97477 Development Initiation Meeting (DIM) Required Project Information (Applicant: complete this section) Prospective Applicant Name: Phone: Company: E-mail: Address: Prospective Applicant’s Rep.: Phone: Company: E-mail: Address: Property Owner: Phone: Company: E-mail: Address: ASSESSOR'S MAP NO: TAX LOT NO(S): Property Address: Size of Property: Acres Square Feet Description of Proposal: If you are filling in this form by hand, please attach your proposal description to this application. Existing Use: # of Lots/Parcels: Avg. Lot/Parcel Size: sf Density: du/acre Prospective Applicant: Date: Signature Print Required Project Information (City Intake Staff: complete this section) Case No.: Date: Reviewed by: Application Fee: $ Technical Fee: $0 Postage Fee: $0 TOTAL FEES: $ PROJECT NUMBER: August 29, 2023 Lifepoint Hospital Development Initiation Meeting Map 17-03-15-40, Tax Lots 0800, 0900, 1000, and 1100 I. THE PROJECT Lifepoint Health and PeaceHealth, propose to develop a 50-bed rehabilitation hospital on the 4.99- acre property identified as Map 17-03-15-40, Tax Lot 1000 and the southern portions of Tax Lots 800, 900, and 1100 (the Subject Property). The proposal is dependent on a Metro Plan and Zone Change that would allow the use on the Subject Property as a permitted use. PeaceHealth, as owner of the Subject Property, has filed an application for a Plan Amendment and Zone Change and is currently in review with the City. Sould the Plan Amendment application be approved, the Refinement Plan designation for the Subject Property will automatically be changed to be consistent with the Metro Plan designation and the proposed zoning for the Subject Property. Outlined below is a brief description of the project and the property, followed by issues and questions. In advance, Lifepoint Health and its development team thank staff for their assistance. II. THE PROPERTY The site is located south of International Way, north of East Game Farm Road and east of Maple Island Road in the Gateway area of Springfield. It is comprised of three full tax lots (Map 17-03-15-40, Tax Lots 800, 900, and 1000) and total approximately 7.22 acres in size. Tax Lot 1100 is 22.55 acres. Tax lots 800, 900, and 1100 are proposed to be the subject of a Property Lot Line Adjustment to reduce the Subject Property to approximately 4.99 acres. The Subject Property abuts office facilities to the east, west and north. To the south is a developed mobile home park with amenities. Subject Property Google Earth March 2023 III. QUESTIONS 1. Land Use. a. Zoning. As noted above, the Subject Property is proposed to receive the necessary Metro Plan Amendment, Refinement Plan Amendment, and Zone Change that will allow the proposed rehabilitation hospital as a permitted use. The proposed zoning will be Community Commercial (CC). The CC zone permits Hospitals and medical services as an allowed right (SDC 3.2.320). The Subject Property is made up of four tax lots of which, after a property line adjustment, will be comprised of one tax lot (southern section) for the Subject Property, a tax lot to the north (remainder of tax lot 800), Tax lot 900 remaining only in the north section between Tax Lots 800 and 1100, and the remainder of Tax Lot 1100 to the east. Lifepoint Hospital Page 2 of 3 Development Initiation Meeting – Questions Map 17-03-15-40, Tax Lots 800, 900, 1000, and 1100 August 29, 2023 The Satre Group  375 West 4th Avenue, Suite 201, Eugene, OR 97401  (541) 686-4540  www.satregroup.com Q: Does staff concur with the Property Line Adjustment Process proposed? Would this be three individual property line adjustment applications or one application for all three adjustments? b. Land Use Application(s). Once the Subject Property has a Community Commercial designation, the logical applications seem to be a Property Line Adjustment, Drinking Water Protection, Site Plan Review, followed by Final Site Plan Review. The applicant believes Property Line Adjustment, Drinking Water and Site Plan Review can be submitted concurrently. Q: Does staff concur with the applications and the order described above? c. Parking Section 4.6.125 has parking requirements but does not specifically list “Hospitals or Rehabilitation facilities”. The applicant is proposing 130 spaces based on past experience for similar-sized prototype facilities. The bicycle parking is listed in SDC 4.6.155 and requires 1 space per 3,000 square feet of floor space. The proposed building will be approximately 42,667 square feet in size requiring 15 bicycle spaces, 13 of which would be long term, sheltered spaces. A bike shelter is proposed with 15 spaces proposed, located 100 feet from the front door, due to the arrangement of the drop-off area. Q: Does staff concur with the parking quantity and bike parking requirements? 