HomeMy WebLinkAboutItem 05 Bid Award P21114AGENDA ITEM SUMMARY Meeting Date: 4/20/2020 Meeting Type: Regular Meeting Staff Contact/Dept.: Jeff Paschall/Community Development Staff Phone No: 541-726-1674 Estimated Time: Consent Calendar S P R I N G F I E L D C I T Y C O U N C I L Council Goals: Maintain and Improve Infrastructure and Facilities ITEM TITLE: BID AWARD FOR PROJECT P21114, VIRGINIA – DAISY BIKEWAY – PHASE 1A ACTION REQUESTED: Approve the following motion: TO AWARD THE SUBJECT CONTRACT TO KNIFE RIVER CORPORATION - NORTHWEST IN THE AMOUNT OF $1,137,112.71. ISSUE STATEMENT: Four bids were received on this project. Contract award is now necessary to enable work to proceed. ATTACHMENTS: Attachment 1: Bid Summary DISCUSSION/ FINANCIAL IMPACT: The Virginia-Daisy Bikeway - Phase 1A construction project will grind and overlay the existing asphalt roadway, construct ADA ramps, sidewalks, driveways, a vegetated stormwater planter, raised crosswalks, storm water facilities, speed cushion, landscaping, signage, medians, striping, and other associated features. The following bids were received and opened on March 31, 2020: Engineer’s Estimate $1,314,278.00 Knife River Corporation – Northwest $1,137,113.71 Eugene Sand and Gravel $1,153,719.00 Wildish Construction Company $1,282,267.25 Brown Contracting, Inc. $1,374,675.00 Knife River Corporation - Northwest is the low bidder on this project. The City has budgeted Sufficient funds for this project with federal and state grant funds totaling $1.18 million, and City match in Stormwater and Street Capital funds totaling $698,120 to allow award of the contract. SUMMARY OF UNIT PRICE BIDS RECEIVED: 03/31/2020 PROJECT: Virginia - Daisy Bikeway - Phase 1A Lowest Responsive Bidder:Knife River Corporation - Northwest ENGINEER'S ENGINEER'S ITEM UNIT PRICE EXTENDED UNIT NO.ITEM DESCRIPTION UNIT QUANTITY ESTIMATE PRICE ESTIMATE 1 Mobilization LS 1 125,000.00$ 125,000.00$ 49,703.71$ 49,703.71$ 70,000.00$ 70,000.00$ 115,000.00$ 115,000.00$ 162,000.00$ 162,000.00$ 2 Temporary Work Zone Traffic Control - Complete LS 1 75,000.00$ 75,000.00$ 20,000.00$ 20,000.00$ 35,000.00$ 35,000.00$ 28,000.00$ 28,000.00$ 30,000.00$ 30,000.00$ 3 Erosion Control LS 1 5,000.00$ 5,000.00$ 2,800.00$ 2,800.00$ 2,000.00$ 2,000.00$ 2,200.00$ 2,200.00$ 8,000.00$ 8,000.00$ 4 Concrete Washout Facility EA 1 2,000.00$ 2,000.00$ 1,200.00$ 1,200.00$ 2,500.00$ 2,500.00$ 3,600.00$ 3,600.00$ 5,000.00$ 5,000.00$ 5 Inlet Protection EA 32 100.00$ 3,200.00$ 65.00$ 2,080.00$ 85.00$ 2,720.00$ 200.00$ 6,400.00$ 100.00$ 3,200.00$ 