HomeMy WebLinkAboutStudies APPLICANT 4/2/2021STORMWATER ANALYSIS REPORT FOR: NINTH ST PROPERTIES, LLC 431 35TH STREET Map 17-02-31-24, Tax Lots 11900 Springfield, OR 97478 (Pre -Submittal Case # Prepared by %WENGINEERS. CIVIL STRUCTURAL BUILDING DESIGN SURVEYING LAND USE PLANNING 2350 Oakmont Way, Suite 105 Eugene OR 97401 (547)485-8383 Contact: Michael A Cox, PE Job #20-7774 RENEWS: � Based on the City of Springfield Engineering Design Standards and Procedures Manual —2012 City of Eugene Stormwater Management Manual 2014 Contents ProjectOverview............................................................ ...................................... 1 Methodology.........................................................................................................3 Analysis................................................................................................................3 Engineering Conclusions......................................................................................4 Attachments: Appendix A: Stormwater Scooping Sheet Appendix B: Stormwater Plan Appendix C: Stormwater Design Calculations Appendix D: Web Soil Survey Map Appendix E: Geotechnical Infiltration Report Appendix F: Stormwater Planting Schedule Exhibit Project Overview Location: 431 35" Street, Springfield, OR. Map and Taxlot: Lot 11900 of Assessor's Map 17-02-31-24 Vicinity Map: dWl s EF, Efl [n Tyson Ped r ZiN041 _ _ fo�-yc Taquerie.p Development: The property is a 0.93 acre parcel of land comprised of Tax Lot 11900 of Lane County Assessor's Map 17-02-31-24. The subject property is currently under residential use and developed with an existing single-family dwelling and detached garage to remain (431 35th Street). The subject property is bounded on the West by 35th Street, and is bounded on the North, South and East by previously developed private properties. Said adjacent private properties are under separate ownership. The subject property is currently designated "Low Density Residential" per the Comprehensive Plan, and is currently zoned LDR Low Density Residential. The applicant desires to subdivide the subject property into six lots, each of which is proposed to accommodate one single-family dwelling for a total of 6 dwelling units following subdivision approval. This results in a proposed net density of 6.45 dwelling units per acre, which complies with the permitted density range of 6 to14 dwelling units per net acre within the LDR zoning district per Section 3.2-205 of the Springfield Development Code (SDC). The project site lies within 10 year travel time of the Maia potential wellhead (Wellhead Map - 2013 City of Springfield Development & Public Works — Technical Services Division) with the Q Street Floodway subbasin. The public stormwater follows the drainage system in catchments 10/135. According to the 10 -Year Future model (Figure 3-10 of the Stormwater Facility Master 1 Plan — 2008), the nearest major piped system has no excess capacity. The stormwater scoping sheet, dated 10/21/2020 indicates that detention is not applicable (See Appendix A). Permits required for the project include local building, electrical, and mechanical. Stormwater discharge is covered under the City of Springfield MS4 NPDES permit. Methodology The downstream capacity of the public system is not sufficient. New impervious surface runoff will not be detained per the Stormwater Scooping Sheet (Appendix A). The stormwater treatment facility will treat all proposed impervious surfaces, with design overflow directed to the existing stormwater system located to the north of the property. Facility layout can be seen on plans found in Appendix B and a planting exhibit (Appendix F) SITE SOIL CLASSIFICATIONS The entirety of the soil at the project site is hydrologic soil group D. Infiltration testing performed by K&A Engineering (Project: 20066) produced no infiltration over a 24 hour period. Infiltration will not be used on this site. (See Appendix E: Geotechnical Infiltration Report) 2226A—Awbrig-Urban Land Complex Hydrologic Soil Group D (See Appendix D: Web Soil Survey Map, USDA NRCS Web Soil Survey, and accessed 3/30/21) STORMWATER BMP— Stormwater planters