Loading...
HomeMy WebLinkAboutPermit Correspondence 2004-3-30 "' _. Requirements for Tours of Theater Construction Site on June 4th . Draw up and submit Emergency Plan to Joe Wicks in Fire Department . Provide illuminated exit signage at required exits, . Protect all pits by installing orange construction "netting" around areas a minimum of 4-5' around area and providing personnel at the area at all times the tour is in progress. . Install 2 x 4 rails down all aisles adjacent to pit. Rails should be between 30" and 36" in height with one intermediate rail. . Protect all exp:Osed rebar by installing caps, . Bend back all exposed rebar . Provide an ADA ramp at the alley exit. This ramp can be a portable ramp, The alley needs to be blocked off during the event to prevent any vehicle traffic, (p30 M"-.II"\