Report of lnspection Services
Geotechnicai & Constudion Services Weldino/Hiqh-Stren sth BoltinqI6I[{G&tt{SPr$0tl, Nt
Client: lVlr. Wes Olson
Oregon Community Credit Union
P .O. Box 7702
Eugene, Oregon 97401
lnspection of: Welding
Fabricator or Erector: Gibson Steel
Contractor: lt/lcKenzie Commercial
Reviewed By:
Oregon Community CU
lVohawkBranch-T&l
1981 Mohawk Blvd.
Springfield, Oregon
Project:Date:
Project No.:
Report No.:
lnspector:
lD No.:
Shop: !
Weather:
BP No.:
03-1 6-07
2077034
E-l5731
L. Postier
5232606-85
ICC
Field: V
Clear
cotvl2006-00865
Performed visual inspection on the horizontal tube steel to column connections for the clearance wearing
frame. Completed welds were checked for size, length, profile and location.
Contractor was asked to notify our office when additional services are needed.
To the best of our knowledge, the work checked is in conformance with drawing dated 11-01-06 and
applicable AWS D1.1 code, except if noted above.
#ffiaU*,
Technical N,4anager
lVlcKenzie Commercial
Jonathan Stafford, AIA
City of Springfield
DAW:jw
This report and/or enclosed test data is the confidential property of the client to whom it is addressed and pertains to the specific
process and/or material evaluated. As such, information contained herein shall not be reproduced in part orfull and/or any part
thereof be disclosed without FEI Testing & lnspection, lnc.'s written authorization.
750 NW Comell Avenue . Corvallis, Oregon 97330 ' phone (541) 7574698' fax (541) 757-2991
29540 B Airport Road ' Eugene, Oregon 974A2'phone (541)684-3849 'fax (541)684-3851
63050 Corporate Place, Suite 2 ' Bend, Oregon 97701 'phone (541) 38248M'fax(S4l)3824846
FFIrtl Page 1 of 1
Daily Field ReportGeoteclrnical & Constuction ServicesLrsnne a msptcnon, tltc
Client:Mr. Wes Olson Project
Oregon Community Credit Union
P.O. Box77O2
Eugene, Oregon 97401
Oregon Community CU
Mohawk Branch-T & I
1981 N/ohawk Blvd.
Springfield, Oregon
Date:
Project No.:
Report No.:
lnspector:
lD No.:
03-01-07
2077037
E-1 5631
It/. IVleyer
RECEIVEI
[4AR 0 I 70rl7
lnspection of: Ceiling Grid
Contractor: [t/cKenzieCommercial
Respectfully,
Weather: lnside
BP No.: COM2006-00865
Continuous lnspection: tr
Periodic lnspection: V
Performed inspection on the completed drop-ceiling grid installation. The Armstrong
Prelude XL TEE suspension system for the 2' x 4' ceiling tiles was anchored to the 7/8"
wall moulding with rivets along two (2) adjacent walls at approximately 4' on center.
Unsecured BERC 2 clips were installed on opposite sides except on angled walls.
Support wires are also installed at each 'T'-intersection within 8" of wall faces around
perimeter of rooms. 2112" melal 'C'channel seismic struts are anchored to grids and
roof components at x|2' on center in areas larger than 144 sq. ft.
To the best of our knowledge, the work inspected was in accordance with IBC Seismic
lnstallation Requirements by Armstrong World lndustries provided by contractor,
except if noted above. Contractor was asked to notify our office when additional
services are needed.
C
Technical It/anager
McKenzie Commercial
Jonathan Stafford, AIA
City of Springfield
[/Llt/:jw
This report and/or enclosed test data is the confidential property of the client to whom it is addressed and pertains to the specific
processand/ormaterial evaluated. Assuch,informationcontainedhereinshall notbereproducedinpartorfull and/oranypart
thereof be disclosed without FEI Testing & lnspection, lnc.'s written authorization.
750 NW CornellAvenue ' Corvallis, Oregpn 97330 phone (54'1)7574698 fax (541)757-m1
29540 B Aiport Road Eugene, Oregon 97402 phone (541 ) 684-3849 tux (541 ) 6843851
(iHt
Geotechnical & Consfudbn ServicesrsnN6 & lflsPrcflqN, Nt.