will be used to treat the complete runoff from the property. Three planters located on the north side of the access road will be used to collect all runoff. Lott and the existing garage on Lot 6 shall be treated at Planter 1, Lots 2 & 5 shall be treated at Planter 2, and Lots 3&4 shall be treated at Planter 3. A portion of the access road will be divided between the three planters for treatment. Planters were designed using the presumptive method using a maximum buildout area including roof and driveway surfaces. Actual size of planters exceeds the required area of the proposed planters. Individual lots shall, at time of construction, demonstrate that the produced impervious area is less than what the proposed planters are capable of. Analysis Design Storms: Water Quality Storm = 0.25 Inches per hour (in/hour) Conveyance Storm = 10Y-10 Min Storm 3.60 in/hour Computation Methods: Rational Method Stormwater Quality Retention Volume Storm Pipe Conveyance Software Used: Excel Design Coefficients: C = 0.90 Impervious Pavement 1.1 = 25Y Adjustment Factor Design Calculations: See Appendix C: Stormwater Design Calculations Flood Control & Conveyance Conveyance of runoff is based on a minimum of 3.0 feet per second flow at 10 year —10 minute design storm conditions and minimum pipe slope of 1.0 percent. Engineering Conclusions Stormwater design and plans conform to the City of Springfield Development Code sections 4.3- 110 and Chapters 3 & 4 of the Springfield Design Standards and Procedures Manual, adopted 2012. Stormwater from all proposed impervious pavement areas will be treated and infiltrated consistent with vegetated stormwater planter design. For conveyance, the system is designed to handle flow beyond the 10 year 10 minute design storm to the planter. An O and M agreement specific to the facilities must be filed. Stormwater facilities constructed must be properly operated and maintained for the life of the facility. Stormwater Plans See attached Appendix 8: Stormwater Plan APPENDIX A DEVELOPMENT AND PUBLIC WORKS SPRINGFIELD +F \ 225 FIFTH STREET OREGON SPRINGFIELD, OR 97477 PHONE: 541.726.3753 FAX 541.726.1021 www.spnngheldorgov STORMWATER MANAGEMENT SYSTEM SCOPE OF WORK ------- -- (Area below this tine filled out by Applicant) --------- __---_--_ (Please return to Clayton McEachern ® City ofSprbullield Development and Public Works, Pax # 736-1021, Phone # 736-1036), email: omceachern(ibspringfield-or.gov Project Name: Tentative Subdivision for Ninth St. Properties, LLC Applicant Assessors Parcel #: 17-02-31-24, Tax Lot 11900 Date: Land Use(s): Residential Phone #: Project Size (Acres): Approx. Impervious Area: 0.93 Acres Fax #: Roof: +1- 6,800 to 8,500 sf Email: Other: +/- 8,600 sf Jason Goshert, SSW Engineers Inc. 10/21/2020 541-485-8383 541-485-8384 jasong@sswengineens.com Project Description (Include a copy of Assessor's map): Proposed blot residential subdivision for 1 existing dwelling and 5 new / future dwellings. See attached Site Assessment of Existing Conditions and preliminary Land Division Tentative Plan. Drainage Proposal (Public connection(s), discharge location(s), etc. Attach additional sheets) if necessary: New impervious areas are proposed to drain to privately maintained on-site vegetated stormwater treatment facilities (and detention facilities if necessary) that collect and discharge treated runoff into the public system via piped connections to the existing 30" public stormwater main which runs along the north side of the proposed subdivision. Proposed Stormwater Best Management Practices: Raingardens and/or vegetated planters. ---(Area below this line filled out by the City and Returned to the Applicant) — (At a minimum, all boxes checked by the City on the front and back of this sheet shall be submitted _ or an application to he complete for submittal, although other requirements may be necessa Drainage Study Type (EDSPM Section 4 03.2) (Note UH may be substituted for Rational Method) ® Small Site Study—(use Rational Method for calculations) ❑ Mid -Level Development Study — (use Unit Hydrogfaph Method for calculations) ❑ Full Drainage Development Study — (use Unit Hydrograpb Method for