2. Utilities. a. Stormwater. Onsite storm water drains to the southwest to a natural low point/ pipe connection running west into Maple Island Road. The applicant plans to maintain this water movement, collecting runoff into a swale/ raingarden along the west property edge before exiting into the existing pipe system. Our proposed storm point of connection is a manhole in the SW corner of the Subject Property. City of Springfield ID’s this manhole as asset ID 41203. Q: Does staff agree with our stormwater strategy? b. Sanitary, Water, Gas and Electric. Sanitary sewer, water, and electric all run along both East Game Farm/ Deadmond Ferry, and Maple Island Road. Gas service and fiber optics are available along Deadmond Ferry Road. The water line in Maple Q: Does staff concur or see any need for any utility extensions? 3. Access. a. Driveway. Access to the Subject Property is proposed via the existing Maple Island Road roundabout on the north and west edge and via a right-in and right-out entrance off East Game Farm Road, on the south end of the property. See Site Plan. Q: Does staff concur with the driveway configurations? Are there any fire/ emergency vehicle access concerns based on the proposed design? 4. Fire. There is a hydrant on Game Farm Road, southwest corner of the lot. This hydrant should count towards the hydrant count needed. We are not sure if there is a hydrant flow test available or if a flow test has been done. Lifepoint Hospital Page 3 of 3 Development Initiation Meeting – Questions Map 17-03-15-40, Tax Lots 800, 900, 1000, and 1100 August 29, 2023 The Satre Group  375 West 4th Avenue, Suite 201, Eugene, OR 97401  (541) 686-4540  www.satregroup.com Q: Does the Fire staff have this information and agree with this? Are there any other fire department concerns? 5. Other Information. Q. Is there anything else that staff would like to share with the applicant, or believes the applicant should be aware of, with respect to this project? This concludes the applicant’s Development Initiation Meeting questions. In advance the applicant wishes to express their appreciation of staff time and effort in preparing responses to these questions. Sincerely, John Anderson John Anderson, ASLA, Principal The Satre Group August 25, 2023 LIFEPOINT/PEACEHEALTH HOSPITAL Map 17-03-15-40, Lots 0800, 0900, 1000, and 1100 Land Use Planning Analysis The key to successful property development in Oregon is thorough research and analysis of prospective regulations and requirements. This is followed by the planning, design, and regulatory approval processes. Success comes by taking things one step at a time; each step providing clarity and focus for the next round of activity. The first step is research and analysis, where land use requirements are identified and a foundation for the next steps in the process is established. Presented below are the results of this initial land use analysis. This analysis is based on available public data. It documents known or discovered existing conditions and potentially applicable land use regulations. It is based on what is known at this time. Additional data may be discovered as the project progresses, resulting in modifications to what is presented herein. I. BACKGROUND A. Planning Context Local long-range land use is governed by the Eugene-Springfield Metropolitan Area General Plan (Metro Plan); often supplemented with a more specific refinement plan and/or neighborhood plan. The Metro Plan and if applicable, refinement plan, is then followed by site-specific zoning. Sometimes, zoning is comprised of base zoning and additional overlay zones. For the subject property, the Metro Plan, Gateway Refinement Plan, and Springfield Zoning Map are applicable to the subject property. Additional Planning documents, including the Springfield Transportation System