HomeMy WebLinkAboutOrdinance 6419 10/19/2020
CITY OF SPRINGFIELD, OREGON
ORDINANCE NO. ___________ (SPECIAL)
AN ORDINANCE ADOPTING THE REPORT OF THE CITY ENGINEER AND FORMING A LOCAL
IMPROVEMENT DISTRICT FOR THE INSTALLATION OF SANITARY SEWER IN CREST LANE
FROM 724 CREST LANE TO 749 SUMMIT BLVD
(PROJECT P21171)
WHEREAS, on July 6, 2020, the Common Council adopted Resolution 2020-25 declaring their intent to
initiate public sewer improvements in Crest Lane from 724 Crest Lane to 749 Summit Blvd and to
assess all property to be benefitted by said improvements;
WHEREAS, at the direction of the Council, the City Engineer filed the report attached in Exhibit A with
the City Finance Director on August 4, 2020;
WHEREAS, on September 23, 2020, the Finance Director gave notice as provided in Springfield
ll persons
interested to present their objections to the report, if any they have, before the Council on October 5,
2020; and
WHEREAS, the City Council held a public hearing on October 5, 2020 and no benefitted property
owners have filed objections,
NOW, THEREFORE, THE COMMON COUNCIL OF THE CITY OF SPRINGFIELD ORDAINS AS FOLLOWS:
Section 1. The City Engineer report attached in Exhibit A (P21171) is hereby adopted.
Section 2. The Finance Director is directed to advertise that bids will be received for the
construction of the above improvement project in accordance with the City's general conditions and
standard specifications and that the project shall be awarded to the lowest responsible bidder. The
Council reserves the right to deem any bids unsatisfactory.
ADOPTED by the Common Council of the City of Springfield this ___ day of _________, ____,
by a vote of _____ for and ____ against.
APPROVED by the Council President of the City of Springfield, functioning as Mayor in
accordance with Section 17 of Springfield Charter, this ______ day of __________, ____.
_______________________
Council President
ATTEST:
10-19-20
__________________________
City Recorder
Ordinance No. 6419
Exhibit A, Page 1 of 3
M E M O R A N D U M City of Springfield
Վդ9
NateBell, Finance Director
Հէդբ9
Jeff Paschall, P.E., City Engineer
ԾՖթ՚9
August 4, 2020
Local Improvement DistrictProject No. P21171:
Սժ՟՚թ9
Engineer's Report:
Adjacent to 749 Summit Blvd & 724 CrestLane
Project Name:Crest Lane Local Sewer Extension LID
1.00In accordance with Section 3.004 of the Springfield Municipal Code, the following is
submitted for your action(s)
1.10Project Scope:Install a local sewer extension on Crest Lane toprovide a closer viable
public sanitary sewer for 749 and 789 Summit Boulevard
1.20Project Locationand Affected Properties:The project is located on Crest Lane,from
Summit Boulevard East approximately 130 feet toconnect tothe existing public sanitary
sewer manhole. The properties to be included in the district are as follows:
Map & Taxlot Number:17-03-34-14-07700
PropertyAddress:789 Summit Blvd
Record Owner, MailingAddress: Andan & Margaret Lauber
295 Morrene Drive
Campbell, CA 95008
Map & Taxlot Number:17-03-34-14-07800
PropertyAddress:749 Summit Blvd
Record Owner, MailingAddress: Alderman Family Trust
749 Summit Blvd
Springfield, OR 97477
1.30Right-of-Way:No additional construction easements or rights-of-way are expected to be
needed in the construction of this project.
1.40ProjectSchedule:Preliminary schedule for the project is as follows:
Table 1 Initial Project Schedule(Approximate Only)
MilestoneTarget Date
Complete Preliminary DesignComplete
Complete Final DesignAugust 31, 2020
Advertise for BidsSeptember 28,2020
Open BidsOctober 9, 2020
Ordinance No. 6419
Exhibit A, Page 2 of 3
Notice to ProceedOctober 26, 2020
Start ConstructionNovember 2, 2020
Complete ConstructionNovember 6, 2020
The Project Manager is encouraged to evaluate and revise this schedule often throughout
project development. Notify the City Engineer and Project Team of changes to any
element of this schedule.
