HomeMy WebLinkAboutMiscellaneous Compliance Report 2013-11-11 •
FEI
THINS INSPECTION,IN.
ccotechnicul&Construction Service Geotechnical&Constriction Services
•
November 11, 2013 Project No. 2137002
Report No. E-35431
Ms. Connie Speck
Giustina Resources
PO Box 529
Eugene, Oregon 97440
FINAL SUMMARY REPORT
Giustina Resources Office Bldg.
200 International Way
Springfield, Oregon
Building Permit No. 811-SPR2012-02519
•
Dear Ms. Speck,
This letter confirms that FEI Testing & Inspection, Inc. performed special inspection services in
accordance with IBC and as directed by our client for the above-referenced project. We were
employed to provide continuous or periodic inspection on specific dates, as documented per our
special inspection reports for:
❑earthwork @reinforced concrete @structural welding (shop/field)
❑structural masonry @bolts cast Ehigh-strength bolts
Epost-installed•anchors in concrete @shear wall nailing
Based upon our observations and written reports of this work, it is our judgment that the inspected
work was performed, to the best of our knowledge, in accordance with the approved plans,
specifications, change orders and/or structural engineer's instructions, and applicable provisions
of Chapter 17 of the International Building Code, unless otherwise noted or referenced above.
Respectfully,
Michael L. Me r
Technical Manager
c:
Chambers Construction Co. — Brian Erickson (email)
•
Chambers Construction Co. — Jack Makarchek (email)
Robertson Sherwood Architects — Scott Stolarczyk (email)
City of Springfield
MLM:sc
This report and/or enclesea test data is the confidential property of the client to whom it is addressed and pertains to the specific process and/or material
evaluated. As such,information contained herein shall not be reproduced in pan or full and/or any part thereof be disclosed without FEI Testing&
Inspection,Inc.'s written authorization.
750 IWd Cord Avenue'Co vallis,Oregon 97330 phone(541)7574698 fax(541)757-2991
29540 B Airport Road•Eugene,newt-1 97402 phone(541)6843849•fax(541)6843851
62979 NE Plateau Drive,Suite 3 Bend,Oregon 97701 •phone(541)382-4844•fax(541)382-4846
Iianch
ENGINEERING=
November 8, 2013 Since 1977
civil, • transportaticin
Mr. Scott Stolarczyk structural • geotechnical
Robertson-Sherwood Architects s U R V E-v t N c
132 E Broadway, Suite 540
Eugene,Oregon 97401
RE: PROJECT COMPLETION IEFFFR
LIBERTY PROFESSIONAL CENTER
200 INTERNATIONAL WAY
SPRINGFIELD,OREGON
BRANCH ENGINEERING INC PROJECT No.12-181
Branch Engineering, Inc. (BEI) performed a geotechnical investigation and subsequently provided a
report dated January 7, 2013 for the above referenced project. Throughout the course of
construction BEI geotechnical staff visited the site when requested by the construction team of
Chambers Construction and Kipco Inc. to evaluation excavation subgrade, monitor aggregate
placement and compaction, observe foundation excavations, proof-roll and test compaction of
foundation and pavement base aggregates to ensure accordance with our recommendations and
project specifications. BEI's observations included the following aspects of the project's
construction:
-Site Stripping and Subgrade approval
-Structural fill placement and density testing for building pad and perimeter footings
-Column footing over-excavation and placement of Controlled Density structural fill
-Parking area pavement base rock placement and density testing
Copies of our construction observation reports are attached for reference. Based on our
observations and testing, we conclude that the site work was performed in accordance with standard
practices in the area and the work complies with our recommendations and project specifications.
Sincerely,
Branch Engineering Inc,
<cc PROF
1617 °
C O` GON
�O seA 15 �g9� �
241 O J. DE��
EXPIRES: 12/31/2013
Ronald J.Derrick,P.E., G.E.
Principal Geotechnical Engineer
EUGENE-SPRINGFIELD SALEM-KEIZER
310 51h Street,Springfield,OR 97477 I p: 541.746.0637 I www.branchengineering.com
Corporate Headquarters Salem Engineering Office
(tranCh (541)746-0637 (503)779-2577
310 5'"Street (503)Cherry Avenue N
E'N�G I N E E R I N G=
Springfield,OR 974 OR 97303
Engineering.com
ww
Since 1971
civil • transportation
structural geotechnical
SURVEYING
CONSTRUCTION OBSERVATION REPORT
Date: February 26,27,28,2013
Project: Giustina Resources—Liberty Professional Center
Project No.: 12-181:o1
BEI Field
Representative: Matthew Renner
Re: Site Stripping and Building Pad fill
February 26,2014: A Branch Engineering,Inc.(BEI)geotechnical representative visited the site of the
Liberty Professional Center to observe the stripping of topsoil and vegetation. Kipco Inc had mobilized to the
site a 350 Excavator,mid sized dozer,and a Dynapac 15-ton vibratory smooth drum roller. At the time of the
site visit the majority of the strippings had been removed from the site. Across the building pad area the
approximate fills to the top of the structural fills were laid out. Fills ranged from 3.0-feet to 5.5-feet with the
highest areas of the stripped subgrade being along the north and east sides of the buildings and the lowest
portion lying near the southwest corner of the building pad.