6 Clearing and Grubbing LS 1 40,000.00$ 40,000.00$ 3,300.00$ 3,300.00$ 30,000.00$ 30,000.00$ 17,000.00$ 17,000.00$ 40,000.00$ 40,000.00$ 7 Mainline Video Inspection LF 142 3.00$ 426.00$ 5.00$ 710.00$ 7.00$ 994.00$ 5.75$ 816.50$ 30.00$ 4,260.00$ 8 Controlled Low Strength Material (CLSM)CY 250 100.00$ 25,000.00$ 113.00$ 28,250.00$ 99.00$ 24,750.00$ 70.00$ 17,500.00$ 25.00$ 6,250.00$ 9 10-inch ASTM D3034 SDR 35 PVC Storm Sewer Pipe LF 142 100.00$ 14,200.00$ 105.00$ 14,910.00$ 100.00$ 14,200.00$ 116.00$ 16,472.00$ 100.00$ 14,200.00$ 10 Connect New Pipe to Exisitng Manhole EA 3 500.00$ 1,500.00$ 1,200.00$ 3,600.00$ 1,100.00$ 3,300.00$ 1,200.00$ 3,600.00$ 1,000.00$ 3,000.00$ 11 Connect New Pipe to Exisitng Pipe EA 2 500.00$ 1,000.00$ 1,200.00$ 2,400.00$ 1,100.00$ 2,200.00$ 1,200.00$ 2,400.00$ 1,800.00$ 3,600.00$ 12 Install New Curb Inlet, Type 2 1/2 A EA 2 4,000.00$ 8,000.00$ 2,600.00$ 5,200.00$ 3,200.00$ 6,400.00$ 2,300.00$ 4,600.00$ 4,500.00$ 9,000.00$ 13 Install New Catch Basin,Type 2 1/2 A, w/ Steel Bike Proof Grates EA 3 4,000.00$ 12,000.00$ 3,600.00$ 10,800.00$ 4,100.00$ 12,300.00$ 2,200.00$ 6,600.00$ 4,800.00$ 14,400.00$ 14 24-inch Vegetated Stormwater Planter Overflow Inlet EA 1 2,000.00$ 2,000.00$ 1,850.00$ 1,850.00$ 1,800.00$ 1,800.00$ 1,700.00$ 1,700.00$ 3,100.00$ 3,100.00$ 15 Minor Adjustment of Manholes EA 22 2,000.00$ 44,000.00$ 1,400.00$ 30,800.00$ 1,500.00$ 33,000.00$ 1,700.00$ 37,400.00$ 3,800.00$ 83,600.00$ 16 Adjusting Catch Basins and Inlets EA 10 800.00$ 8,000.00$ 1,800.00$ 18,000.00$ 2,500.00$ 25,000.00$ 1,500.00$ 15,000.00$ 1,900.00$ 19,000.00$ 17 Adjusting Boxes, Cleanout Lids and Similar Structures EA 20 500.00$ 10,000.00$ 375.00$ 7,500.00$ 500.00$ 10,000.00$ 900.00$ 18,000.00$ 1,900.00$ 38,000.00$ 18 Cold Plane Pavement Removal, 2 Inches Deep SY 965 5.00$ 4,825.00$ 4.00$ 3,860.00$ 6.50$ 6,272.50$ 7.75$ 7,478.75$ 9.00$ 8,685.00$ 19 Cold Plane Pavement Removal, Taper 0 – 2 Inches Deep SY 6,600 5.00$ 33,000.00$ 3.50$ 23,100.00$ 3.25$ 21,450.00$ 2.50$ 16,500.00$ 5.00$ 33,000.00$ 20 Level 2, ½-inch Dense Asphalt Concrete Pavement (ACP)TON 1,650 90.00$ 148,500.00$ 83.00$ 136,950.00$ 73.00$ 120,450.00$ 105.00$ 173,250.00$ 89.00$ 146,850.00$ 21 16-inch Asphalt Concrete Pavement Repair SY 980 50.00$ 49,000.00$ 65.00$ 63,700.00$ 46.00$ 45,080.00$ 65.00$ 63,700.00$ 55.00$ 53,900.00$ 22 Plain Concrete Pavement, Undowelled, 9 Inches Thick SY 400 150.00$ 60,000.00$ 190.00$ 76,000.00$ 197.00$ 78,800.00$ 145.00$ 58,000.00$ 142.00$ 56,800.00$ 23 Concrete Curb LF 185 35.00$ 6,475.00$ 33.00$ 6,105.00$ 37.00$ 