HomeMy WebLinkAboutMiscellaneous Field Test & Inspection Report 2013-6-5 (6) i Information a' .To Build On Engineering•Consulting•Testing DAILY OBSERVATION REPORT OF SINGLE-PLY THERMOPLASTIC ROOFING Date: 6/5/13 PROJECT INFORMATION Client: Wal-Mart Stores, Inc. (Store#4178) . Work Area: Various Areas Project Name: Roofing Project Manufacturer: Johns Manville 60 mil reinforced TPO Location: Springfield, OR Insulation Type: JM Energy 3 Isocyanurate PSI Report No.: 654137-102-17 Contractor: Central Oregon Roofing PSI Hours Worked: 12.0 Approximate Contractor Hours Worked: 12.0 SIGNATURES Sam Stoner Isaac Doug Roth, RRO PSI Quality Assurance Observer Roofing Contractor Reviewed By: Representative PSI Project Manager PROJECT STATUS AT-A-GLANCE Today's Performance Comment Construction today? ® Yes ❑ No If No Construction, Inspection Done? ❑Yes ❑ No Contractor performance issues? ❑Yes ® No Schedule/scope issues? ❑Yes ® No DAILY PRODUCTION Total Square Feet Completed To Date Previously Today's Total Square Total Square Roof Section Completed Square Feet Feet Feet in % Complete Square Feet Completed Completed Section Main Roof Area 39,049 0 39,049 39,049 100 39,049 100 Crew Size—4 Roofers—4 Sheet Metal Workers—0 Page 1 of 4 PSI Project No:654137 Date: 6-5-13 WEATHER CONDITIONS & EMERGENCY COVER ® Dry ® Sunny ❑ Cloudy ® Windy ❑ Rain ❑ Snow Temp Range (low-high) 50°to 84° F Emergency cover/protection on-site? ®Yes❑No Type of Protection-TPO & EPDM membrane MATERIALS CONTROL & STORAGE In original identified packaging? ®Yes❑ No Off ground or deck? ® Yes❑ No Covered and vented? ® Yes❑ No Roll goods stored on side? ®Yes❑ No Adhesive storage temperature Yes❑ No Unapproved, damaged, or wet ❑ Yes 0 N maintained? material? If Yes, how disposed? Comments: Stored material protection appears adequate. SUBSTRATE PREPARATION Night tie-in removed? ®Yes❑ No Substrate clean and debris ®Yes❑ No removed? Substrate and penetrations ready? ® Yes❑ No Substrate tested for dryness? ®Yes❑ No Comments: Substrates that received new roofing components appeared clean and dry. COVER BOARD APPLICATION (1" ENERGY 3) Correct Number of fasteners & Rhino Additional fasteners at Plates? (12 in corners, 9 at perimeter, ❑Yes❑ No perimeters and corners? 111 Yes❑ No 6 in the field) Fasteners checked by technician? ❑yes❑ No Short insulation joints ❑ Yes❑ No staggered? New/Existing Insulation joints tight? ❑Yes❑ No All joints staggered between ❑ Yes❑ No layers? Gaps filled with spray foam? ❑Yes❑ No Drainage crickets installed per ❑Yes❑ No plans and specifications? Comments: Cover board installation is complete. SINGLE-PLY MEMBRANE APPLICATION (60 MIL REINFORCED JOHNS MANVILLE TPO) Membrane allowed to relax prior to ❑ Yes❑ No Membrane fully welded to Rhino ❑ Yes❑ No attachment? Plates? Membrane/plate welds checked by technician? ❑Yes❑ No Membrane properly lapped? ❑ Yes❑ No Seams clean prior to welding? ❑Yes❑ No Continuous weld achieved? ❑ Yes❑ No Page 2 of 4 PSI Project No:654137 Date: 6-5-13 SINGLE-PLY MEMBRANE APPLICATION (60 MIL REINFORCED JOHNS MANVILLE TPO) (CONT'D) Membrane flow at lap welds? ❑Yes❑ No Seams probed by technician ❑Yes 0 No Cut edge sealant installed? ❑Yes❑ No T-patches installed? ❑ Yes ❑ No Primary field membrane termination ❑ Yes ❑ No (T-bar) installed? Comments: TPO membrane installation is complete. BASE FLASHING APPLICATION (60 MIL REINFORCED JOHNS MANVILLE TPO) Substrate clean and prepared? ®Yes❑ No Adhesive applied to substrate ®Yes ❑ No and allowed to dry? Adhesive applied to back of base flashing? ®Yes❑ No Adhesive allowed to flash off? ®Yes ❑ No Flashing pressed onto substrate to Yes ❑ No Flashing properly lapped onto ®Yes❑ No promote adhesion? field membrane? Seams cleaned prior to welding? ®Yes❑ No Membrane flow at welds? ® Yes ❑ No Continuous weld achieved? ® Yes❑ No Manufacturer's approved corner 0 Yes ❑ No patches installed? Seams probed by technician ® Yes❑ No Cut edge sealant installed? ❑Yes®No Termination bars installed? ®Yes❑ No Counterfashings installed? ❑ Yes 0 No Comments: Parapets received membrane base flashings. NIGHT TIE-IN I DAMAGE I SITE CLEANUP INSPECTION Night seal installed? ❑Yes 0 No Roofing appears watertight? ®Yes ❑ No Roof drain flashings completed? ® Yes❑ No Damage to property? ❑Yes® No Damage to clients equipment? ❑ Yes ® No Site broom clean? ❑ Yes® No All debris removed from roof? ❑Yes® No Roof materials and equipment Yes❑ No appear secured? Comments:A night seal is no longer required. Page 3 of 4 PSI Project No:654137 Date: 6-5-13 DETAIL INSTALLATION (NOTE DRAWINGS USED AS REFERENCE) Detail# Detail Name Construction Summary(Quantity/Description/Comment) 2-A4.1 Membrane Flashing Membrane base flashing was installed along G from 1.9 to 3.1, 2.6 from A to B, and B from 2.6 to 6 per Detail Drawing. SUMMARY OF TODAY'S WORK/DEVIATIONS/SPECIAL NOTES: Summary Comments: The Roofing Subcontractor cleaned the roof and installed membrane base flashing. Work completed today appeared to conform to project plans and specifications. Unresolved EVOCO Deviation Number(s): 0 Special Notes: None today. Respectfully Submitted, PROFESSIONAL SERVICE INDUSTRIES, INC. PSI Roof Observer: Sam Stoner CC: Portland, OR—One copy electronically Reviewed By: Doug Roth, RRO Page 4 of 4