Loading...
HomeMy WebLinkAboutRNG Upgrades Presentation 11-8-19Renewable Natural Gas Project Update Josh Newman Luke Werner – KJ Will Overly – Blue Source November 8, 2019 1 Project context/overview Schedule update Financial status - capital cost estimate and expenditures committed Current RNG market dynamics Revised financial projection Discussion/questions/direction Presentation topics 2 Project Schedule Key Milestones Reached: Negotiation of NW Natural agreement Procurement and negotiation of long lead time biogas upgrading equipment agreement Review of pre-purchased equipment shop drawing submittals Procurement and negotiation of biogas sales (offtake) agreement 3 Capital Cost Evolution Key Changes: Additional site prep/grading necessary for the NW Natural RPF Move from Air Liquide to Greenlane Biogas for upgrading equipment Additions/modifications to increase safety/access/reliability, and lower ops costs Fiberglass reinforced plastic -> stainless steel vessels Larger manways Higher quality variable frequency drives (VFDs) Expansion of RNG building footprint Larger size and number of Greenlane equipment skids Additional separation of equipment spaces for improved O&M access and safety Reduction in potential NW Natural credit for natural gas usage in boiler Design scope/cost increases 4 Project Agreements (1) Anticipated future amendment for interconnection facility construction cost will bring total to $2,300,000 (2) Anticipated execution date 5 Facility Rendering 6 RFS market update Battle of Big Oil vs Big Ag (corn)- continues D3 Price volatility in 2019 because of exemptions (SRE) 53 SRE eligible out of 133 refiners (10% of capacity) 7% of SREs were awarded in 2018 If EPA sets reasonable targets future prices remain strong Congress intent for D3 is 10 billion vs actual of 400 mil Post 2022 RVOs being worked on currently Congress intent is growth in 2nd & 3rd generation fuels 7 RFS market update 8 RFS market update 9 RFS market update 10 RFS market update 11 June 2019 Fiscal Projection Speak to the fact that the six leftmost are extremely low probability. 12 November 2019 Fiscal Projection Low Likelihood High Likelihood Speak to the fact that the six leftmost are extremely low probability. 13 January 2020 – NW Natural construction agreement March 2020 – Installation Contractor award April 2020 – Groundbreaking Next Steps 14 Questions /Discussion/Direction 15 16 November 2019 Fiscal Projection With SB 98 Utility Pricing ($4,000,000) with SB 98, $13/MMBTU RNG and no RINs/LCFS 17 Click to add text Click to add text 18 Click to add text Click to add text 19 Click to add text Click to add text 20 Click to add text Click to add text 21 Click to add text Click to add text 22 Click to add text Click to add text 23 Click to add text Click to add text 24 Click to add text Click to add text 25 Click to add text Click to add text 26