1.50Project Standards:The project shall be designed in accordance with the following
standards:
Engineering Design Standards and Procedures, City of Springfield (2019or latest
edition)
Oregon Standard Specifications For Construction
2.00s:
The total project cost has been estimatedbetween$15,000 and $25,000.Final actual
costs will be determined upon completion of the projectand assessed as provided in
Springfield Municipal Code sections 3.050-3.074.The general breakdown of costs is
shownbelow. A detailed breakdown of estimated construction costs is included (Exhibit
B).
Table 2 Project Budget(Based on estimated $30,000 Project Cost)
2.102.202.302.40
TotalProperty Assessment
City
EstimatedOwners Cost
Cost
CostCost(per Lot)
Design and
$5,000$0$5,000$2,500
Administration
Right of WayN/AN/AN/AN/A
Construction$10,000-$0$ 10,000-$5,000-$10,000
$20,000$20,000
Assessment $1,000-$0$1,000-$500-$750
Service Fee$1,500$1,500
(SMC 3.072,
6.2% of direct
costs)
$16,000-$16,000-
Total$0$8,000-$13,250
$26,500$26,500
2.50Assessment Rate: Private Property
Ordinance No. 6419
Exhibit A, Page 3 of 3
The private property assessment rate will attributed 50% to the property at 789 Summit
Blvd and 749 Summit Blvd. The district will involveonly two properties and no City
participation in the costs.The final assessment rates and amounts will be set by the City
Council following a public hearing as per Springfield Municipal Code sections 3.050-
3.074.
2.60Assessment Financing: Private Property
Program. The interest rate established by the City Council for the subject Local
Improvement District is . The City offers
a 10-year financing program with semi-annual payments. Property owners who are
seniors may qualify for the Elder HousingDeferral Program, which is run by the state
3.00Resolutionof Intent to Improve No. 2020-25; Date of adoption: July 6,2020.
4.00Please proceed with the preparation and execution of the following documents in
accordance with Sec. 3.006 of the Springfield Municipal Code:
4.10Public Hearing:
4.11Date of Hearing: September 8, 2020
4.12Publish Notice of Hearing on,in the Eugene Register Guardno later than 10 days prior to
the September 8 public hearing.
4.13Furnish Engineering Office with two (2)copies of the Public Hearing notice.
Ordinance No. 6419
Exhibit B, Page 1 of 1
Exhibit B Detailed Cost Breakdown
9ƓŭźƓĻĻƩƭ 9ƭƷźƒğƷĻ ŅƚƩ /ƩĻƭƷ \[ğƓĻ {ğƓźƷğƩǤ {ĻǞĻƩ 9ǣƷĻƓƭźƚƓ9ƭƷźƒğƷĻ \[ĻǝĻƌʹ90%
tЋЊЊАЊ wĻǝźƭźƚƓ 5ğƷĻ 7/30/2020
5ĻƭĭƩźƦƷźƚƓvǒğƓƷźƷǤtĻƩ
ƓźƷ tƩźĭĻ 9ǣƷĻƓķĻķ
Mobilization1LS$1,000.00$1,000.00
Temporary Work Zone Traffic Control - Complete1LS$500.00$500.00
Erosion Control 1LS$100.00$100.00
Inlet Protection1EA$100.00$100.00
8-inch ASTM D3034 SDR 35 PVC Sanitary Sewer Pipe135LF$100.00$13,500.00
6-inch ASTM D3034 SDR 35 PVC Sanitary Sewer Pipe15LF$90.00$1,350.00
Connect New Pipe to Exisitng Manhole1EA$500.00$500.00
Level 2, ½-inch Dense Asphalt Concrete Pavement (ACP)20TON$90.00$1,800.00
4-inch Concrete Sidewalk30SF$17.50$525.00
Concrete Curb and Gutter5LF$60.00$300.00
ƚƷğƌυЊВͲЏАЎ͵ЉЉ
Ordinance No. 6419