HomeMy WebLinkAboutMiscellaneous Field Test & Inspection Report 2013-6-11 (4) irargyis Information 11/""f° .To Build On Engineering•Consulting• Testing DAILY OBSERVATION REPORT OF SINGLE-PLY THERMOPLASTIC ROOFING Date: 6/11/13 PROJECT INFORMATION Client: Wal-Mart Stores, Inc. (Store#4178) Work Area: Various Areas Project Name: Roofing Project Manufacturer: Johns Manville 60 mil reinforced TPO Location: Springfield, OR Insulation Type: JM Energy 3 Isocyanurate PSI Report No.: 654137-121-21 Contractor: Central Oregon Roofing PSI Hours Worked: 10.0 Approximate Contractor Hours Worked: 10.0 SIGNATURES Sam Stoner • Isaac Doug Roth, RRO PSI Quality Assurance Observer Roofing Contractor Reviewed By: Representative PSI Project Manager PROJECT STATUS AT-A-GLANCE Today's Performance Comment • Construction today? ®Yes ❑ No If No Construction, Inspection Done? ❑Yes ❑ No Contractor performance issues? ❑Yes ® No Schedule/scope issues? ❑ Yes ® No • DAILY PRODUCTION Total Square Feet Completed To Date Previously Today's Total Square Total Square Roof Section Completed Square Feet Feet Feet in % Complete Square Feet Completed Completed Section Main Roof Area 39,049 0 39,049 39,049 100 39,049 39,049 100 Crew Size—4 Roofers—4 Sheet Metal Workers-0 Page 1 of 4 • PSI Project No:654137 Date: 6-11-13 WEATHER CONDITIONS & EMERGENCY COVER ® Dry ❑ Sunny ® Cloudy ❑ Windy ❑ Rain ❑ Snow Temp Range (low-high) 48° to 67° F Emergency cover/protection on-site? ®Yes ❑No Type of Protection -TPO & EPDM membrane MATERIALS CONTROL &STORAGE In original identified packaging? ®Yes❑ No Off ground or deck? ® Yes❑ No Covered and vented? ® Yes❑ No Roll goods stored on side? 0 Yes❑ No Adhesive storage temperature Unapproved, damaged, or wet maintained? ®Yes ❑ No material? If Yes, how disposed? ❑Yes 01 No Comments:Very few materials remain on site. Stored material protection appears adequate. SUBSTRATE PREPARATION Night tie-in removed? ❑Yes ® No Substrate clean and debris ®Yes ❑ No removed? Substrate and penetrations ready? ®Yes❑ No Substrate tested for dryness? ® Yes ❑ No Comments: Substrates that received new roofing components were made clean with Johns Manville membrane cleaner. COVER BOARD APPLICATION (1" ENERGY 3) Correct Number of fasteners &Rhino Additional fasteners at Plates?(12 in corners, 9 at perimeter, ❑ Yes❑ No perimeters and corners? ❑Yes ❑ No 6 in the field) Fasteners checked by technician? ❑Yes❑ No Short insulation joints ❑ Yes ❑ No staggered? New/Existing Insulation joints tight? ❑ Yes❑ No All joints staggered between ❑Yes❑ No layers? Gaps filled with spray foam? ❑Yes❑ No Drainage crickets installed per ❑Yes❑ No plans and specifications? Comments: Cover board installation is complete. SINGLE-PLY MEMBRANE APPLICATION (60 MIL REINFORCED JOHNS MANVILLE TPO) Membrane allowed to relax prior to ❑Yes❑ No Membrane fully welded to Rhino ❑Yes ❑ No attachment? Plates? Membrane/plate welds checked by ❑Yes❑ No Membrane properly lapped? ❑Yes❑ No technician? Seams clean prior to welding? ❑Yes❑ No Continuous weld achieved? ❑Yes❑ No Page 2 of 4 ti PSI Project No:654137 Date: 6-11-13 SINGLE-PLY MEMBRANE APPLICATION (60 MIL REINFORCED JOHNS MANVILLE TPO) (CONT'D) Membrane flow at lap welds? ❑Yes❑ No Seams probed by technician El Yes❑No Cut edge sealant installed? El Yes❑ No T-patches installed? ❑Yes El No Primary field membrane termination El Yes❑ No (T-bar) installed? Comments: TPO membrane installation is complete. BASE FLASHING APPLICATION (60 MIL REINFORCED JOHNS MANVILLE TPO) Substrate clean and prepared? ❑Yes❑ No Adhesive applied to substrate ❑Yes El No and allowed to dry? Adhesive applied to back of base El Yes El No Adhesive allowed to flash off? ❑Yes❑ No flashing? Flashing pressed onto substrate to ❑Yes❑ No Flashing properly lapped onto ❑Yes ❑ No promote adhesion? field membrane? Seams cleaned prior to welding? El Yes❑ No Membrane flow at welds? ❑Yes ❑ No Continuous weld achieved? ❑ Yes❑ No Manufacturers approved corner ❑ Yes ❑ No patches installed? Seams probed by technician ❑Yes❑ No Cut edge sealant installed? ❑ Yes❑ No Termination bars installed? ❑Yes❑ No Counterflashings installed? ❑Yes El No Comments: Membrane base flashing is complete. NIGHT TIE-IN/ DAMAGE I SITE CLEANUP INSPECTION Night seal installed? El Yes®No Roofing appears watertight? ®Yes❑ No Roof drain fleshings completed? ®Yes❑ No Damage to property? ❑Yes 0 No Damage to client's equipment? ❑Yes 0 No Site broom clean? ❑ Yes r:4 No All debris removed from roof? ❑Yes 0 No Roof materials and equipment ®Yes❑ No appear secured? Comments:The roofing contractor has removed most of the roofing debris from the roof. Page 3 of 4 PSI Project No:654137 Date: 6-11-13 DETAIL INSTALLATION (NOTE DRAWINGS USED AS REFERENCE) Detail# Detail Name Construction Summary(Quantity/Description/Comment) 10-A4.1 Pad Layout Walkway pads were installed per Detail Drawing around several RTU units- 3-A4.1 Penetration Thirteen pipe penetrations were flashed per Johns Manville Detail TF-51. SUMMARY OF TODAY'S WORK/ DEVIATIONS /SPECIAL NOTES: Summary Comments: Work completed today appeared to conform to project plans and specifications. Unresolved EVOCO Deviation Number(s): 0 Special Notes: None today. Respectfully Submitted, • PROFESSIONAL SERVICE INDUSTRIES, INC. PSI Roof Observer: Sam Stoner CC: Portland, OR—One copy electronically Reviewed By: Doug Roth, RRO Page 4 of 4