calculations) Environmental Considerations: ❑ Wellhead Zone: 10 year TOT ❑ Hillside Development: N/a ❑ Wetland/Riparian: N/a ❑ Floodway/Floodplain: N/a ❑ Soil Type: 6-Awbirg Urban Land Complex -likely a ❑ Other Jurisdictions N/a Downstream Analysis yrdrologic group C/D soil -infiltration test —required ® N/A ❑ Flow line for starting water surface elevation: ❑ Design IIGL to use for starting water surface elevation: ❑ Manhole/Junction to take analysis to: Return to Clayton McEachern Q City of Springfield, email. criceachern@springfield-orgov, FAX- (541) 736-1021 COMPLETE STUDY ITEMS I For Official Uw Only. * Based upon the information provided on the front of this sheet, the following represents a minimum ofwhat is needed for an application to be complete for submittal with respect to drainage,' however, this list should not be used in lieu of the Springfield Development Code (SDC) or the City's Engineering Design Manual. Compliance with these requirements does not constitute site approval, Additional site specific information may be required Note: Upon scoping sheet submittal, ensure completedfnon has been signed in the space provided below: Interim Design Standards/Water Quantity (EDSPM Chapter 3 Req'd N/A Z ❑ All non -building rooftop (NBR) impervious surfaces shall be pre-treated (e.g. multi-chambered eatchbasin wood filtration media) for stonnwater quality. Additionally, a minimum o&50% of the NBR impervious surface shall be treated by vegetated methods. Z Where required, vegetative stormwater design shall be consistent with design standards (EDSPM Section 3.02), set forth in Chapter 2 of the Eugene Stormwater Management Manual. For new NBR impervious arca less than 15,000 square feet a simplified design approach may be followed as specified by the Eugene Stormwater Management Manual (Sec2.4.1). V1 ❑ If a stormwater treatment Swale is proposed, submit calculations/specifications for sizing, velocity, flow, side slopes, bottom slope, and seed mix consistent with City of Springfield or Eugene's Stormwater Management Manual. Z ❑ Water Quality calculations as required in Section 3.03.1 of the EDSPM, only required a proposed area don't meet COE st�naaids (or treat M All building rooftop mounted equipment, or other fluid containing equipment located outsi�c of the building, shall be provided with secondary containment or weather resistant rnalnsnrn. Z ❑ Drainage study prepared by a Professional Civil Engineer licensed in the state of Oregon. Z ❑ A complete drainage study, as required in EDSPM Section 4.03.1, including a hydrological study map. ZE] Calculations showing system capacity for a 2 -year storm event and overflow effects of a 25 -year storm event. 7 n The time of concentration (Tc) shall be determined using a l0 minute start time for developed basins. E] Z A downstream drainage analysis as described in EDSPM Section 4.03A.C. On-site drainage shall be governed by the Oregon Plumbing Specialty Code (OPSC). E] 0 Elevations of the HCI. and flow lines for both city and private systems where applicable. Design of Storm Systems (EDSPM Section 4.04). Flow lines, slopes, rim elevations, pipe type mil sizes clearly indicated on the plan set. Minimum pipe cover shall be 18 inches for reinforced pipe and 36 inches for plahn concrete and plastic pipe materials, or proper engineering calculations shall be provided when less. The cover shall be sufficient to support an 80,000 Ib load without before of the pipe structure. Z E Manning's "n" values for pipes shall be consistent with Table 4-1 of the EDSP. All storm pipes shall be designed to achieve a minimum velocity of three (3) feet per second at 0.5 Dice full based on Table 4-1 as well. Z Ej Existing and proposed contours, located at one foot interval. Include spot elevations and site grades showing how site drains. 7 F-1 Private stormwater easements shall be clearly depicted on plans when private stormwater flows from one property to another. 2 ❑ Drywells shall not receive runoff from any surface w/o being treated by one or more BMPs, with the exception of residential buildutg roofs (EDSP Section 3.03.4.A). Additional provisions apply to this as required by the DEQ. Refer to the website: htto://w v.deg.smle.or uywq/uic/uic htm for more information. Detention ponds shall be designed to limit runoff to pre -development rates for the 2 through 25 -year storm events. onsite soils may limit infiltration of treatment areas, but should still be maximized as much as possible to limit downstream discharge. "This form shall be included as an attachment, inside the front cover, of the stormwuter study. 'IMPORTANT. • ENGLVEER PLEASE READ BELOWAND SIGN.r As the engineer of record, I hereby certify the above required items are complete and included with the submitted stormwater study and plan set. Signature Date Form Version 5: June 2015 APPENDIX B m— I SITE STORMWATER PLAN SCALE 1 -20 A e A' q IN m 1.55'—•w a �@ a T 8800 I. O 850' FACN) R IRiUOSri P P as -ncw .0 -mss c x, I TP aII X BY2 E L LOT . 4"`n u IIY — T. \ NET I I 7 ANUT+I . L Y.R� „soR -Ol \q \ LN]PIT _ "I e 0 w.xo• n.xa• ° FL 73B g i SITE STORMWATER PLAN SCALE 1 -20 A e A' q IN m 1.55'—•w a �@ a T 8800 I. O 850' FACN) R IRiUOSri P P as -ncw SITE STORMWATER PLAN SCALE 1 -20 A e NOT TO SCALE MSYMBOLS p^ PROPOSED CLEANOUT, SEE 1C/1 SS PROPOSED DOWNSPOUT —ST— PROPOSED STORM LINE ------ PROPOSED PERFORATED STORM LINE PROPOSED STORMWATER PLANTER NOTES 1 ALL STORMWATER PIPE ARE PVC UNLESS OTHERWISE NOTED 2. PLANTING FOR S70EMWATER FACILITIES BY OTHERS. MALYMUM LOT IMPERVIOUS SURFACE 1 LOT 2 049 SO ET LOT 2 1 OU SO Fi LOTS 2, 575 SO FT LOT I 21551 SO FT LOTS 2,ACEDF NOTE LOT MAX IMPERVIOUS SURFACE IS THE PROPOSED BUILDING & DRIVEWAY SURFACE. CCC�MM`� ENGINEERSI® P.. LNC Xs..._SE OJo Z J rn J � � IL F P, >aOwm W QaF�o F h0 Z O V7=- W N�– F� MLL z z U) pia pz< Z-� EVISO 5 SITE STORMWATER PLAN wxnX MAC 01312011 MAC 6H LET q i m 1.55'—•w a _ 1_1S 13295• as -ncw .0 -mss c x, I TP aII L LOT . 4"`n EST. u IIY I I 7 _ _ e w.xo• n.xa• s 9P0.5'm. w, ss i + _ e I i Tw 1011-1 NOT TO SCALE MSYMBOLS p^ PROPOSED CLEANOUT, SEE 1C/1 SS PROPOSED DOWNSPOUT —ST— PROPOSED STORM LINE ------ PROPOSED PERFORATED STORM LINE PROPOSED STORMWATER PLANTER NOTES 1 ALL STORMWATER PIPE ARE PVC UNLESS OTHERWISE NOTED 2. PLANTING FOR S70EMWATER FACILITIES BY OTHERS. MALYMUM LOT IMPERVIOUS SURFACE 1 LOT 2 049 SO ET LOT 2 1 OU SO Fi LOTS 2, 575 SO FT LOT I 21551 SO FT LOTS 2,ACEDF NOTE LOT MAX IMPERVIOUS SURFACE IS THE PROPOSED BUILDING & DRIVEWAY SURFACE. CCC�MM`� ENGINEERSI® P.. LNC Xs..._SE OJo Z J rn J � � IL F P, >aOwm W QaF�o F h0 Z O V7=- W N�– F� MLL z z U) pia pz< Z-� EVISO 5 SITE STORMWATER PLAN wxnX MAC 01312011 MAC 6H LET SYMBOLS .,�..� EXISTING ELEVATION TOP OF CURB ...... EXISTING ELEVATON ® PROPOSED SPOT ELEVATION /.asc P ROPOS EO SPoT ELEVATION-TOPOFCURB wa uc PROPOSe05POTELEVATION-MATCHEXISTING jos=i PPO.EBSPOl DLEVATIGN-FLCI 0 �, SITE GRADING PLAN m csa ® NOT TO SCALE N.� Y JJrr ENGINEERS ®t 97401 O J o Z J rn J C d W F W�Owm w QW�O F d 4.9i ZO Vy W Z aMr,Z O�Npaa oFo_ OZa gz� REVISIONS SITE GRADING PLAN 2677]4 MAC 099 Q021 MAC (�Moo iV t, • � w I� I m Fw._M_ G.Sir _ s n_ NI.R�•_ n y n _ cl v f o Lvw; Ito a ? R I t IF eon' `w -.fit zcao ff o vsrc uvM T aa�vss, ?. - ^ w t a I{ XXI A. 8 ,.. rw z>ao i I I I~o fR Lm • 2 o,§ 14 1 �gti ru wrx®� _ ON. 0 �, SITE GRADING PLAN m csa ® NOT TO SCALE N.� Y JJrr ENGINEERS ®t 97401 O J o Z J rn J C d W F W�Owm w QW�O F d 4.9i ZO Vy W Z aMr,Z O�Npaa oFo_ OZa gz� REVISIONS SITE GRADING PLAN 2677]4 MAC 099 Q021 MAC (�Moo APPENDIX C Stormwater Surface Filtration/Infiltration Facility Sizing Spreadsheet 24 Hour Storm, NRCS Type 1A Rainfall Distribution City of Eugene Version 2.1 Name: NINTH ST PROPERTIES Date: 3/17/21 Add.; 43135TH STREET Permit Number: SPRINGFIELD. OR 87478 CatchmeatlD: PLANTERI art MICHAEL A COX. P.E. ay: SSW ENGINEERS INC Complete this bourn for each drainage catchment in the project she that is to be sized per the Presumptive Approach. Provide a distinctive Catchment ID for each facility coordinated with the site basin map to correlate the appropriate calculations with the facility. The maximum drainage catchment to be modeled per the Presumptive Approach is 1 acre (43,560 SF) =or infiltration facilities in Class A or B soils where no infiltration testing has been perfromed use an infiltration rate of 0.5 in/h r. For all