DAILY OBSERVATION REPORT OF
SINGLE-PLY THERMOPLASTIC ROOFING
Date: 6/7/13
PROJECT INFORMATION
Client:Wal-Mart Stores, Inc. (Store#4178) • Work Area:Various Areas
Project Name: Roofing Project Manufacturer: Johns Manville 60 mil reinforced TPO
Location: Springfield, OR Insulation Type: JM Energy 3 Isocyanurate
PSI Report No.: 654137-104-19 Contractor: Central Oregon Roofing
PSI Hours Worked: 5.0 Approximate Contractor Hours Worked: 6.0
SIGNATURES
•
Sam Stoner Isaac Doug Roth, RRO
PSI Quality Assurance Observer Roofing Contractor Reviewed By:
Representative PSI Project Manager
PROJECT STATUS AT-A-GLANCE
Today's Performance Comment
Construction today? 0 Yes ❑ No If No Construction, Inspection Done? ❑Yes ❑ No
Contractor performance issues? ❑Yes 0 No
Schedule/scope issues? ❑ Yes ® No
DAILY PRODUCTION
Total Square Feet Completed To Date
Previously Today's Total Square Total Square
Roof Section Completed Square Feet Feet Feet in Tu Complete
Square Feet Completed Completed Section
Main Roof Area 39,049 0 39,049 39,049 100
39,049 39,049 100
Crew Size—4 Roofers—0
Sheet Metal Workers—4
•
Page 1 of 4
PSI Project No:654137 Date: 6-7-13
WEATHER CONDITIONS & EMERGENCY COVER
N Dry ❑ Sunny ❑ Cloudy ❑ Windy ❑ Rain ❑ Snow Temp Range (low-high) 51° to 83° F
Emergency cover/protection on-site? ®Yes ❑No Type of Protection -TPO & EPDM membrane
MATERIALS CONTROL& STORAGE
In original identified packaging? N Yes❑ No Off ground or deck? N Yes❑ No
Covered and vented? N Yes❑ No Roll goods stored on side? N Yes❑ No
Adhesive storage temperature Unapproved, damaged, or wet
maintained? ® Yes❑ No material? If Yes, how disposed? ❑Yes N No
Comments: Very few materials remain on site. Stored material protection appears adequate.
SUBSTRATE PREPARATION
Night tie-in removed? ❑ Yes N No Substrate clean and debris N Yes❑ No
removed?
Substrate and penetrations ready? N Yes❑ No Substrate tested for dryness? N Yes ❑ No
Comments: Substrates that received new roofing components appeared clean and dry. A night seal is no
longer required.
COVER BOARD APPLICATION (1" ENERGY 3)
Correct Number of fasteners& Rhino Additional fasteners at
Plates?(12 in corners, 9 at perimeter, ❑Yes❑ No perimeters and corners? CI Yes❑ No
6 in the field)
Fasteners checked by technician? ❑Yes❑ No Short insulation joints ❑ Yes ❑ No
staggered?
New/Existing Insulation joints tight? ❑Yes❑ No All joints staggered between ❑Yes❑ No
layers?
Gaps filled with spray foam? ❑Yes❑ No Drainage crickets installed per ❑Yes❑ No
plans and specifications?
Comments: Cover board installation is complete.
SINGLE-PLY MEMBRANE APPLICATION (60 MIL REINFORCED JOHNS MANVILLE TPO)
Membrane allowed to relax prior to ❑Yes❑ No Membrane fully welded to Rhino ❑ Yes❑ No
attachment? Plates?
Membrane/plate welds checked by
technician? ID Yes❑ No Membrane properly lapped? ❑Yes❑ No
Seams clean prior to welding? ❑ Yes❑ No Continuous weld achieved? ❑Yes❑ No
Page 2 of 4
•
PSI Project No:654137 Date: 6-7-13
SINGLE-PLY MEMBRANE APPLICATION (60 MIL REINFORCED JOHNS MANVILLE TPO) (CONT'D)
Membrane flow at lap welds? ❑Yes❑ No Seams probed by technician ❑Yes ❑ No
Cut edge sealant installed? ❑Yes❑ No T-patches installed? ❑ Yes❑ No
Primary field membrane termination ❑Yes❑ No
(T-bar)installed?
Comments: TPO membrane installation is complete.
BASE FLASHING APPLICATION (60 MIL REINFORCED JOHNS MANVILLE TPO)
Substrate clean and prepared? ❑ Yes❑ No Adhesive applied to substrate ❑Yes ❑No
and allowed to dry?
Adhesive applied to back of base ❑Yes❑ No Adhesive allowed to flash off? ❑ Yes❑ No
flashing?
Flashing pressed onto substrate to ❑Yes❑No Flashing properly lapped onto ❑Yes❑ No
promote adhesion? field membrane?
Seams cleaned prior to welding? ❑Yes❑ No Membrane flow at welds? ❑Yes❑ No
Continuous weld achieved? ❑ Yes❑ No Manufacturer's approved corner
patches installed? ❑ Yes❑ No
Seams probed by technician ❑ Yes❑ No Cut edge sealant installed? ❑Yes❑ No
Termination bars installed? ❑Yes❑ No Counterflashings installed? ❑ Yes❑ No
Comments: Membrane base flashing is complete.
NIGHT TIE-IN/ DAMAGE /SITE CLEANUP INSPECTION
Night seal installed? ❑ Yes 0 No Roofing appears watertight? 0 Yes ❑ No
Roof drain flashings completed? ®Yes❑ No Damage to property? ❑Yes® No
Damage to client's equipment? ❑ Yes® No Site broom clean? ❑ Yes ® No
All debris removed from roof? ❑Yes No Roof materials and equipment ®Yes❑ No
appear secured? •
Comments: The roof appears watertight.
•
Page 3 of 4
PSI Project No:654137 Date: 6-7-13
DETAIL INSTALLATION (NOTE DRAWINGS USED AS REFERENCE)
Detail# Detail Name Construction Summary(Quantity/Description/Comment)
1-A4.2 Parapet Cap The contractor elected to install the pre-existing metal cap flashing per
Flashing the original detail (SMACNA 3-3#18 Butt Seam with Backup Plates)
SUMMARY OF TODAY'S WORK/ DEVIATIONS/SPECIAL NOTES:
Summary Comments: Stedman Sheet Metal re-installed the existing parapet coping. A new continuous
cleat was fastened 6" on center with 1.5" double hot dipped galvanized nails. The cleat was set in a bed of
Tremco Spectrum (S1) prior to attachment. The existing coping system utilized 6" wide concealed splice
plates at the coping butt joints. The contractor duplicated the concealed splice plate system. Three beads
of S1 were applied to each side of the splice plate prior to setting and fastening the metal coping. 0.25"
gaps were maintained between the successive lengths of coping to allow for thermal movement.
Unresolved EVOCO Deviation Number(s): 0
Special Notes: None today.
Respectfully Submitted,
PROFESSIONAL SERVICE INDUSTRIES, INC.
PSI Roof Observer: Sam Stoner
CC: Portland, OR—One copy electronically
Reviewed By: Doug Roth, RRO
Page 4 of 4