HomeMy WebLinkAboutPermit Building 2000-2-25
"
~
225 North Fifth Street
Springfield, OR 97477
.
.
;
I Job# 99~1681~1
Page 1 of4
TRANS#:01-0000727
DATE:FEB 25 2000
AMT RECD:2 $ 4851.74
CHANGE:
CASHIER: 059
CITY OF SPRINGFIELD, OREGON
RESIDENTIAL PERMIT
City Of Springfield
Community Services Division
Building Safety
Job Number: 99,01681,01
Office: 726,3759
Inspection Line: 726,3769
Location Of Proposed Site: 6744 Ivy St Spr
Assessors Map#: 18020314
Lot: 10 Block: Addition:
Owner:
Address:
Tax Lot #: 01600
Subdivision: South Hills North
Morgan Design and Construct
Phone Number: 541-687-9318
City/StatelZip: Eugene, OR 97408
New Value: $158,587
Scope Of Work: Single Family Residence
,
1520 Balboa Street
Contractor Registration # Expiration Date
Morgan Design and Construct
1520 Balboa Street, Eugene, OR 97408
Electrical Contr Rose Electric
89976 DAY LANE, EUGENE. OR
97402,9415
Contractor Type
General Contr
Phone
541-687,9318
541-686-0905
Mechanical Contr Associated Heating and Air Cond
PO Box 412, Eugene, OR 97440
Plumbing Contr Fridlund Plumbing
X,X,X
Quad Area:
# Of Units:
Constr. Type:
Water Heater:
541-683,2590
1
(VN) Wood Frame
Office Use
Land Use:
Zoning Code:
Bedrooms: 4
Range:
# Of Buildings: 1
Occupancy Group: Dwelling
Heat Source:
Sq. Footage: 2164
To request an inspection call the 24 hour recording at 726-3769, All inspections requested before 7:00
a.m, will be made the same working day, inspections requested after 7:00 a,m, will be made the following
working day.
Site
Verify Ground Rod
Footing
Foundation
Post and Beam
Floor Insulation
Ceiling Insulation
Shear Wall Nailing
Required Inspections
I Building I
,To be made after excavation but prior to setting forms,
,Install ground rod at footing, and call for inspection in conjuction with footing and/or foundation i
,After trenches are excavated,
,After forms are erected but prior to concrete placement.
,Prior to floor insulation or decking,
,Prior to decking,
,Prior to cover,
,Before covering sheathing with finish materials,
Framing
Wall Insulation
Drywall
Final Building
Temporary Power
Rough Electrical
Electrical Service
Final Electrical
Underfloor Plumbing
Underfloor Drain
Rough Plumbing
Water Line
Sanitary Sewer Line
Storm Sewer Line
Final Plumbing
Underfloor Mechanical
Rough Gas
Rough Mechanical
Gas Service
Final Mechanical
Curbcut
Sidewalk
.
.
Job# 99-01681-01 I
Required Inspections
Building
Page 2 of4
,Prior to cover,
,Prior to Cover
-Prior to taping,
,When all required inspections have been approved and the building is complete,
I Electrical I
,Approval required prior to SUB energizing pole,
,Prior to cover.
,Must be approved to obtain permanent power,
,When all electrical work is complete.
I Plumbing
,Prior to insulation or decking,
,Prior to cover or placement of concrete,
,Prior to cover,
,Prior to filling trench.
,Prior to filling trench.