facilities use a maximum soil infiltration rate of 2.5 in/hr for topsoil/growing medium. hoose "Yes" from the dropdown boxes below next to the design standards requirements for this facilely. Pollution Reduction (PR) FYes FlowControl(FC)l No Destination(DT) No an ii ancon hurt, Maar be moue as he really rse to Meet castrare,eyei,meme Total Square Footage Impervious Area= 7217 sqft Total Square Footage Pervious Area- 0 sgft Impervious Area CN=l 98 Pervious Area CN= 85 3.6 inches Total Square Footage of Drainage Area= 7217 at Time of Concentration Post Development- 10 min Weighted Average CN= 98 Site Dattel Development (Data in this section is only used if Flow Control is required) Pre -Development CN= 85 Time of Concentration Pre -Development= rain Soil Data Tested Soil Infiltration Rate= 5 iNhr(See N l Destination Design= l�.•.•••rin/hr Design Sell Infiltration Ratas=l 2.5 in/hr Soil Infiltration Rate Re vire-ant Rainfall Depth Desi nStorm Pollution Reduction 1.4 inches Water OUal' Flow Control 3.6 inches IFlootl Control Destination I 3.6 inches IFlootl Control Surface Width=If SurFdce Length=It Facility Type=RIB Facility Side Slopes=to Max. Ponding Depth in Stormwater Facility=in Depth of Growing Metlium (Soip=in tonnwater Planter Facility Surface Area= FacilitySurface PedmeW Facility Bottom Area= 1 Facility Bottom Perimeter- Basin Volume= Ratio of Facility Area to Impervious Area= 250 sgft ft sgft ft cf 110 250 110 125.0 0.035 3/30/21-12:24 PM Pollution Reduction-Calculation Hesults Peak Flow Rate to Slormwater Facility= 0051 cis Peak Facility Overflow Rate= 0.000cfs Total Runoff Valume to S[ormwater Facility= 707 cf Total Overflow Volume= 0 cf Max. Depth of Stormwater in Facility= 4.0 in Drawdown Time= 02 hours Facility Sizing Meets Pollution Reduction Standards? Meets Requirement of No Facility Flooding? Meets Requirement for Maximum of 18 Hour Drawdown Time? Flow Control-Calculation Results Peak Flow Rate to Stormwater Facility=Ncfs Peak Facility Overflow Rate= 0.125 cis Total Runoff Volume to St. an Facility=cf Total Overflow Volume= 725 cf Peak Off -Site Flow Rate Max. Depth of Stormwater in Facility=in Filtration Facility Undentrain= 0.014 cfa Drawdown Time=hours Pre-Development Runoff Data Peak Flow Rate= 0.086 cis Total Runoff Volume= 1265 cf NW Facility Sizing Meets Flow Control Standards? NA Meets Requirement for Post Development offsite flow less or equal to Pre-Development Flow? NA IMests Requirement for Maximum of 18 Hour Drawdown Time? Destination-Calculation Results cfs Peak Flow Rate to Stormwater Facility =INIA Peak Facility Overflow Rate= N!A cis Total Runoff Volume to Stormwater Facility-cf Total Overflow Volume= NIA cf Max. Depth of Stormwater In Facility=in Drawdown Time=hours N/A Facility Sizing Meets Destination Standards? NIA Meets Requirement of No Facility Flooding? N!A Meets Requirement for Maximum of 30 hour Drawdown Time? 3/30/21-12:24 PM Stormwater Surface Filtration/Infiltration Facility Sizing Spreadsheet 24 Hour Storm, NRCS Type 1A Rainfall Distribution City of Eugene Name: ntntrlbt m<urbHnr Date: 3/17/21 Address: 431 36TH STREET Permit Number: SPRINGFIELD. OR 97478 CatchmentlD: PLANTER2 :r: MICHAEL A CO%PE ay: SSW ENGINEERS INC Complete this form for each drainage catchment in the project site that is to he sized per the Presumptive Approach. Provide a distinctive Catchment ID for each facility coordinated with the site basin map to correlate the appropriate calculations with the facility. The maximum drainage catchment to be modeled per the Presumptive Approach is t acre (43,560 SF) =or infiltration facilities in Class A or B sails where no infiltration testing has been perfromed use an inti thation rate of 0.5 With, For all facilities use a maximum soil infiltration rate of 2.5 in/hr for topsoil/growing medium. loose "Yes" from the dropdown boxes below next to the design standards requirements for this facility. Pollution Reduction (PR)Yes Flow Control (FC)l No Destination(DT) No 'An initiation radaly horn be u,ixec as the Isoll"pe to MWdececetmc rensnamems Total Square Footage Impervious Area= 7292 sgft Total Square Footage Pervious Area= 0 sgft Impervious Area CN=l 98 Pervious Area CN=j 85 Total Square Footage of Drainage Area= 7292 sfl Time of Concentration Post Development= 10 min Weighted Average Ci 98 Time of Concentration Tested Soil Infiltration Rate= inim(Seenote,l) Destination Design-®inlhr Design Soil Infiltration Ratemi 2.5inlhr Soil Infiltration Rate Requirement Rainfall Death IDeadamStorm Pollution Reduction 1 4 incM1es Water Qual' Flow Cordrol 3.6 inches I Flood Control Destination 1 3.6 inches I Flood Control Surface Lengl Facility Side Slope Max. Pending Depth in Stormwater Facility= Depth of Growing Medium (Soi 3/30/21-12:24 PM Facility Surface Facility Surface Perir Facility Bottom Facility Bottom Pedr Ratio of Facility Area to Pollution a uchon- alculanon esu Peak Flow Rate to Stonnwater Facility 0.051 cfs Peak Facility Overflow Rate= 0.000 cfs Total Runoff Volume to Stormwater Facility 715 of Total Overflow Volume= 0 cf Max. Depth of Stormwater in Facility_ 5.9 in Drawdown Time= 0.2 hours Yes Facility Sizing Meets Pollution Reduction Standards? FY—EF-17111fileets, Requirement of No Facility Flooding? VE` Meets Requirement for Maximum of 18 Hour Drawdown Time? Flow Control -Calculation Results Peak Flow Rate to Stormwater Facility= 0.141 cfs is Peak Facility Overflow Rate=plis Total Runoff Volume W Stormwas" Facility= 203] cf Total Overflow Volume=f Peak Off-site Flow Rate Max. Depth of Stormwater in Facility= 6.0 in Filtration Facility llnderdrain= Drawdown Time= 25 hours Pre-Develo ment Runoff Data Peak Flow Rate = 0.087 cls Total Runoff Volume =1 1278 d NW Facility Sizing Meets Flow Control Standards? NW Meets Requirement for Post Development offsite flow lessor equal to Pre -Development Flout! NW Meets Requirement for Maximum of 18 Hour Drawdown Time? Destination -Calculation Results cfs Peak Flow Rate to Stormwater Facility =R", Peak Facility Overflow Rate= WA cfs Total Runoff Volume to Stormwater Facilitycl Total Overflow Volume= N/ Cf Max. Depth of Stormwater in Facility=in Drawdown Time=hours N/A Facility Sizing Meets Destination Standards? W77IMe.ts Requirement of No Facility Flooding? r— N/A Meets Requirement for Maximum of 30 hour Drawdown Time? B1!<ll/ii6PJPZf9�Gl Stormwater Surface Filtration/Infiltration Facility Sizing Spreadsheet 24 Hour Storm, NRCS Type to Rainfall Distribution City of Eugene Version 2.1 Name: NINTH ST PROPERTIES Date: 3/17121 Address: 431 35TH STREET Permit Number: SPRINGFIELD, OR 97478 Catchment ID: PUNTER )r: MICHAELA COX, P.E. ty: SSW ENGINEERS INC Complete this form for each drainage catchment In the project site that is to be sized per the Presumptive Approach. Provide a distinctive Catchment ID for each facility coordinated with the site basin map to correlate the appropriate calculations with the facility. The maximum drainage catchment to be modeled per the Presumptive Approach is 1 acre (43,560 SF) :or infiltration facilities in Class A or B soils where no infiltration testing has been perfromed use an infiltration rete of 0.5 in/hr. For all facilities use a maximum soil infiltration rete of 2.5 in/hr for topsoil/growing medium. loose "Yes" from the dropdown boxes below next to the design standards requirements for this facility. Pollution Reduction (PR) Yes Flow Control (FC) No Destination(DT) No 'nn saltation tenity Ten be chosen as the Miry nine to meet destination regovememe Total Square Footage Impervious Area= 6974 sgft Total Square Footage Pervious Area= 0 act Impervious Area CN= 98 Pervious Area CN= 85 Total Square Footage of Drainage Aress-1 6974 sit Time of Concentration Post Development- 10 min Weighted Average CN= 98 Site Data -Pre Development (Data in this section is only used if Flow Control is required) Pre -Development CN= 85 Time of Concentration Pre -Development= t nrn Soil Data Tested Soil Infiltration Rate= inlhr(See Note 4) Destination Design=®inlhr Design Soil Infiltration Ratismi 2.5 in/hr Soil Infiltration Rate Requirement Rainfall De th Design Storm Pollutlon option 1.4 inches Water Quality Flow Control 3.6 inches Flood Control Destination I 3.6 inches Flood Control Surface Wid Surface Long Facility Side Slops Max. Ponding Depth in SWrmwater Facility= Depth of Growing Medium (So 3/30/21-12:25 PM Planter I