HomeMy WebLinkAboutPermit Building 2004-2-13 (6)
_~.P'j;I".'I~l;.'_ ~.-- I.,....
~... I'
~.~ .f
Status
Issued
.
. CITY OF SPRINGFIELD
Building/Combination Permit
PERMIT NO: COM2004-00017
ISSUED: , 02/13/2004
APPLIED: 01107/2004
EXPIRES: 08/13/2004
VALUE: $ 157,805.66
225 Fifth Street, Springfield, OR
541-726-3753 Phone
541-726-3676 Fax
541-726-3769 Inspection Line
SITE ADDRESS: 2027 S A ST
ASSESSOR'S PARCEL NO.: 1703364207300
Springfield TYPE OF WORK: Office
TYPE OF USE:
New
Commercial
PROJECT DESCRIPTION: Office building
Owncr: ROSBORO LUMBER CO
Address: PO BOX 20 SPRINGFIELD OR 97477
Phone Number: 541-746-8411
# of Units:
Primary Occupancy Group:
Secondary Occupancy Group:
Primary Construction Type
Secondary Construction Type:
# of Bedrooms:
Contractor Type
General
Engineer
Mechanical
Plumbing
SETBACKS
Frontyard Setback:
Side I Setback:
Side 2 Setback:
Rearyard Sctback:
Solar Setbacks:
Street Improvements:
Storm Sewer Available:
Special Instruction:
Notes:
I CONTRACTOR INFORMATION I
Contractor
KOALA CONSTRUCTION
SS & W INC - ENGINEERS
COMFORT FLOW
PLUMB CRAZY PLUMBING INC
License
54325
Expiration Date
09/01/2006
Phone
541-461-3040
541-485-8383
541-726-0100
(541)895-4768
460
I3f,,~'1
06/27/2004
~I?d os-
BUILDING INFORMATION I
B
# of Stories:
Height of Structure
Type of Heat:
Water Type:
Range Type:
Energy Path:
I
16.50
Heat Pump
Electric
Lot Size:
Sq Ft 1st Floor: 1,584
Sq Ft 2nd Floor:
Sq Ft Basement:
Sq Ft Garage/Carport
Sq Ft Other:
Impervious Surface Area: 3,972.00
VN
- --t
NOlleE: ~~NP0RMATlON I
lHIS PERM\l SH ER lHIS PERMin!::~(,.l
AU1HORIZEO UNO S ABtat~~PR
COMMENCED OR \00 # Street Trees Rqd:
AN'{ 180 OA'{ PER . Paved Drive Rqd:
% of Lot Covcrage:
REQUIRED PARKING
Total:
Handicapped:
Compact:
I PUBLIC IMPROVEMENTS! requIreS yoU to
ra n laW n UtilitY
Jl.,TTEN110N:dQU pt~d bY t1ideQ.l~Pillt tori
UleS a tlJll1es p -. ,,"
tollOW r, cenl.er .1hOS w<<'iB~/m'iin."
-lotiticatlon 001-001 0 tnro~g sot ttle rules t
n oM'\ 952- obtain cople e telephOne
v090. :OUt~:~enter. \Not~\:~tY Notitication
calling tne oregon 2344).
umber tor ,~ _Rnn-332-
n r~""'+("""r:'
Pa!!e I of5
Status
Issued
225 Fifth Street, Springfield, OR
541-726-3753 Phone
541-726-3676 Fax
541-726-3769 Inspection Line
Description Tvpe of Construction
Bid Amount Use Bid Amount
Fee Description
Plan Review CommlInd/Public
Plan Review Fire & Life Safety
-Mechanical Issuance Fee-
+ 10% Administrative Fee
+ 7% State Surcharge
Air Handling Unit Up to 10,000
Appliance Not Listed
Building Permit
Fixture
Heat Pump
Miscellaneous Plumbing
Plan Review CommlInd/Public
Plan Review Fire & Life Safety
Planning Final Occy Inspection
Sanitary Sewer - Ist 50 Feet
Sanitary Sewer - Improvement
Sanitary Sewer - Reimbursement
SDC MWMC Administration
SDC MWMC Improvement
SDC MWMC Reimbursement
SDC Sanitary/Storm Admin
SDC Transpo Admin
SDC Transpo Improvement
SDC Transpo Reimbursement
Storm Drainage Impervious Area
Storm Sewer - Ist 50 Feet
Storm Sewer Each Addlll00'
Vent Fan
Water Line - Ist50 Feet
Total Amount Paid
.