*REVISED 02-22.07
February 19,2007
Mr. Richard Hunsacker
M&MLandCompany
101 East Broadway
Suite 101
Eugene, Oregon 97401
Frrual SunauaRy Reponr
Mohawk Corner t
SE Mohawk & Marcola
Springfield, Oregon
Building Permit No. COM2006-00865
Dear Mr. Hunsacker,
This letter confirms that FEI Testing & lnspection, lnc. performed special inspection services
in accordance with IBC and as directed by our client for the above-referenced project. We
were employed to provide continuous or periodic inspection on specific dates, as documented
per our special inspection reports for:
Mearthwork Mreinforced concrete Mstructuralwelding (shop)*
Estructural masonry Mbolts installed Mhigh-strength bolts
Eepoxy dowels/wedge anchors in concrete trspray applied fireproofing
Based upon our observations and written reports of this work, it is our judgment that the
inspected work was performed, to the best of our knowledge, in accordance with the approved
plans, specifications, change orders and/or structural engineer's instructions, and applicable
provisions of Chapter 17 of the International Building Code, unless otherwise noted or
referenced above.
Respectfully,
lSl fAcha,^tL
Road
M,
Technical Manager
c: l\4cKenzie Commercial
Concentric Arch itectu re
tMGH Associates
City of Springfield
MLM:jw
This report and/or enclosed test data is the confidential property of the client to whom it is addressed and pertains to the specific process and/or material
evaluated. As such, information contained herein shall not be reproduced in part or full and/or any part thereof be disclosed without FEI Testing &
lnspection, lnc.'s written authorization.
750 NIW CrrndlArrenue ' Coruallis, Oregon 97330 ' phone (541) 7574698 .tarr<(il1)757-2€F1
2540 B Airport Road ' Euoene, Oreqon 97402 ' phore (541 ) 684-3849 . fax (541 ) 684ii851
Project No.2067197
Report No. E-15520
0iit Page 1 of 1
Report of lnspection Services
IffilllffiflIl*fiffllm Geotect-rnicat & Consfuction Senaces Weldinq/H iqh-Stren h Boltinq
Client: Mr. Wes Olson* project
Oregon Community Credit Union*
P.O. Box 7702*
Eugene, Oregon 97401.
Oregon Community CU*
MohawkBranch-T&l*
1981 Mohawk Blvd.*
Springfield, Oregon
-REVISED
Date:
Project No.:
Report No.:
lnspector:
ID No.:
Shop: g
Weather:
BP No.:
REPORT 02-19-07
02-08-07
2077034.
E-l5434
D. Webber
93050801
AWS CWI
Field: !
lnside
coM2006-00865
lnspection of: Welding
Fabricator or Erector: Gibson Steel
Contractor: McKenzie Commercial
Performed visual inspection on a fabricated structural steel clearance assembly: (2) columns, (1)header
and (1) hanging pipe. Completed welds were checked for size, length, profile and location.
To the best of our knowledge, the work checked is in conformance with shop drawings dated 01-26-0T
and applicable AWS D1.1 code. Fabricator was asked to notify our office when additional services are
needed.
Reviewed By:
fr{,/U.
Michael L. Mey$r/
Technical [t/lanager
N/cKenzie Commercial
Jonathan Stafford, AIA*
City of Springfield
DAW:jw
RFC€/ LrEr
FFB2Tnw
This report and/or enclosed test data is the confidential property of the client to whom it is addressed and pertains to the specific
process and/or material evaluated. As such, information contained herein shall not be reproduced in part or full and/or any part
thereof be disclosed without FEI Testing & lnspection, lnc.'s written aulhorization.
750 NW Comell Avenue Corvallis, Oregon 97330 ' phone (541) 7574698 fax (M1) 757-2991
29540 B Airport Road Eugene, Oregon 97402 ' phone (541) 684-3849 ' fax (54'1) 684-3851
63050 Corporate Place, Suite 2 . Bend, Oregon 97701 ' phone (541) 38248M. fax (541) 3824846
0iil
Geotechnical & Constudion Serviesfi5ltfl6 & tilsPtfil0N, Il.lC
February 19,2007 Project No. 2067197
Repod No. E-15520
Mr. Richard Hunsacker
tU & tU Land Company
101 East Broadway
Suite 101
Eugene, Oregon 97401
Ftull Suut tulny RepoRr
Mohawk Corner
SE Mohawk & Marcola Road
Springfield, Oregon
Building Permit No. GOM2006-00865
Dear Mr. Hunsacker,
This letter confirms that FEI Testing & lnspection, lnc. performed special inspection services
in accordance with IBC and as directed by our client for the above-referenced project. We
were employed to provide continuous or periodic inspection on specific dates, as documented
per our special inspection reports for:
Mearthwork greinforced concrete Estructuralwelding (shop)
Estructural masonry Mbolts installed Mhigh-strength bolts
Depoxy dowels/wedge anchors in concrete trspray applied fireproofing
Based upon our observations and written reports of this work, it is our judgment that the
inspected work was performed, to the best of our knowledge, in accordance with the approved
plans, specifications, change orders and/or structural engineer's instructions, and applicable
provisions of Chapter 17 of the lnternational Building Code, unless othenruise noted or
referenced above.