The building pad area was sufficiently stripped of topsoil and the native silty sandy soil was exposed. The
excavation contractor planned on beginning to import 3"-o crushed quarry rock beginning the next morning
and a subsequent visit was scheduled. There was discussion regarding Item#1 of Addendum No.2,
densification of the native soils.
February 27.2014: Branch Engineering,Inc.geotechnical engineer of record and representative met at the
start of the day with the excavation contractor and general contractor regarding the compaction of native soils.
Both the general and the excavation contractor proposed placing a 1.o-feet thick lift on the native soil before
running heavy compaction equipment due to concerns with the softness of the soil and the suitability of the
equipment. BEI requested that a first lift thickness of 6-inches be attempted and some compactive effort put
into the native soils due to the unconsolidated nature of the material. A return visit for test strips and proof
rolls was scheduled for later in the day.
A BEI representative returned to the site at approximately 12:00 to observe the placement and compaction of
3"-o structural fill. A test area was established and a first lift thickness of 6-inches was placed and a few passes
with a vibratory smooth drum roller were placed on the lift. A second 6-inch lift was placed and subsequently
compacted. A loaded dump truck was used for proof rolls on the material and significant deflection and
pumping under the tires was observed. A second test area using a lift thickness of 1.o-feet was established. A
proof roll was conducted with another loaded dump truck and a similar amount of deflection and pumping was
observed. Provided that the contractor can achieve acceptable levels of compaction of the 3"-o fill material and
95%max.dry density(per ASTM 1557)of the top 1.0-feet of 3/4"-0 crushed aggregate a first lift thickness of 1.o-
feet is acceptable for the fill in the building pad.
February 28,2014: A BEI representative visited the site at approximately 10:30 a.m.and observed 3"-o
crushed aggregate fill being placed and compacted on the building pad. The pad was approx.50%covered with
crushed aggregate and the lift being placed was approx.1.o-feet in thickness. Loaded gravel trucks were in the
process of delivering the aggregate and were observed traveling on the freshly compacted lift. Some deflection
of the aggregate mat is present under the truck traffic but appears to be improving with sustained traffic and
compaction. Item#2 of Addendum No.2 was discussed with representatives of Kipco Inc.and Chambers
Construction,3.o-feet of compacted crushed aggregate is required beneath the bottom of the perimeter
footings. BEI,Kipco Inc.,and Chambers Construction reviewed the perimeter footing details(t4/Sheet S3.1
and ao/Sheet S3.2).
.......... .. . ....
Corporate Headquarters Salem Engineering Office
*anch (541)746-0537 (503)779-2577
310 Sr'Street 4310 Cherry Avenue N
E N G I N E E R I N G
Springfield,gfia OR an4 Engineering omR 97303
Since 1977
civil • transportation
structural geotechnical
5u.Rv E:YtNc ,.
CONSTRUCTION OBSERVATION REPORT
Date: March 8,2013
Project: Giustina Resources—Liberty Professional Center
Project No.: 12-181:01
BEI Field
Representative: Matthew Renner
Re: Column Footing and Perimeter Footing Over-Excavation
March 4,2013 A Branch Engineering,Inc.(BEI)geotechnical representative visited the site of the Liberty
Professional Center at approximately 10:00 to observe the over-excavation and placement of CLSM material
underneath the future column foundation footings. Kipco Inc.was on-site and in the process of excavating to
the existing bar-run gravel at the column footing locations,CLSM was concurrently being delivered and placed
as work conditions allowed. Five excavations were open with the bottoms of the excavations visible and found
to be advanced to satisfactory depths. During the time of the site visit 8-footing excavations,primarily along
the southern portion of the building footprint were observed;either filled with CLSM,open,or in the process of
excavation. No sidewall caving or sloughing was observed in any of the open excavations.
March 9,2014: A BEI geotechnical representative visited the site of the Liberty Professional Center at
approximately 9:00 to observe the over-excavation and compaction of aggregate fill underneath the future
perimeter footings to be placed along the edge of the building footprint. At the time of the visit Kipco Inc.was
in the process of over-excavation along the northern building edge. The depth of the excavation was being set
by Kipco Inc.with a laser level and was to accommodate 3-feet of compacted aggregate underneath the
perimeter footing. The subgrade material exposed was consistent and appeared to match the descriptions of
the test pit logs(silty fine-grain sand). Aggregate removed from the footing excavations was free of
contamination from native soils and placed back in the excavation to be compacted with a back-hoe mounted
hoe-pack.