. CITY OF SPRINGFIELD
Building/Combination Permit
PERMIT NO: COM2004-00017
ISSUED: 02/13/2004
APPLIED: 01107/2004
EXPIRES: 08/13/2004
VALUE: $ 157,805.66
I Valuation Descriotion I
$ Per Sq Ft
or multiplier
$1.00
Square Footage
or Bid Amount
157,806.00
Value
Date Calculated
Total Value of Project
$157,806.00
$157,806.00
02/11/2004
Fpp< tlWiIJ
Amount Paid
Date Paid
Receipt Number
$384.57
$236.66
$10.00
$116.32
$81.42
$8.00
$9.00
$754.15
$126.00
$12.00
$45.00
$105.63
$-236.66
$118.00
$45.00
$275.36
$362.24
$10.00
$193.91
$284.79
$57.20
$87.98
$1,193.04
$270.44
$313.78
$45.00
$56.00
$18.00
$45.00
1/7/04
1/7/04
2/13/04
2/13/04
2/13/04
2/13104
2/13/04
2/13/04
2/13/04
2/13/04
2/13/04
2/13/04
2/13/04
2/13/04
2/13/04
2/13/04
2/13/04
2/13/04
2/13/04
2/13/04
2/13/04
2/13/04
2/13/04
2/13/04
2/13/04
2/13/04
2/13/04
2/13/04
2/13/04
2200400000000000011
2200400000000000011
1200400000000000204
1200400000000000204
1200400000000000204
1200400000000000204
1200400000000000204
1200400000000000204
1200400000000000204
1200400000000000204
1200400000000000204
1200400000000000204
1200400000000000204
1200400000000000204
1200400000000000204
1200400000000000204
1200400000000000204
1200400000000000204
1200400000000000204
1200400000000000204
1200400000000000204
1200400000000000204
1200400000000000204
1200400000000000204
1200400000000000204
1200400000000000204
1200400000000000204
1200400000000000204
1200400000000000204
$5,027.83
I Plan Reviews I
Pal!e 2 of5
. . CITY OF SPRINGFIELD
Building/Combination Permit
Status Issued PERMIT NO: COM2004-000I7
225 Fifth Street, Springfield, OR ISSUED: 02/13/2004
541-726-3753 Phone APPLIED: 0110712004
541-726-3676 Fax EXPIRES: 08/13/2004
541-726-37691nspection Line VALUE: $ 157,805.66
Fire Department Review 01/13/2004 01/23/2003 OK GRG Plan Review: New office building.
Job #COM2004-00017. Occupancy
Classification: B. Construction
Type: V-No 1584 square feet.
Provide address numbers in
contrasting color from the
background positioned plainly
visible and legible from the street or
road fronting the property (1998
Oregon Structural Specialty Code
502 and 1997 Springfield Uniform
Fire Code 901.4.4).
Provide fire extinguishers with a
minimum rating of 2-A:I0-B:C
every 75 feet of travel distance. The
top of the extinguisher(s) shall be
between 3 and 5 feet above finished
floor (Springfield Uniform Fire
Code 1002.1).
Dumpsters and containers with an
individual capacity of 1.5 cubic
yards or more shall not be stored in
buildings or placed within 5 feet of
combustible walls, openings, or
combustible roof eave lines (SUFC
1103.2.2).
Initial Review 01/08/2004 01/12/2004 APP LLH
Plannin!! Review 01/13/2004 WE EMM Waiting for Improvement
Agreement, Final Plot Plan and
Development Agreement. Planner is
Tara Jones. If grading, filling or
excavating more than 50 cubic yards
an LDAP will be required.
Plannin!! Review 02/02/2004 02102/2004 APP EMM Turned in Development Agreement
on 1/29/04. Tara Jones to call
regarding submittal of an LDAP
Public Works Review 01/13/2004 02104/2004 APP SB Reviewed by E. Walters. SDCs by
SB
Revised Plan Review - Str 02/06/2004 02106/2004 APP JMP Mechanical.
Revised Plan Review - Str 02/10/2004 02110/2004 APP JMP
Revised Plan Review - SU 02/03/2004 01/30/2004 WE JF Pass lighting system and building
envelope. HV AC not yet received.
Revised Plan Review - SU 02/06/2004 02/11/2004 APP JF
Pa!!e 3 of5
.
. CITY OF ~nul'1l:.t<IELD
Building/Combination Permit
PERMIT NO: COM2004-00017
ISSUED: 02/13/2004
APPLIED: 01107/2004
EXPIRES: 08/13/2004
VALUE: $ 157,805.66
Status
Issued
225 Fifth Street, Springfield, OR
541-726-3753 Phone
541-726-3676 Fax
541-726-3769 Inspection Line
Structural Review
01/1212004
01/13/2004
WE
JMP
JMP called Mark Rainville. He will
provide the mechanical information
later with contractor information.
JMP called Ralph Wilson. He will
provide the special inspection forms.
JMP called Mark Rainville to notify
of need to complete and submit the
revised energy code forms. Gave
him the website addresses for forms
and Chapter 13.
SUB Review
01/13/2004
01/20/2004
WE
JF
To Request an inspection call the 24 hour recording at 726-3769. All inspection requested before 7:00 a.m.
will be made the same working day, inspections requested after 7:00 a.m. will be made the following work
day.
I Rpnn~pr:tinn\l
I Ufer Electrical Ground: Install ground rod at footing and call for inspection in conjunction with footing and/or
foundation inspection.
