APPLICANT: Village Park Apartments
MEETING DATE/TIME: Thursday, October 14, 2021, 1:30 — 2:30
PLACE: Virtual via Microsoft Teams
CONTACT PERSON: Melissa Carifio
_X_ Current Planning Staff: L Miller, A Limbird, M Rust, D Larson, M Carifio
Jeff Paschall, City Engineer, DPW
_X_ Kyle Greene, Managing Civil Engineer—DPW
Ken Vogeney, Emergency Manager (DPW)
_X_ Clayton McEachem, Civil Engineer, Development & Public Works
Matt Stouder, Environmental Services Div. Manager/MWMC General Manager
Kristi Krueger, Rincipal Engineer, Development & Public Works
_X_ Michael Lieb@. ler, Transportation Planning, Civil Engineer, Development Public Works
_X_ Eric Phillips -Meadow, Deputy Fire Marshall 2, Fre & Life Safety Department
Ben Gibson, Maintenance Supervisor, Development & Public Works
Eric Adams, Planning, Willamalane Park and Recreation District
_X_ Ladd Boyce, Keoki Lapina, Springfield Utility Board (Water)
_X_ Greg Miller, Springfield Utility Board (Water)
_X_ Sanjeev King, Nick Amann, Springfield Utility Board (Electric)
Amy Chinitz, Springfield Utility Board (DWP)
Thomas Jeffreys, (EPUD) Emerald Peoples Utility District
Michael Wargo, Willamalane Park and Recreation District
_X_ Matt Caswell, Planning & Development Manager, ODOT, State Highway Division
(odotr2planngr@odot.smte.or. us)
Brad Rudler, (Electric) Eugene Water and Electric Board
Wallace McCullough, (Water), Eugene Water and Electric Board
Brett Yancey, Chief Operations Officer; Springfield Public Schools
Chris Reiersgaard, Asst. Director of Facilities @. Operations; Springfield Public Schools
Safe Routes to School, Springfield Public Schools
_X_ Chris Carpenter, DPW Building Official
Rick Lewis, Police Chief, Police Department
Tom Schwetz, LTD, Planning and Development Director
Luke Pilon, Centuryl-ink
Tom Boyatt, Community Development Manager, DPW
_X_ Jeff Paschall, AIC DPW City Surveyor
Sunny Washburn, Program Coordinator, Environmental Services
Sasha Vartanian, Lane County Transportation (Steve Gallup, oc only)
Tom Boyatt, Interim Development and Public Works Director
Marie Longworth, Central Lane Communications 911
Monte Brown, Northwest Natural Gas
Jason McDonald, Comcast Cable
Water Resource Coordinator, ESD
Jamie Porter, Rainbow Water District
Kristina Kraaz, City Attorney (Mary Bridget Smith upon specific request)
Courtney Griesel, Senior Management Analyst (EDM)
Brenda Jones, Administrative Specialist (DIM Annexations)
Please mark who you would like to attend this meeting and return form and
file to Shannon. Thanks!
Revised: 86/88/2828
DEVELOPMENT ISSUES
MEETING
DEVELOPMENT AND PUBLIC WORKS DEPARTMENT
SPRINGFIELD CITYHALL
225 FIFTH STREET
nD1417 C...�615,41
Meeting Date; Thursday, October 14, 2021 1;30-2;30
1. DEVELOPMENT ISSUES MTG #811 -21 -000251 -PRE Village Park Apartments
Assessor's Map: 17-02-33-31 TL 4400 & 4404
Address: 5236 Main Street
Existing Use: multi -unit complex / vacant parcel
Applicant has submitted proposal to construct maintenance shop and office.
Planner: Melissa Carifio
The Development Issues Meeting informational packet for this meeting is available on-line for
you to review or print out @ Laserfiche website: www.springfield-or.gov/weblink8/browse.aspx
VICINITY MAP
811 -21 -000251 -PRE Development Issues Meeting
17-02-33-31 TL 4400 & 4404
5236 Main Street
Village Park Apartments LLC
City of Springfield
Development & Public Works
225 Fifth Street
Springfield, OR 97477
Development Issues Meeting (DIM)
SPRINGFIELD
M
Required Project Information (Applicant: complete this section)
Prospective
Applicant Name: Village Park Apartments, LLC Phone- 541-344-0028
Company: Bunting Management Group Fax:
Address: 2677 Willakenzie Road #3 Eugene OR 97401
Prospective Shane McCloskey
Applicant's REP.:
Phone: 541-338-8544
Company: Dustrud Architecture, p.c.
Fax•
Address: 1699Pearl Street I Eugene OR97401 /
Property Owner: Village Park Apartments, LLC
Phone: 541-3440028
Company: Bunting Management Group
Fax'
Address: 2677 Willakenzie Road #3 Eugene OR 97401
ASSESSOR'S MAP NO: 17023311 I N- 'J3 �
TAX LOT NOS : 4400 and 4404
Property Address: 5236 Main Street I Springfield OR 97478
Size of Property: 0.52 AcresitSquare Feet
Description of If you are filling in this form by hand, please attach your proposal description to this application.
Pro oral• parking lot rehab with new One -Way traffic, Exit apron & prefab maintenance shop and office, Type V const.
