HOPKINS Steve
From: Kristen Taylor[ktaylor @tbg-arch.com]
Sent: Friday, June 03, 2011 6:52 PM
To: Damien Gilbert; Andika Murandi; Nick Boyles; Michael Sanchez
Cc: HOPKINS Steve
Subject: RE: 51st& 52d Main Street
Hello team!
I have a couple of additional items.
Damien, in terms of the property line adjustment(PLA). The option of slightly shifting the PL between the residential
buildings does not work because there is a 2nd floor walkway extending over the PL. Therefore, we will either have to
remove the PL entirely and create on tax lot or if code allows and Nick prefers create two lots between residential and
commercial portions of the development. Please follow through with Nick, Steve Hopkins and the building department as
needed so that we can proceed with the PLA as quickly as possible so that it does not hold up the development of the
residential portion of the project. Once you talk to Steve and get a realistic understanding of the application timeline for
the PLA Type I application, please,check in with Andika or John to see how this fits in with the schedule. Damien, while I
am out of the office next week, please contact John if you need help from TBG regarding the PLA.
Steve, in the case that the timing is tight, can an excavation, grading and foundation construction permit be processed and
issued with a pending PLA application? Nick is trying to start the bulk of construction in the dry season.
Also, Steve said that we will not be required to have a pre-application/development meeting for this project prior to
submitting a building permit.
Thank you and have an excellent sunny weekend.
Kristen
Kristen G. Taylor, CSBA I Planner/Senior Project Manager
TBG Architects + Planners
132 East Broadway, Suite 2001 Eugene, Oregon 97401 •
541.687.1010 x15 I ktaylor @tbg-arch.com
•
Please consider the environment before printing this e-mail.
From: Kristen Taylor
Sent: Thursday, June 02, 2011 5:41 PM
To: 'Damien Gilbert'; Andika Murandi; 'Nick Boyles'; 'Michael Sanchez'
Cc: 'HOPKINS Steve'
Subject: 51st & 52d Main Street
Hello team,
I have an update on the Site Plan Review process. Nick has decided to proceed with Site Plan Option C for the Tentative
SR approval and Final SR. Steve Hopkins will add language in the Tentative decision allowing flexibility to modify the SR
to Option B (Type I process or less) or Option C (he will evaluate how to best include language to allow some review
flexibility for this option) so Nick can proceed with one of the other options if he receives interest from specific commercial
tenants and/or potential for ODOT policy changes.
We should expect the Tentative decision by about June 14th-15th. Steve will send me a final draft for review by June
13th.
1
•
•
•
The PIP permit can be issued once the Tentative approval is finalized (mid-week of June 13th). The trees can be
removed at any time because the tree removal permit has been approved.
I will back in the office on June 13th. If there are questions related to the Site Review, please wait until I get back or •
contact Damien.
•
Thanks,
Kristen
•
Kristen G. Taylor, CSBA I Planner/Senior Project Manager