Facility Surface Facility Surface Perir Facility Bottom Facility Bottom Perir Ratio of Facility Area to Pollution Recluction-Calculation Results Peak Flow Rate to Stormwatrr Facility 0.049 chic Peak Facility Overflow Rate= 0.000 cfs Total Runoff Volume to Stormwater _ Facility 684 cf Total Overflow Volume= 0 cf Max. Depth of Stormwater in Facility= 5.9 in Drewdawn Time= 0.2 hours Yes Facility Sizing Meets Pollution Reduction Standards? YES Meets Requirement of No Facility Flooding? YES Meets Requirement for Maximum of 18 Hour Drawdown Time? Flow Control-Calculation Results Peak Flow Rate to Stormwater Facility =Ecis Peak Facility Overflow Rate= 0.123 cfs Total Runoff Volume to Stormwater Facility=of Total Overflow Volume= 905 cf Peak Off -Site Flow Rate Max. Depth of Stormwater in Facility=in Filtration Facility Underdmin= p 1112 cfs Drawdown Time=hours Pre-Develo mentRunoff Data Peak Flow Rate - 0.083 ofs Total Runoff Volume =1 1223 cf NW Facility Sizing Meets Flow Control Standards? Nw Meets Requirement for Post Development offsite flow less or equal to Pre-Development Flow, EE MA Meatr Requirement for Maximum of 18 Hour Drawdown Time? Destination-Calculation Results Peak Flow Rate to Stormwatrr Facility= N/A cis Peak Facility Overflow Rate= N/A cis Total Runoff Volume to Stormwatrr Facility N/ ' of Total Overflow Volume= N/A cf Max. Depth of Stormwater in Facility= N/ in Drawdown Time= N/ hours N/A Facility Sizing Meets Destination Standards? N/A Meets Requirement of No Facility Flooding? N/A Meets Requirement for Maximum of 30 hour Drawdown Time? 3/30/21-12:25 PM nmuni��i �iini�eeM ■iii�� �ioi�in ■�uA n�n�iw n ��ie�' N�i�i'dn� IlO�i nui u� �Alinm�� A Nninid ��u■i■ viii i i ���R��� v.... � m un° �i a�iiiiiiiiii�� nnn Ooi ��� �ivai �� nnA� imm�� APPENDIX D 70 Md 8 d ma N 2N N N p g n E � 5 �O $2 VG z� 2 U Ms[,us .s d � / ! .2E ! E A 8 9 »mea, } {!|> \■ )[2g�,�4«ao>+z,_* • !!,r ) - _ \/{ \ ){/ \);<A ® ! �#f19 !| )\ \ - 21 T q){1 b; »mea, } {!|> \■ )[2g�,�4«ao>+z,_* Soil Map—Lane County Area. Oregon 431 35th St, Springfield, Oregon Map Unit Legend Map Unit Symbol Map Unit NameAcres in AOI Percent of AOI 2226A Awbng-Urban land complex, 0 2.2 100.0% to 2 percent slopes Interest 2.2 I 100.0% USDn Natural Resources Web Soil Survey 3/30/2021 :G Conservation Service National Cooperative Soil Survey Page 3 of 3 APPENDIX E K & A ENGINEERING, INC. 91051 S. WILLAMETTE STREET *a P.O. Box 8486, COBURG, OR 97408 (541) 684-9399 KAENGINEERS.COM enginee-ing November 30, 2020 Project: 20066 Ninth St. Properties, LLC 17605 NW Autumn Ridge Dr. Beaverton, OR 97006 Subject: Infiltration Test Summary 43135" Street, Springfield, Oregon. PURPOSE AND SCOPE At the request of the Lane County, K & A Engineering, Inc. has completed one (1) infiltration test for the purpose of determining allowable infiltration rates for the design of stormwater facilities associated with the subject development. The scope of our services included one (1) infiltration tests, conducted on November 19, 2020 and this Written Report. INFILTRATION TEST RESULTS Locations and Depths One (1) shallow infiltration test were made at the subject project site to characterize the Infiltration rates for design and specification of stormwater retention/detention facilities for the project. The test location and depth (3 -feet) were specified by the project architect. The test location has been labelled as IT 1. The testwas made at an approximate depth of 3 -ft below the existing ground surface. See the attached Site Plan drawing for approximate location. Procedure • 6 -inch diameter borings were pre -drilled to a 3 -foot depth using 6 -inch solid stem auger and our geotechnical drill. • 5 -inch diameter PVC casing was placed in the holes and pushed approximately 6 -inches into the soil at the bottom of the hole to form the requisite soil plug. • Water was placed in the casing to a minimum height of 1 -foot above the bottom of the borehole. • Measurement of drawdown commenced within approximately 4 -hours of initial filling. • Observations continued for a period of 24 -hours after initial filling Subsurface conditions Subsurface soils, based on visual inspection of the soil cuttings