HomeMy WebLinkAboutPP_FY20-21_RWP_Budget 02-14-20MWMC Regional Wastewater Program
FY 20-21 Capital Budget &
5-Year Capital Plan
Presented By:
Troy McAllister
Michelle Miranda
1
Status of FY 19-20 Capital Program
Proposed FY 20-21 Capital Program
Proposed 5-Year Plan
Capital Improvement Plan
Asset Management Capital Plan
Presentation Objectives
2
Projects Completed FY 19-20
Decommission WPCF Lagoon (P80093)
Thermal Load Mitigation: Pre-Implementation (P80062)
3
Operations and Maintenance Building Improvements (P80085)
Resiliency Planning (P80096)
4
Projects Carried Over to FY 20-21
Renewable Natural Gas Upgrade Facilities
Class A Disinfection Facilities
Administration Building Improvements
Aeration Basin Improvements
Poplar Harvest Management Services
Riparian Shade Credit Program
Comprehensive Facility Plan Update
Recycled Water Demonstration
Facilities Plan Engineering Services
5
Projects Carried Over to FY 20-21
Renewable Natural Gas Upgrade Facilities (P80095)
Facilities Plan Engineering Services (P80090)
Comprehensive Facility Plan Update (P80101)
6
Projects Carried Over to FY 20-21
Poplar Harvest Management Services (P80083)
Riparian Shade Credit Program (P80080)
Poplar harvest services – planting activities will continue, some replanting is required, followed by initial round of MU 3 harvest in 2020. Last picture of saw logs prior to milling
at Urban Lumber’s shop.
Thermal load pre-implementation will be finishing up with completion of the phase three study report (Todd Miller)
7
Riparian Shade Credit Program (P80080)
8
Projects Carried Over to FY 20-21
Class A Disinfection Facilities (P80098)
Recycled Water Demonstration Project (P80099)
Class A Disinfection – will allow us to produce Class A level recycle water suitable for use outside of the MWMC’s fence line
The Recycled Water Demonstration Projects -- includes the urban street tree watering project in partnership with Eugene Parks and Open Space, And pumping Class A recycled water to Delta
S&G for equipment washing and dust control operations
The Riparian Shade Credit program which will develop shade credit under the PWP framework to potentially apply as offsets to the MWMC’s thermal load under a renewed MWMC NPDES permit
9
Aeration Basin Improvements (P80100)
Administration/Operations Building Improvements (P80104)
Projects Carried Over to FY 20-21
AB Phase 2 – The bulk of that project is deferred to 2021 but a smaller portion will be implemented in 2020 to do a predesign study looking at improving the aeration efficiency of the
existing phase 1 work. We will re-evaluate and potentially defer the full project anticipated for 2021 (which would modify the four western basins). For now, it is scheduled for 2021.
Administration building improvements will address the needs for remodeling that were identified in the original bid package that also included the new maintenance building and new laboratory…but
that bid option was not implemented yet those improvements are still needed.
10
New Projects for FY 20-21
Glenwood Pump Station Upgrades (P80064)
Resiliency Follow-Up (P80109)
11
Capital Improvement Program Budget
This is a partial rolled up version of Exhibit 13 that shows the total carryover and new funding adding up to the total FY 19-20 budget.
12
Asset Management Capital Program
Equipment Replacement
Major Rehabilitation
13
FY 20-21 Equipment Replacement
Programmable Logic Controllers - BMF
Belt Filter Press - Plant
Heat Exchangers - Plant
14
FY 20-21 Equipment Replacement
Automatic Transfer Switch – Irvington Pump Station
Sludge Grinders - Plant
Biosolids Spreaders - BMF
15
FY 20-21 Equipment Replacement
Centrifugal Blowers - Plant
Secondary Clarifier Rake Arms - Plant
Process Water Supply Tank - BMF
Irrigation Well Pump - BRS
16
FY 20-21 Equipment Replacement
CAB Blower Filters &
Pre-Aeration Blower Filters - Plant
Heat Pump -BMF
Polymer Feeder -BMF
17
50-Ton Shop Press - Plant
Phase Contrast Microscope - Plant
FY 20-21 Equipment Replacement
18
Equipment Replacement Program Budget
19
FY 20-21 Major Rehabilitation Program
Fog/Slurry Sealing – Air Drying Beds, BMF
Roadways Resurfacing - BMF
20
Operations & Maintenance Building Improvements
Roof Rehab – Gravity Belt Thickener Building
FY 20-21 Major Rehabilitation Program
21
Asphalt Maintenance
FY 20-21 Major Rehabilitation Program
22
FY 20-21 Major Rehabilitation Program
23
Regional Wastewater 5-Year Capital Programs
24
Questions / Comments