Plan, the Springfield Stormwater Facilities Master Plan and Wastewater Master Plan also apply. Excerpt Springfield Zoning Map January 2023 Subject Property Planning and Zoning Metro Plan Designation Campus Industrial Refinement Plan Designation Campus Industrial Base Zone Campus Industrial Overlay Zone Floodplain Development, and Drinking Water Protection Lifepoint/PeaceHealth Hospital Page 2 of 9 Land Use Planning Analysis Map 17-03-15-40, Lots 0800, 0900, 1000, and 1100 August 25, 2023 The Satre Group  375 West 4th Avenue, Suite 201, Eugene, OR 97401  (541) 686-4540  www.satregroup.com B. Physical Setting The site is located south of International Way, north of East Game Farm Road and east of Maple Island Road in the Gateway area of Springfield. It is comprised of three full tax lots (Map 17-03-15- 40, Tax Lots 800, 900, and 1000) and total approximately 7.22 acres in size. Tax Lot 1100 is 22.55 acres. Tax lots 800, 900 and 1100 are proposed to be the subject of a Property Lot Line Adjustment to reduce the Subject Property to approximately 4.99 acres. The site abuts office facilities to the east, west and north. To the south is a developed mobile home park with amenities. Subject Property Google Earth March 2023 C. Development Objective The applicant, Lifepoint Health and PeaceHealth, propose to develop a 50-bed rehabilitation hospital on the 4.99-acre property identified as Map 17-03-15-40, Tax Lot 1000, and the southern portions of Tax Lots 800, 900 and 1100 (the Subject Property) located at the corner of East Game Farm and Maple Island. II. LAND USE ANALYSIS A. Regulatory Review The following plans, documents and database sources were included in this review: 1. Planning and Zoning. a. Aerial Photographs (Google Earth). b. Regional Land Information Database (RLID). c. Eugene – Springfield Metropolitan Area General Plan (Metro Plan). d. Gateway Refinement Plan. e. Springfield Zoning Map. 2. Transportation. a. Eugene-Springfield Metropolitan Area Transportation Plan (TransPlan). b. Springfield 2035 Transportation System Plan. c. Lane Transit District (LTD) System Map. 3. Utilities. a. Springfield Stormwater Facilities Master Plan. b. Springfield Wastewater Master Plan. c. Springfield Storm and Sanitary Infrastructure. d. Springfield Wellhead Protection Areas Map. e. Springfield Utility Board (SUB) – Water and Electric Infrastructure. 4. Natural Resources. a. Springfield Natural Resources Study Report. b. Springfield Floodplain Floodway Map. Lifepoint/PeaceHealth Hospital Page 3 of 9 Land Use Planning Analysis Map 17-03-15-40, Lots 0800, 0900, 1000, and 1100 August 25, 2023 The Satre Group  375 West 4th Avenue, Suite 201, Eugene, OR 97401  (541) 686-4540  www.satregroup.com 5. Parks and Open Space. a. Willamalane Park and Recreation District Comprehensive Plan – Project Maps. 6. Development Standards. a. Springfield Development Code – Land Use Districts (Chapter 3), Development Standards (Chapter 4), and Land Use Process and Applications (Chapter 5). B. Findings 1. Planning and Zoning. a. Jurisdiction: City of Springfield b. Metro Plan: Campus Industrial c. Refinement Plan: Campus Industrial d. Base Zoning: Campus Industrial e. Overlay Zoning: Drinking Water Protection and Floodplain Development f. Map: 17-03-15-40 g. Tax Lots: 1000 and portions of 800, 900 and 1100 h. Acreage: 4.99 acres after adjustment Tax Lot Maps RLID 2023 2. Transportation. a. Metro Area TransPlan. The metro area’s adopted transportation plan, The Eugene – Springfield Transportation System Plan (TransPlan) does not include projects abutting the subject property but does include a few projects nearby the Subject Property. These projects are described as a new Collector Street in the vicinity of the nearby PeaceHealth Riverbend medical campus (Projects 715, 721, and 756) and an Urban Standards project improving an existing nearby street (Project 724). Excerpt Transportation System Plan City of Springfield 2020 b. City of Springfield 2035 Transportation System Plan. The City of Springfield’s transportation plan adopted in 2014 and updated in 2020, does not include any projects abutting the subject property. As with TransPlan, the Springfield TSP includes projects on nearby streets (new Minor Collector projects R-5 and R-6 at the nearby PeaceHealth RiverBend campus). These improvements