March 8,2014: A BEI geotechnical representative visited the site of the Liberty Professional Center at
approximately 1:30 to perform density tests on compacted 3/4"-o aggregate fill placed underneath future
perimeter footings. The fill was compacted and brought to grade along the north and east boundaries of the
building pad. Density tests were taken at 4-locations along the north and east boundaries,the results of the
tests ranged from 95%to loo+%of a modified proctor(AASHTO T-18o). See Table 1 below for density testing
results.
Approx.Location Dry Density(pcf) Moisture Content(%) %Max Dry Density(%)
42'west of D/1 138.7 4.5 100+
0/1.2 131.7 4.8 96.9
G/2 130 5.3 95.6
6/5 129.5 5.3 95.2
Table 1:Density Test Results
Corporate Headquarters Salem Engineering Office
(541)746-0637 (503)779-2577
�
ranch 310 5th Street 4310 Cherry Avenue N
E-( G I N E E R I N G Sp"" ensw.B anchEngineeS 'g.comR 97303
Since 1977
civil • transportation
structural geotechnical
. . SURVEYING .
CONSTRUCTION OBSERVATION REPORT
Date: March zt,2013
Project: Giustina Resources—Liberty Professional Center
Project No.: 12-181:01
BEI Field
Representative: Matthew Renner
Re: Perimeter Footing Compacted Aggregate Fill
March 12,2ot3: A Branch Engineering,Inc.(BEI)geotechnical representative visited the site of the Liberty
Professional Center at approximately moo to perform density testing by nuclear densometer method on
compacted aggregate fill below the building perimeter strip footings along the southern and western edges of
the building footprint. Test Results listing percent compaction of material's maximum thy density are as
determined by AASHTO T-t8o(modified proctor). Test Results are listed below in Table 1.
Approx.Location Dry Density(pcf) Moisture Content(%) %Max Dry Densi ty(%)
D/6 134.5 4.3 989
C/6 132.2 3.5 973
B.5/6 1323 4.7 97.4
A5/5 133.6 4.4 983
A/4 130.1 4.5 95.7
Table 1: Density Test Results
` �����y Corporate Headquarters Salem Engineering Office
�i,�g (541)746-0637 (503)779-2577
310 5'"Street 4310 Cherry Avenue N
ENGINEERING
-
Springfield,w .B 97477 nginee�l9 coma 97303
Since 1977
civil -• transportation
structural • geotechnical
SURVEYING
CONSTRUCTION OBSERVATION REPORT
Date: October 15,2013
Project: Giustina Resources
International Way,Springfield,OR
Project No.: 12-181
BEI Field
Representative: Matt Renner,P.E.
Re: Base Rock—Proof Rolls
October 1S. 2014: A representative from Branch Engineering,Inc.(BEI)visited the above referenced site to
observe proof rolls with a to CY loaded haul truck on the shared roadway accessing the Giustina site parking lot
and the site to west that is yet to be developed. Proof rolls were conducted across the full width of the roadway
from the approach at International Way to the northern end of the roadway. Minimal or no deflection of the
base rock under the load was noted. The proof rolls were discussed with Jack Makarcheck from Chambers
Construction and a return visit to perform density tests the following day was scheduled.
( B�K1 t'� ��11 Corporate Headquarters Salem Engineering Office
ranch 3ID 5'"Shee7 4370)Cherry Avenue
‘E'N/G I N E E R I N G- Springfield,°a anchEngineennlg.comR 97303
Since 1977
civil. • "transportation
structural • geotechnical
' SURVEYING
CONSTRUCTION OBSERVATION REPORT
Date: October i6,2013
Project: Giustina Resources
International Way,Springfield,OR
Project No.: 12-181
BEI Field
Representative: Matt Renner,P.E.
Re: AC Base Rock—Density Tests
October 16, 2013: A representative from Branch Engineering,Inc(BEI)visited the above referenced site to
perform density tests with a nuclear densometer(ASTM D-6938)on compacted 3/4'-(o)crushed rock aggregate
from the Wildish pit placed as AC pavement base rock. An AASHTO T-18o proctor curve was provided by
Kipco Inc. dated 7-30-13 and a maximum dry density of 138.4 pcf was used to evaluate percent relative
compaction. Density test results and approximate locations are listed below.
Dry Density Moisture Relative
Location (pcf) Content(%) Compaction(%)
Southern portion of roadway,
East lane 134.3 3.4 97
5'south of cleanout in 129.9 3.8 94
roadway,west lane
10'north of catch basin,east
129.7 4.2 94
land
South side of driveway
approach to parking lot 131.4 2.6 95
Parking lot,driving lane to
garage/dumpster area 131.0 3.0 95
Southwest area of parking lot 134.6 3.4 97
Southeast area of parking lot 135.1 3.1 98
Table-1: Density Test Results