,Prior to filling trench,
,When all plumbing work is complete,
I Mechanical
,Prior to insulation or decking,
-After line is installed and capped if not attached to an appliance,
,Prior to cover,
,After line is installed and line has been connected to a minimum of one appliance. Pressure tes
-When all mechanical work is complete,
I Public Works I
,After forms are ereceted but prior to placement of concrete,
,After excavation is complete, forms and sub base material is in place,
Construction Types~VN) Wood Frame
Occupancy Groups: Dwelling
# Of Buildings: 1
# Of Bedrooms: 4
Handicap Access? 0
rArea (Sq. Feet)
I Main: 2164 Accessoryl'l30
Building Permit
State Surcharge For Building Permit
Building Administrative Fee
Total Building
Wiring Footage 1,000 Sq Ft or Less
Wiring Footage Each Add'l 500 Sq Ft
Fee
Residential Plan Check
Total Plan Check
# Of Stories: 3
Current Units:
Census Code: Does not apply
Total:2594 J
Paid On Receipt#
Plan Check
02/25/2000 36445
Height (feet): 39
Proposed Units: 1
Value/Quantity
Fee Amount
r
158,587
$367,74
$367,74
Building
02/25/2000 727
02125/2000 727
02125/2000 727
158,587
$565,75
$39,60
$16,97
$622,32
Electrical
02/25/2000 727
02/25/2000 727
1
4
$85,00
$60,00
.
., Fee
Temporary: 200 Amps or Less
State Surcharge For Electrical Permit
Electric Administrative Fee
Total Electrical
Minimum Plumbing Permit Fee
Three Bathrooms
State Surcharge For Plumbing Permit
Plumbing Administrative Fee
Total Plumbing
Hood and Exhaust
One to Four Outlets
Minimum Mechanical Permit
Mechanical Administrative Fee
Less than 100,000 BTU
Vent Fan to One Duct
Dryer Vent
Mechanical Issuance
State Surcharge For Mechanical Permit
Total Mechanical
New Sidewalk
Total Public Works
Residential, Single Family, Storm
Sanitary Sewer
Residential Transportation
Residential Sanitary MWMC
Residential Improvement MWMC
MWMC Administrative Fee
SDC Administrative Fee
Property Annexed 1994
Total System Development
S,F, Residence, Willamalane
Total Willamalane SDC
Grand Total
Plan Check Type
Structural,Res
Checked By
Don Moore
Job# 99-01681-01 I
Paid On Receipt#
Electrical
02/25/2000 727
02/25/2000 727
02/25/2000 727
Plumbing
02/25/2000 727
02125/2000 727
02/25/2000 727
02/25/2000 727
Mechanical
02125/2000 727
02/25/2000 727
02/25/2000 727
02/25/2000 727
02/25/2000 727
02/25/2000 727
02/25/2000 727
02/25/2000 727
02/25/2000 727
Public Works
02/25/2000 727
System Development
02/25/2000 727
02/25/2000 727
02/25/2000 727
02/25/2000 727
02/25/2000 727
02/25/2000 727
02/25/2000 727
02/25/2000 727
Willamalane SDe
02/25/2000 727
Date Completed
02/25/2000
.
Page 3 of4
Value/Quantity Fee Amount
1 $40,00
$12,95
$5,55
$203,50
1
$,00
$192,50
$13.48
$5,78
$211.76
1
1
$4,50
$2,00
$,00
$,83
$6,00
$12,00
$3.00
$10.00
$1,93
$40,26
1
4
1
72
$60,00
$60.00
2,308
27
1
1
1
1
$535,34
$1,303.29
$491,60
$242,76
$22,05
$10,00
$129,23
$,20,37
$2,713.90
24
1
$1,000,00
$1,000.00
$5,219.48
.
.
I Job# 99~1681~1 I Page 4 of 4
.By signature, I state and agree, that I have carefully examined the completed application and do
hereby certify that all information hereon is true and correct, and I further certify that any and all work
performed shall be done in accordance with the Ordinances of the City of Springfield and the Laws of
the State of Oregon pertainin~ to the work described herein, and that NO OCCUPANCY will be made
of any structure without permission of the Community Services Division, Building Safety, I further
certify that only contractors and employees who are in compliance with ORS 701,055 will be used on
this project.
I further agree to ensure that all required inspections are requested at the proper time, that each
address is readable from the street, that the permit card is located at the front of the property, and the
appr sRPI~main on the site at all times during construction. ...l-&~r.J
p-nature
Date