will be implemented as development occurs. c. Street Classification. Lifepoint/PeaceHealth Hospital Page 4 of 9 Land Use Planning Analysis Map 17-03-15-40, Lots 0800, 0900, 1000, and 1100 August 25, 2023 The Satre Group  375 West 4th Avenue, Suite 201, Eugene, OR 97401  (541) 686-4540  www.satregroup.com There are three abutting streets – International Way (north), East Game Farm Road (south), and Maple Island Road (west). Springfield’s Street Classification Map identifies International Way and East Game Farm Road as collector streets and Maple Island Road as a local street. The street classification carries with it a standard right-of-way (ROW). The standards are as follows: Street Classification Existing ROW Max / Min ROW Existing Curb- to-Curb Max / Min Curb-to-Curb International Way Major Collector 72 feet 72 / 56 feet 48 feet 52 / 36 feet East Game Farm Rd Major Collector 72 feet 72 / 56 feet 48 feet 52 / 36 feet Maple Island Rd Major Collector 50 feet 72 / 56 feet 48 feet 52 / 36 feet d. Public Transit. The metro area’s public transit system, Lane Transit District (LTD), provides service near the development via the EMX Springfield route. LTD’s International Way route is just to the north of the subject property with a transfer station located in the center of International Way. There is a flashing beacon pedestrian crosswalk to the island and a dedicated bus only lane in each direction. e. Bicycle and Pedestrian Facilities. There are setback sidewalks but no bike lanes on International Way and Maple Island roads. East Game Farm Road has bike lanes. Excerpt LTD System Map 2019 3. Utilities. a. Stormwater and Wastewater Master Plans. The Subject Property is located in the North Gateway Stormwater Drainage Basin. The Springfield Stormwater Facilities Master Plan identifies one capital improvement project, “Low Priority CIP 43,” to address current issues around water quality from the campus industrial area. (The stormwater system for the subject property and others along International Way flooded in 1996.) Capital Improvement Map Excerpt (Fig. 5-1) Stormwater Facilities Master Plan City of Springfield 2008 System Improvements Map Excerpt (Fig. 5-3) Wastewater Master Plan City of Springfield 2008 b. Stormwater and Wastewater Infrastructure. Lifepoint/PeaceHealth Hospital Page 5 of 9 Land Use Planning Analysis Map 17-03-15-40, Lots 0800, 0900, 1000, and 1100 August 25, 2023 The Satre Group  375 West 4th Avenue, Suite 201, Eugene, OR 97401  (541) 686-4540  www.satregroup.com Stormwater service is available to the Subject Property through existing lines in International Way (15-inch trunk line), in Game Farm Road (15- inch trunk line), and in Maple Island Road (a 15-inch trunk line that extends along the western boundary to the tax lot to the north. Wastewater service is also available to the Subject Property via International Way (8-inch line), Game Farm Road (10-inch line), and Maple Island Road (10-inch line). c. Wellhead / Water Quality Protection The subject property is located in the Sports Way wellfield in the 2-year Time of Travel Zone (TOTZ). Any development will require approval of a Drinking Water Protection application. Wellhead Protection Areas Map Excerpt City of Springfield and Springfield Utility Board January 2013 4. Natural Resources. Lifepoint/PeaceHealth Hospital Page 6 of 9 Land Use Planning Analysis Map 17-03-15-40, Lots 0800, 0900, 1000, and 1100 August 25, 2023 The Satre Group  375 West 4th Avenue, Suite 201, Eugene, OR 97401  (541) 686-4540  www.satregroup.com a. The northern section of the Subject Property is in the Special Flood Hazard Area — Floodplain Zone A (the blue hatch). Zone A is the 100-year flood plain with base flood elevation determined. A larger portion (the southern section and Subject Property) of the site is in Zone X, areas of 500-year floodplain (the yellow hatch). Excerpt Floodplain Floodway Map City of Springfield 2019 5. Parks and Open Space. Willamalane Park and Recreation District does not include projects in the vicinity of the subject property. 6. Development Standards. The Springfield Development Code (SDC) governs all lands within Springfield’s city limits and its urban services area. All six chapters apply to the Subject Property, but three in particular, detailed here and including Land Use Districts (Chapter 3), Development Standards (Chapter 4), and the Development Review Process and Applications (Chapter 5), are particularly applicable. As land use applications are prepared, a detailed review of the Code will be required. A brief overview of relevant sections follows. NOTE: Always refer to the full code when generating plans and completing applications. a. Land Use Districts (Chapter 3). Within Chapter 3, the project will need to comply with SDC 3.2.300 Commercial Districts, SDC 3.3.200 Drinking Water Protection Overlay District, and 3.3.400 Floodplain Overlay District. SDC 3.2.300 Commercial Districts. o 3.2.320 Schedule of Use Categories (Table). Hospital and associated uses are a permitted use in the Community Commercial zone. o 3.2.325 Base Zone Development Standards (Table). The following Base Zone Development Standards apply: ­Minimum Development Area: 6,000 sq. ft. ­Minimum Street Frontage: 50 ft ­Maximum Lot Coverage: Limited by requirements in other sections of the code. ­Front Yard, Street Side Yard, and Through Lot Rear Yard Setback: 10 ft - Parking, Driveway, and Outdoor Storage: 5 ft ­Building separation from other Buildings within the CI District: 20 ft ­Maximum Building Height: none, except next to residential ­Footnotes: Lifepoint/PeaceHealth Hospital Page 7 of 9 Land Use Planning Analysis Map 17-03-15-40, Lots 0800, 0900, 1000, and 1100 August 25, 2023 The Satre Group  375 West 4th Avenue, Suite 201, Eugene, OR 97401  (541) 686-4540  www.satregroup.com (4) Setbacks must be landscaped. (6) Incidental equipment may exceed height standards.\ 3.3.200 Drinking Water Protection Overlay District. o 3.3.210 Applicability. As of May 15, 2000, all areas within specified wellhead TOTZ automatically are rezoned to add the DWP Overlay District to the underlying zoning district. The areas to which the DWP Overlay District is applied are shown on the Drinking Water Protection Area Maps on file in the Development Services Department and incorporated in this Section by reference. As shown above, the subject property meets this standard as it is in a wellhead TOTZ. If the standard is met, see remainder of Section 3.3-200 for requirements. 3.3.400 Floodplain Overlay District. o 3.3.410 Applicability. The FP Overlay District applies to all areas of special flood hazard. As shown above, the subject property meets this standard as it is in a special flood hazard area. If the standard is met, see remainder of Section 3.3-400 for requirements. b. Development Standards (Chapter 4). SDC Chapter 4, Development Standards, addresses general development standards that could apply, depending on a particular proposal, to any property in Springfield. The following Sections apply to the project. See the full text of the Code for specific requirements. 4.2.100 Infrastructure Standards – Transportation. o 4.2.105 Public Streets. o 4.2.120 Site Access and Driveways. o 4.2.125 Intersections. o 4.2.130 Vision Clearance. o 4.2.135 Sidewalks. o 4.2.140 Street Trees. o 4.2.145 Lighting Standards. 4.3.100 Infrastructure Standards – Utilities. o 4.3.105 Sanitary Sewers. o 4.3.110 Stormwater Management. o 4.3.120 Utility Provider Coordination. o 4.3.125 Underground Placement of Utilities. o 4.3.130 Water Service and Fire Protection. o 4.3.140 Public Easements. 4.4.100 Landscaping, Screening and Fence Standards. o 4.4.105 Landscaping. o 4.4.110 Screening. o 4.4.115 Fences. 4.5.100 On-Site Lighting Standards. o 4.5.105 Purpose and Applicability. o 4.5.110 Illumination and Height. 4.6.100 Vehicle Parking, Loading and Bicycle Standards. o 4.6.115 Parking Lot Design. o 4.6.120 Parking Lot Improvements. o 4.6.125 Parking Space Requirements. o 4.6.135 Loading Areas – Facility Design and Improvements. o 4.6.145 Bicycle Parking – Facility Design. o 4.6.150 Bicycle Parking – Improvements. Lifepoint/PeaceHealth Hospital Page 8 of 9 Land Use Planning Analysis Map 17-03-15-40, Lots 0800, 0900, 1000, and 1100 August 25, 2023 The Satre Group  375 West 4th Avenue, Suite 201, Eugene, OR 97401  (541) 686-4540  www.satregroup.com o 4.6.155 – Bicycle Parking – Number of Spaces Required. One (1) space per 3,000 square feet of floor area. c. Development Review Process and Applications (Chapter 5). SDC Chapter 5, The Development Review Process and Applications contains requirements applicable to all land use proposals in Springfield’s jurisdictions. Those applicable to the subject property include the following. 