2 Footing: After trenches are excavated.
3 Post and Beam: Prior to floor insulation or decking.
4 Floor Insulation: Prior to decking.
5 Framing Inspection: Prior to cover and after all rough in inspections have been approved.
6 Wall Insulation: Prior to cover.
7 Ceiling Insulation: Prior to cover.
8 Roofing: Prior to installing any roof covering.
9 Drywall: Prior to taping.
10 Bolts Installed in Concrete: To be done by a State Certified Special Inspector. Provide inspection test reports to
City Building Inspector.
II Structural Concrete: In excess of2500 psi. To be done during construction by a State Certified Inspector.
Provide results to City Buiding Inspector
12 Glu-Lam Beams: Inspection Certificate by an approved agency to be provided to City Building Inspector prior to
placement.
13 Final Fire Department. After all requirements of the Fire Department have been met.
14 Final Building: After all required inspections have been requested and approved and the building is complete.
15 Rough Plumbing: Prior to cover and including required testing.
16 Final Plumbing: When all plumbing work is complete.
17 Sanitary Sewer Line: Prior to fIlling trench and including required testing.
18 Rough Mechanical: Prior to Cover
19 Final Mechanical: When all mechanical work is complete.
20 SUB Insulation Vapor Barrier: To he called for at the same time as the SUB framing inspection.
21 SUB Final: After all required energy inspections have heen requested and approved.
22 SUB Plumhing: Following City Rough Plumbing inspection approval and prior to cover.
23 SUB Mechanical: Following City Rongh Mechanical inspection approval aud prior to any cover.
24 SUB Ceiling Grid: Interior Lighting
25 SUB Exterior Lighting
Paee40f5
Status
Issued
225 Fifth Street, Springfield, OR
541-726-3753 Phone
541-726-3676 Fax
541-726-3769 Inspection Line
.
. CITY OF SPRINGFIELD
Building/Combination Permit
PERMIT NO: COM2004-00017
ISSUED: 02/13/2004
APPLIED: 01107/2004
EXPIRES: 08/13/2004
VALUE: $ 157,805.66
By signature, I state and agree, that I have carefully examined the completed application and do hereby certify that all
information hereon is true and correct, and I further certify that any and all work performed shall be done in accordance with
the Ordinances of the City of Springfield and the Laws of the State of Oregon pertaining to the work described herein, and
that NO OCCUPANCY will be made of any structure without permission of the Community Services Division, Building Safety.
I further certify that only contractors and employees who are in compliance with ORS 701.005 will be used on this project.
I further agree to ensure that all required inspections are requested at the proper time, that each address is readable from the
street, that the permit card is located at the front of the property, and the approved set of plans will remain on the site at all
times during construction.
'-74'41 JtfI
Ow.t.r or Contract:'s Signature
Pal!e 5 of5
')./'3/0 tj
/
Date
d'
225 Fifth Street
Springfield, Oregon 97477
541-726-3759 Phone
Job/Journal Number
COM2004-000 17
COM2004-000 17
COM2004-000 17
COM2004-00017
COM2004-000 17
COM2004-000 17
COM2004-000 17
COM2004-00017
COM2004-00017
COM2004-00017
COM2004-00017
COM2004-00017
COM2004-000 17
COM2004-000 17
COM2004-000 17
COM2004-000 17
COM2004-000 17
COM2004-000 17
COM2004-000 17
COM2004-000 17
COM2004-000 17
COM2004-000 17
COM2004-000 17
C0M2004-000 17
COM2004-000 17
COM2004-000 17
COM2004-000 17
Payments:
Type of Payment
'Check
Paid By
ROSBORO
.r'
-Wii~.i"~."."'......'.... '~':".
',',-_. , :
. !
",y-.~-'" ". ,~".,- ,
,"
;r
Receipt #: 1200400000000000204
Description
+ 10% Administrative Fee
Planning Final Occy Inspection
Stonn Drainage Impervious Area
Sanitary Sewer - Reimbursement
Sanitary Sewer - Improvement
SDC Transpo Reimbursement
SDC Transpo Improvement
SDC MWMC Reimbursement
SDC MWMC Improvement
SDC MWMC Administration
SDC SanitarylStonn Admin
SDC Transpo Admin
Fixture
Sanitary Sewer - Isl50 Feet
Water Line - 1st 50 Feet
Slonn Sewer - 1st 50 Feet
Stonn Sewer Each Addtl 100'
Miscellaneous Plumbing
Air Handling Unit Up to 10,000
Vent Fan
Heal Pump
Appliance Nol Listed
-Mechanical Issuance Fee-
Plan Review ConunlInd/Public
Plan Review Fire & Life Safety
Building Pennit
+ 7% State Surcharge
Received By
djb
Check Number
Batch Number Authorization Number
72048
City of Sprin'gfield Official Receipt.
Development Services Department
Public Works Department
Date: 02/13/2004 IO:18:52AM
Amount Paid
Item Total:
116.32
118.00
313.78
362,24
275.36
270.44
1,193.04
284.79
193.91
10.00
57.20
87.98
126.00
45.00
45.00
45.00
56.00
45.00
8.00
18.00
12.00
9.00
10.00
105.63
(236.66)
754.15
81.42
$4,4U6.6U
.
.
How Received
In Person
Payment Total:
Amount Paid
$4,406.60
$4,4U6.6U