6,845.00$ 51.00$ 9,435.00$ 42.00$ 7,770.00$ 24 4-inch Concrete Sidewalk SF 11,600 17.50$ 203,000.00$ 11.00$ 127,600.00$ 9.00$ 104,400.00$ 12.00$ 139,200.00$ 10.00$ 116,000.00$ 25 Concrete ADA Ramps SF 6,434 25.00$ 160,850.00$ 32.00$ 205,888.00$ 35.00$ 225,190.00$ 33.00$ 212,322.00$ 26.00$ 167,284.00$ 26 Concrete Curb and Gutter LF 519 55.00$ 28,545.00$ 57.00$ 29,583.00$ 49.00$ 25,431.00$ 86.00$ 44,634.00$ 79.00$ 41,001.00$ 27 6-inch Concrete Residential Driveway Apron SF 387 25.00$ 9,675.00$ 18.00$ 6,966.00$ 19.00$ 7,353.00$ 12.00$ 4,644.00$ 19.00$ 7,353.00$ 28 Vegetated Stormwater Planter (STA 69+90)LS 1 15,000.00$ 15,000.00$ 30,000.00$ 30,000.00$ 35,000.00$ 35,000.00$ 28,000.00$ 28,000.00$ 29,000.00$ 29,000.00$ 29 Tree Well Each 4 10,000.00$ 40,000.00$ 11,330.00$ 45,320.00$ 11,700.00$ 46,800.00$ 13,000.00$ 52,000.00$ 10,500.00$ 42,000.00$ 30 Raised Crosswalk Each 3 12,500.00$ 37,500.00$ 16,000.00$ 48,000.00$ 14,100.00$ 42,300.00$ 18,000.00$ 54,000.00$ 24,000.00$ 72,000.00$ 31 Speed Cushion LS 1 7,500.00$ 7,500.00$ 21,000.00$ 21,000.00$ 14,100.00$ 14,100.00$ 15,000.00$ 15,000.00$ 23,000.00$ 23,000.00$ 32 Concrete Valley Gutter LF 30 60.00$ 1,800.00$ 85.00$ 2,550.00$ 93.00$ 2,790.00$ 90.00$ 2,700.00$ 190.00$ 5,700.00$ 33 Concrete Traffic Median in ACP Section LF 100 50.00$ 5,000.00$ 75.00$ 7,500.00$ 62.00$ 6,200.00$ 95.00$ 9,500.00$ 165.00$ 16,500.00$ 34 Concrete Traffic Median in PCCP Section LF 180 50.00$ 9,000.00$ 45.00$ 8,100.00$ 45.00$ 8,100.00$ 38.00$ 6,840.00$ 35.00$ 6,300.00$ 35 8-inch Concrete Commercial Driveway Apron - Reinforced SF 700 75.00$ 52,500.00$ 21.00$ 14,700.00$ 22.00$ 15,400.00$ 20.00$ 14,000.00$ 26.00$ 18,200.00$ 36 Bi-Directional Yellow Type 1 Markers EA 106 10.00$ 1,060.00$ 5.50$ 583.00$ 7.00$ 742.00$ 5.00$ 530.00$ 7.00$ 742.00$ 37 4-inch Yellow Paint Stripe LF 1,540 0.50$ 770.00$ 0.30$ 462.00$ 0.30$ 462.00$ 0.30$ 462.00$ 0.50$ 770.00$ 38 8-inch White Paint Stripe LF 7,220 0.60$ 4,332.00$ 0.40$ 2,888.00$ 0.60$ 4,332.00$ 0.40$ 2,888.00$ 0.50$ 3,610.00$ 39 Pavement Legend Type B-HS: Bicycle Lane Stencil EA 12 400.00$ 4,800.00$ 300.00$ 3,600.00$ 240.00$ 2,880.00$ 280.00$ 3,360.00$ 300.00$ 3,600.00$ 41 Pavement Legend Type B-HS: Shared Lane Stencil EA 17 400.00$ 6,800.00$ 325.00$ 5,525.00$ 270.00$ 4,590.00$ 300.00$ 5,100.00$ 310.00$ 5,270.00$ 41 Pavement Bar Type B: White 12 Inch SF 100 15.00$ 1,500.00$ 9.00$ 900.00$ 9.00$ 900.00$ 9.00$ 900.00$ 11.00$ 1,100.00$ City's Notice of Intent to Award as required by ORS 279C.375 UNIT PRICE UNIT PRICE Knife River Corporation - Northwest Eugene Sand and Gravel