during the advancement of the auger, consist of (approximately): Infiltration Test Results ma 43135`^ Street, Springfield OR November 30, 2020-K& A Engineering, Inca Project No.: 20066 en s.n Pe .n • Undocumented FILL: 1.5 -feet of dark gray,damp, soft organic SILT with woody debris, over • Organic CLAY: 1.5 -feet of dark brown, damp, soft, silty -CLAY. In general, the soil layer at the depth of infiltration test can be described as silty -CLAY. Infiltration Observations Infiltration was observed in the casing over a period of 24 -hours. No changes in the water column height inside the casing could be detected over the test period. SUMMARY AND RECOMMENDATIONS Test indicates extremely poor infiltration capacity of the organic silty -CLAY at the depth tested and we recommend that these soils are not suitable for conventional on-site storm water disposal systems such as soakage trenches. We recommend that detention or retention facilities can be used but should not be designed to incorporate any significant infiltration back into soils at the site, at least at this depth. Based on our research of logs for nearby wells', groundwater is likely to be found as shallow as 10 -feet. Further testing at greater depths may find increased infiltration capacity, but additional testing should also be accompanied by at least one deep boring to determine actual groundwater levels at the site. Deep infiltration testing, if successful, requires deeper stormwater handling facilities, which cost more to construct. K & A Engineering, Inc. should be contacted if further exploration and testing is desired to improve the viability of on-site stormwater disposal or storage. 1 Oregon Water Resources Department Well Report Query. See Well Report Query (state.or.us) Page 12 Infiltration Test Results. kea 431 35`^ Street, Springfield OR November 30, 2020 K & A Engineering, Inc. - Project No.: 20066 engineering LIMITATIONS AND USE OF GEOTECHNICAL RECOMMENDATIONS This report has been prepared for the exclusive use of Ninth St. Properties, LLC for the subject project. The geotechnical testing, analysis, and recommendations for this report meet the standards of care of competent geotechnical engineers providing similar services at the time these services were provided. We do not warrant or guarantee site surface subsurface conditions. Infiltration testing in this case was made without investigating the depth of groundwater, which can have a significant effect on seepage characteristics. We made reasonable assumptions of groundwater depth from well log report of nearby sites. The scope of our services does not include construction safety precautions, techniques, sequences, or procedures, except as specifically recommended in this report. Our services should not be interpreted as an environmental assessment of site conditions. Thank you for the opportunity to be of service. Please call me if you have any questions. Sincerely, /% Xe'-41� Michael Remboldt, P.E., G.E. K & A Engineering, Inc. SPED PROF'S G IN E X02 19,474 9 FN OREGON 1 icy TF418ER ib', p�O qF! dfNNls'RE�O EXPIRES'. DECEMBER 31. 2020 Page 1 3 APPENDIX F I + + JUNCUS EFFUSUS (COMMON RUSH) 4" POTS - 12" O.C. + 3/8" TO 3/4" ROUND ROCK NON-FLOATABLE MULCH 4" TO 8" COBBLES AT INLET LOCATIONS PIPE INLET OVERFLOW PLANTER 1 PIPE INLET io. . . . . . . . . . . . . . . v 83'-22' 4 12" INLET IN CURB m A @ 12' O.C., TYP, 47'-04" 6" 4'-6'12,-10" .........} ............................ J 4' YIW�tlN iii WN 4 3 ......... 6'' ... ....PLANTER 2 'IPE INLET PIPE INLET C T 12" INLET IN CURB NOTES @ 12'0.C., TYP. PLANTINGS PER CITY OF SPRINGFIELD, OREGON: ENGINEERING DESIGN ���D STANDARDS AND PROCEDURES MANUAL (2012) APPENDIX 6B, ZONE A; PAF MOIST TO WET CONDITIONS & CITY OF EUGENE STORMWATER MANAGEMENT MANUAL (2014); APPENDIX D, ZONE A ,S? 2� a ] 0 r STORMWATER PLANTING SCHEDULE'c Zo CO EX1 SCALE: V= 5'-0" ygFL ALpN RENEWS: 12/31/21 o -m4 LAND DIVISION TENTATIVE PLAN FOR: oarsvzoz0 SSWENGINEERS. i NINTH ST. PROPERTIES, LLC ""° r CIVIL STRUCTURAL -BUILDING DESIGN MAP 17-02-31-24, TAX LOT 11900 SURVEYING LANDUSEPLANNING 43135TH STREET xEE��'({� es" wsv� e<"<o,<e4 ,4o SPRINGFIELD OR 97478 LSLN u so1)4e �(5., 4M-aea."