Existin Use: tax lot 4400 is currently a vacant lot
# of Lots Parcels: N/A
Av . Lot Parcel Size: N/A Sf
Densi 29 du acre
Prospective
<ny
Applicant:�—Date: September 20, 2021
Signature
Shane McCloskey Dustrud Architecture
Print
Required Project Information (City Intake Staff., complete this section)
Case No.: %I I _2 - L?o0"2-St- PRS Date: 2E-ff� 74 1 Z9 I Reviewed by:
Application Fee: 16 10D
Technical Fee: 0
Posta a Fee: 0
TOTAL FEES: &q& -01b PR03ECT NUMBER:
Revised 5/21/13 KL 1 of 3
AN
DUMUD
architecture
1699 Pearl Street I Eugene OR 974011541.338-85441 dustrudarchitecture.com
September 20, 2021
Development Issues Meeting for 5236 Main Street ( Springfield, Oregon
Proposed Scope of Work at Village Park Apartments IVPAI:
- Replacement of (e) parking lot with minor additions & upgrades for Fire & Stormwater.
- Development of adjacent parcel for added parking, outdoor amenities & exit apron onto Main St.
The (e) Parking lot of the VPA is in need of replacement due to its 1964 installation. The (e) stormwater
piping, of the same vintage, and should be replaced while the parking lot is pulled up. Staff had previously
directed the catch basins to be upgraded to 2 stage units with approved filtration as well. This has been
scheduled for mid-November.
At some point afterwards, the adjacent parcel will be developed as additional residential parking with
outdoor picnic and gardening amenities, a stormwater treatment facility tied to the rehabbed piping & a new
Exit driveway onto Main Street. The (e) lot and proposed lot would be connected and used as one U shaped
circulation path. The proposed Exit would beget the (e) access point to be the dedicated Entry. The VPA and th[
future parking lot are two separate tax lots, thus the 2 aprons should be allowable, yet ODOT may have more
direction to provide for development. At a previous DIM, Staff advised that the Sites be tied together with a
deed covenant eliminating the option to sell the parcels individually, and the Owner agreed it would preserve
the intent of the development.
The (e) parking lot does not conform to the current Fire Code as the depth is greater than 150' from Main
with no option to turnaround. Once both lots have been revived and developed the Owner would like to
eliminate some spots from the center parking isle to accommodate a Fire truck hammerhead turnaround
navigable from either the Entrance or Exit. As no parking stalls can impede the clear turning radius and the lot
currently allows parking in this area, a small planting island is proposed for the semi -circular areas to clearly
delineate the fire isle. Alternately the area could be delineated with striping but current parking patterns could
persists despite the lines in the AC. Staff input on best practices to preserve the hammerhead clearances is
welcomed.
The dedicated Ingress & Egress will make the lot and Main Street safer for residence and drivers.
Tenants within the facility will have directional flow of traffic, significantly reducing the opportunity for
collisions. Currently traffic shares the same apron which is situated <10' from a 2 story building to the East
adjacent to the West bound lane of Main St.. Exiting the parking lot eastbound while a car enters from that
eastbound lane requires one party to wait. With a'-40' buffer between one way traffic onto and off of Main
Street traffic can proceed without major pause nor conflict.
Previous development proposals for the empty lot located a wood framed Maintenance Shop in the SW
corner where parking spot 36-38 now appear. The Owner wanted to preserve the 'open lawn' feel of the
gardening and playground amenities by placing a prefabricated 'Tuff Shed' (24'x30') toward the North PL to the
West behind the (e) apartments. They intend to have a WC, lavatory and utility sink within the shed, tying into
the (e) apartment sanitary system.
DIM QUESTIONS for 5236 Main Street to City Staff: 9/20/21
1. How does Staff view the final parking lot configuration as it relates to the added planting isle in the (e)
lot, developed to clearly set the fire isle aside from parking? Would this trigger other development
requirements in the (e) lot beyond the intended rehabbed stormwater piping and 2 stage catchment
basins? Is a permit required for replacement piping that maintains the drain locations, routes, and
destination?
2. Does the City or ODOT take issue with proposed one-way traffic where the (e) apron is ENTER & the
proposed Western apron is EXIT? The Entry will have 50' queuing lane before the barrier arm security
gate, traffic control arm which will be active after 6PM until 7AM. The Exit drive will have the same
barrier arm security gate near the ROW to clearly delineate the Entry from the EXIT.
3. Stormwater: Is the removal of the AC between the northern most units an acceptable offset to add a
drive isle to the face of the shop?
4. Stormwater: Is it acceptable to collect the 'proposed' lot runoff in a swale tied to the (e) stormwater
system, which will be re-habbed at the time of AC maintenance in November?
5. Wastewater & Supply: is it acceptable to connect the maintenance shed plumbing to the existing
apartments supply and wastewater?
6. Fire: Does the Site Plan meet the requirements for fire equipment/access? How does the development
need to address fire access and circulation once the two lots are combined in a U -pattern?
7. What does City Staff require for the placement of a prefabricated "Tuff Shed" Maintenance shop
(24"x30') behind the (e) apartments 5' from the N PL?
Dustrud Architecture, p.c. Page 2 of 2