EXTENDED PRICE EXTENDED PRICE It is the policy of the City of Springfield to award Contracts to the Responsible Bidder submitting the lowest Responsive Bid. The City of Springfield reserves its right to reject any or all bids not in compliance with all prescribed public bidding procedures and requirements, waive minor irregularities not affecting substantial rights, and may reject for good cause any or all bids upon a finding of the City of Springfield that it is in the best public interest to do so, and accept such bids that in the opinion of the Springfield City Council are in the best interest of the City of Springfield. Please be informed that the City intends to award a contract to the Bidder so designated. Brown Contracting, Inc. UNIT PRICE EXTENDED PRICE Wildish Construction Company UNIT PRICE EXTENDED PRICE Attachment 1, Page 1 of 2 ENGINEER'S ENGINEER'S ITEM UNIT PRICE EXTENDED UNIT NO.ITEM DESCRIPTION UNIT QUANTITY ESTIMATE PRICE ESTIMATE UNIT PRICE UNIT PRICE Knife River Corporation - Northwest Eugene Sand and Gravel EXTENDED PRICE EXTENDED PRICE Brown Contracting, Inc. UNIT PRICE EXTENDED PRICE Wildish Construction Company UNIT PRICE EXTENDED PRICE 42 Pavement Bar Type B-HS: White 24 Inch SF 220 20.00$ 4,400.00$ 9.00$ 1,980.00$ 9.00$ 1,980.00$ 9.00$ 1,980.00$ 10.00$ 2,200.00$ 43 Remove and Reinstall Existing Sign Assemblies EA 13 300.00$ 3,900.00$ 200.00$ 2,600.00$ 190.00$ 2,470.00$ 300.00$ 3,900.00$ 310.00$ 4,030.00$ 44 Install Sign Support EA 27 250.00$ 6,750.00$ 480.00$ 12,960.00$ 150.00$ 4,050.00$ 500.00$ 13,500.00$ 550.00$ 14,850.00$ 45 Signs, Type IX Sheeting, Sheet Aluminum SF 100 20.00$ 2,000.00$ 15.00$ 1,500.00$ 24.00$ 2,400.00$ 17.00$ 1,700.00$ 18.00$ 1,800.00$ 46 Landscape Strip Topsoil and Seeding SF 790 3.00$ 2,370.00$ 3.00$ 2,370.00$ 3.25$ 2,567.50$ 3.50$ 2,765.00$ 5.00$ 3,950.00$ 47 Street Trees EA 47 300.00$ 14,100.00$ 600.00$ 28,200.00$ 540.00$ 25,380.00$ 530.00$ 24,910.00$ 400.00$ 18,800.00$ 48 Stormwater Facility Blended Topsoil CY 60 100.00$ 6,000.00$ 74.00$ 4,440.00$ 69.00$ 4,140.00$ 68.00$ 4,080.00$ 100.00$ 6,000.00$ 49 Vegetated Stormwater Planter Plantings LS 1 3,000.00$ 3,000.00$ 3,800.00$ 3,800.00$ 3,500.00$ 3,500.00$ 3,500.00$ 3,500.00$ 4,000.00$ 4,000.00$ 50 Tree Well Topsoil and Plantings EA 4 1,000.00$ 4,000.00$ 1,320.00$ 5,280.00$ 1,300.00$ 5,200.00$ 1,300.00$ 5,200.00$ 1,500.00$ 6,000.00$ PROJECT BID ITEM - TOTAL 1,314,278.00$ 1,137,113.71$ 1,153,719.00$ 1,282,267.25$ 1,374,675.00$ Percent Over or Under Engineer's Estimate -13.48%-12.22%-2.44%4.60% Attachment 1, Page 2 of 2