5.1.100 The Development Review Process. o 5.1.120 Pre-Development Meetings. 5.16.100 Property Line Adjustments 5.17.100 Site Plan Review. III. LAND USE APPLICATIONS Land use approval is required prior to the issuance of any building permits. Required land use applications for the subject property, in sequential order, are as follows. A. Development Issues Meetings (SDC 5.1.120A) 1. A Development Issues Meeting (DIM) is required for certain land use applications. For other applications, a Development Issues Meeting is voluntary. (It is required for Site Plan Review applications). Regardless of whether required or voluntary, a DIM is an excellent opportunity to present a development proposal and ask questions of city staff prior to generating a particular application. The meeting is tailored to address specific issues or concerns. 2. As part of the Development Issues Meeting process, the City of Springfield distributes application material to key staff that review, prepare for, and attend the meeting. 3. As this is not a land use decision, no ‘decision’ is issued. However, there is a take-away of city responses to submitted questions. 4. Meetings are generally scheduled 10 to 15 working days from application submittal. B. Property Line Adjustments (SDC 5.16.100) 1. A single Property Line Adjustment is a Type I land use application that provides a process for the relocation of a common boundary between two abutting properties. It is a Planning Director decision and includes public notice, but no public hearing. C. Site Plan Review (SDC 5.17.100) 1. Site Plan Review is a Type II land use application that provides a process to regulate the manner in which land is used and developed, ensuring compliance with various public policies and objectives. In Springfield, Site Plan Review is required for most new developments, additions, or expansions. It is a Planning Director decision and includes public notice, but no public hearing. D. Final Site Plan Review (SDC 5.17.135) 1. The Final Site Plan submittal incorporates all approval conditions from the Site Plan Review decision into a revised set of plans. Upon approval of Final Site Plan review, the city executes a Development Agreement which is then signed by the applicant. E. Drinking Water Protection (SDC 3.3.200) 1. The Drinking Water Protection (DWP) Overlay District was established to protect aquifers used as potable water supply sources from contamination. DWP requirements establish procedures and standards for the physical use and storage of hazardous or other materials harmful to groundwater by requiring development approval for new and existing land uses. Drinking Water Protection is a Type I procedure – no public notice and staff decision. F. Floodplain Development (SDC 3.3.400) Lifepoint/PeaceHealth Hospital Page 9 of 9 Land Use Planning Analysis Map 17-03-15-40, Lots 0800, 0900, 1000, and 1100 August 25, 2023 The Satre Group  375 West 4th Avenue, Suite 201, Eugene, OR 97401  (541) 686-4540  www.satregroup.com 1. The Floodplain (FP) Overlay District was established to promote public health, safety, and general welfare, and to minimize public and private losses due to flood conditions in specific areas. Development proposals must follow specific standards, including minimum elevations. Floodplain Development is a Type I procedure – no public notice and staff decision. IV. PRELIMINARY SITE PLAN A preliminary site plan has been generated for the proposed development. A site plan has immense value in assisting with initial land use analysis and in providing an explanation and asking questions in a pre-application meeting. V. ATTACHED INFORMATION 1. Planning and Zoning. a. Google Earth – Aerial Photograph with Site Boundaries. b. Regional Land Information Data Base (RLID) – Tax Lot Reports and Tax Lot Map. c. MetroPlan - Map. d. City of Springfield – Refinement Plan Map. e. City of Springfield – Base Zoning. 2. Transportation. a. City of Springfield – TSP 20-Year Improvement Projects: As Development Occurs b. City of Springfield – TSP Recommended Frequent Transit Network 3. Utilities. a. City of Springfield – Wellhead Protection Map. b. City of Springfield – Existing Stormwater and Wastewater Infrastructure Map. 4. Natural Resources. a. City of Springfield – Floodplain Floodway Map. VI. CONCLUSION AND RECOMMENDATION The above information represents a brief outline of known and discovered applicable planning, zoning, and site development requirements for the contemplated development of the Subject Property. It is recommended that a pre-application meeting (Development Initiation Meeting) be scheduled and undertaken to clarify and/or confirm the findings herein. We hope this initial land use analysis proves helpful. Our office is available to discuss these findings, provide additional graphics upon request, or assist with additional project needs1. Sincerely, Dan Halverson Senior Planner The Satre Group 1 The information presented herein is the professional opinion of the primary author based on interpretation of applicable land use codes within a particular jurisdiction. It is limited to the information as interpreted to the best of our abilities and is not warranted beyond this opinion. Opinions in no way represent or imply information, decisions, opportunities, potentialities, or outcomes not in control of the author. Google Aerial Tax Map Metro Plan Map I-5I-1 05 5TH STQ S TGATEWAY STBIKE PATH HARLO W RD W N ST V ST W M ST BELTLINE RD FAIRVIEW DR U ST 2ND STARCADIA DRW CENTENNIAL BLVD P H E A S A N T B LV D CHAD DR CALVIN STSHELLEY ST PI ONEER PARKWAY EASTPI ONEER PARKWAY WEST9TH STMILL STINTERNATIONAL WAY LAURA STCENTENNIAL BLVD7TH STM C KENZIE VIEW DR WATER ST8TH STON RAMP PRESCOTT LNKELLY BLVDN GAME F ARM RD3RD STI-5 OFFRAMPMARTI N LUTHER KI NG J PKWYMANOR DRWAVERLY ST1ST STT ST C R E S C E N T A V E REGENCY DR S ST M ST HAYDEN BRIDGE WAY N GARDEN WAYOLD COBURG RDWOODLANE DR LOCHAVEN AVE W Q ST PRIV ATE BEVERLY ST6TH STWILLAKENZIE RD P RIVATE RDASPEN STORIOLE STS GARDEN WAYDEAD M O N D FERRY RDW K ST GAME FARM RD I-5 ONRAMPMENLO LP DON STLINDALE DRVICTORIAN WAYM ALLAR D A V E KINSROW AVEPRESIDENT STGATEWAY LP OX B O W W A YCARDINAL WAY VILLA WAYTAMARACK STBERKSHIRE STDORNOCH STSHERATON DRBAL DY V I E W L NANDERSON LNSHADYLANE DRSEQUO IA A V E W Q U I N A L T S T L ST ETHAN CT WESTERN D R DARLENE AVE OAK D A L E A V E SEWARD AVE VAN DUYN STPANDA LPSUSSEX ST MANSFIELD ST SCOTTS GLEN DR N ST LINDEN A V E FLAMINGO AVE WAYSIDE LN1ST P LGREENVALE DR NICHOLA S D R ALLEN AVE MA H LON AVE CO M M O N S DR NOVA STSPORTS WAYCLOVERLEAF LP NANCY AVE COLONIAL DR KRUSE WAY B A IL E Y L N KIN G EDWAR D S C T PART RID G E W A Y R STHONEYSUCKLE LNCOTTONWOOD AVE MA R T IN L U T H E R K IN G J B LV D ROSEMONT WAY SWEET GUM LNPOSTAL WAYCHESAPEAKE DRLORD BYRON PLRIVERBEND DRR A L EIG H W OOD AVE W L STSAINT CR O IX S THAMPTO N WAY CLEAR VUE LNVAL L EY F ORGE DRPRIVATE R O A D ELWING AVE HARTMAN LNHAYDEN BRIDGE PL WESTWAR D HO AVE D O UTHIT DR REGENT AVEKINGS NORTH STSIS T E RS VIEW AVE NORTH R I D G E A V E HICK ORY AVE GROVEDALE DRS A IN T THOMAS STBROADWAY S H A D Y LPWINC H E S T E R WAY MARCHE CHASE DRSAINT ST PLEASANT ST CAMBRIDGE ST KODIAK STPARISH ST W A Y S IDE LPCH A T E A U M EADOWS DRKENR A Y L PRIDGLEY B L V D ELLIE LNH O S A N N A L N ROYALDEL L N RAINBOW DRED IE DR W OLYMPIC ST L ORN E LP FENST ER STPINEDALE AVE PRASAD CT HATHAWAY AVE S C L O V E R L E A F L P BROOKDALE AVE SPRINGDALE AVE DONNELLY DRR O Y A L CARIBBEAN WAYMCPHERSON PLU N N A M E D K E E L E R A V E PRESTON ST MAPLE ISLAND RDFIESTA DRMOFFITT LN P R I VATE P R IVATES STSPORTS WAYM ST PRIVATE RD 1ST ST6TH ST7TH STW OLYMPIC ST PR IVATE HARLOW RD T STPRIVATE DON STS ST B I K E P A T HPRIVATE RDI-5L STGAME FARM RDPRIVA TEBI KE PATHPRI VATE ROADLAURA ST8TH STV ST PR IVAT E W QUINALT S T3RD STBIKE PATHPRIVATEI -5 O FFRAMPLOCHAVEN AVE PR IVATEPRIV A T E 8TH STON R A M P 6TH STPRIVATE V ST GATEWAY REFINEMENT PLAN April 2008 Springfield,OR There are no warranties that accompany this product. Users assume all responsibility for any loss or damage arising from any error, omission or positional inaccuracy of this product. I Mc Kenzie River Legend CI -Campus Industrial LMI - Light-Medium Industrial NC - Neighborhood Commercial Community Commercial LDR - Low Density Residential MDR - Medium Density Residential HDR - High Density Residential PLO - Public Land & Open Space GO - General Office MU - Mixed Use - LMI/CC MU - Mixed Use 0 1,000 2,000Feet Zoning Map Stormwater Map Wastewater Map Flood Zone