Respectfully,
/1././fo,---
Michael L. MC(rer
Technical Manager
c McKenzie Commercial
Concentric Arch itectu re
MGH Associates
City of Springfield
RECEIVED
FEB 227007
MLM:jw
This report and/or enclosed test data is the confidential property of the client to whom it is addressed and pertains to the specific process and/or material
evaluated. As such, information contained herein shall not be reproduced in part or full and/or any part thereof be disclosed without FEI Testing &
lnspection, lnc.'s written authorization.
750 NW Corndl Avenue ' Corr,allis, Oegon 97330 plrcre (541 ) 757469€l ' tux (541)757-2P€1
29540 B Airport Road ' Eugere, Oregen 97402 ' phone (541 ) 684-3849 ' fax (541 ) 684-3851
I
,/
.t
Page 1 of 1
Report of lnspection Services
C,eotechnical & Constr.dion Services Weldins/Hish-Stren gth BoltinsTSTTNG & lNSPKItoil, rNC.
Client:tt/r. Richard Hunsacker
M&MLandCompany
10'1 East Broadway
Suite 101
Eugene, Oregon 97401
lnspection of: Welding
Fabricator or Erector: Gibson Steel
Contractor: McKenzie Commercial
Reviewed By:
A. Webber
Structural Steel Supervisor
McKenzie Commercial
Concentric Architecture
MGH Associates
City of Springfield
DAW:jw
Project: [t/ohawkCorner
SE lt/ohawk and Marcola Rd
Springfield, Oregon
Date:
Project No
Report No.
lnspector:
lD No.:
Shop: g
Weather:
BP No.:
02-08-07
2067197
E-15434
D. Webber
93050801
AWS CWI
Field: tr
lnside
coM2006-00865
Performed visual inspection on a fabricated structural steel clearance assembly: (2) columns, (1) header
and (1) hanging pipe. Completed welds were checked for size, length, profile and location.
To the best of our knowledge, the work checked is in conformance with shop drawings dated 01-26-07
and applicable AWS D'1.1 code, Fabricator was asked to notify our office when additional services are
needed.
This report and/or enclosed test data is the confidential property of the client to whom it is addressed and pertains to the specific
process and/or material evaluated. As such, information contained herein shall not be reproduced in part or full and/or any part
thereof be disclosed without FEI Testing & lnspection, lnc.'s written authorization.
750 NW Comell Avenue ' Corvallis, Oregon 97330 ' phone (541) 7574698' fax (541) 757-2991
29540 B Airport Road ' Eugene, Oregon 97402'phone (541) 684-3849 ' fax (541) 68+3851
63050 Corporate Place, Suite 2 ' Bend, Oregon 97701 'phone (54'l) 3824844' fax (541) 38248/:G
I
tri
Geotechnical & Constudion Services
page I of 1
Report of lnspection Services
Welding/Hish-Strensth Bolti nq
Client:Mr. Richard Hunsacker
M&MLandCompany
101 East Broadway
Suite 101
Eugene, Oregon 97401
lnspection of: High Strength Bolts
Fabricator or Erector: Myers Fabrication
Contractor: McKenzie Commercial
Reviewed By:
Project: Mohawk Corner
SE Mohawk and lvlarcola Rd
Springfield, Oregon
Met on-site with contractor to verify the 4325 high strength bolts at beam to column connection at window
opening'P'(west side) has been brought into snug tight condition in accordance with detail 10/S5.2and
RFt-33.
To the best of our knowledge, the work checked is in conformance with structural drawings, RFI-33 and
the A.l.S.C. manual. Contractor was asked to notify our office when additional services are needed.
Date:
Project No.
Report No.r
lnspector:
!D No.:
Shop: tr
Weather:
BP No.:
01-30-07
2067197
E15234
L. Postier
tcc 5232606-85
Field: @
Overcast
coM2006-00865
RECEIVED
FEB 0 5 2007
,/llw
Dale A. Webber
Structural Steel Supervisor
McKenzie Commercial
Concentric Architectu re
MGH Associates
City of Springfield
DAW:jm
This report and/or enclosed test data is the confidential property of the client to whom it is addressed and pertains to the specific
processand/ormaterial evalualed. Assuch,informationcontainedhereinshall notbereproducedinpartorfull and/oranypart
thereof be disclosed without FEI Testing & lnspection, lnc.'s written authorization.
750 NW Comell Avenue . Corvallis, Oregon 97330 ' phone (541) 7574698 fax (5a1) 757-2991
29540 B Airport Road ' Eugene, Oregon 97402'phone (541) 684-3849 fax (541) 684-3851
63050 Corporate Place, Suite 2 . Bend, Oregon 97701 ' phone (541) 38248M' fax (541) 3824846
c: