DAILY OBSERVATION REPORT OF
SINGLE-PLY THERMOPLASTIC ROOFING •
Date: 5/24/13
PROJECT INFORMATION
Client: Wal-Mart Stores, Inc. (Store#4178) Work Area: B to C.4 from 1 to 3.9
Project Name: Roofing Project Manufacturer: Johns Manville 60 mil reinforced TPO
Location: Springfield, OR Insulation Type: JM Energy 3 Isocyanurate
PSI Report No.: 654137-66-09 Contractor: Central Oregon Roofing
PSI Hours Worked: 10.0 Approximate Contractor Hours Worked: 10.0
SIGNATURES
Sam Stoner Isaac Doug Roth, RRO
PSI Quality Assurance Observer Roofing Contractor Reviewed By:
Representative PSI Project Manager
PROJECT STATUS AT-A-GLANCE
•
Today's Performance Comment
Construction today? ® Yes ❑ No If No Construction, Inspection Done? ❑Yes ❑ No
Contractor performance issues? [' Yes ® No
Schedule/scope issues? ❑ Yes ® No
DAILY PRODUCTION
Total Square Feet Completed To Date
Previously Today's Total Square Total Square
Roof Section Completed Square Feet Feet Feet in % Complete
Square Feet Completed Completed Section
Main Roof Area 32,395 5,300 37,695 39,049 96.5
37,695 39,049 96.5
Crew Size—4 Roofers—4
Sheet Metal Workers—0
•
Page 1 of 4
PSI Project No: 654137 Date: 5-24-13
WEATHER CONDITIONS & EMERGENCY COVER
® Dry ❑ Sunny ® Cloudy ❑ Windy ❑ Rain ❑ Snow Temp Range (low-high) 46°to 60° F
Emergency cover/protection on-site? ZYes ❑No Type of Protection -TPO & EPDM membrane
MATERIALS CONTROL & STORAGE
In original identified packaging? ®Yes❑ No Off ground or deck? ® Yes ❑ No
Covered and vented? ®Yes❑ No Roll goods stored on side? 0 Yes 0 No
Adhesive storage temperature Unapproved damaged, or wet
maintained? ❑ Yes ® No material? If Yes, how disposed? ❑ Yes ® No
Comments: Stored material protection appears adequate.
SUBSTRATE PREPARATION
Night tie-in removed? ® Yes❑ No Substrate clean and debris ®Yes ❑ No
removed?
Substrate and penetrations ready? ® Yes❑ No Substrate tested for dryness? Z Yes ❑ No
Comments: Substrates that received new roofing components appeared clean and dry.
COVER BOARD APPLICATION (1" ENERGY 3)
Correct Number of fasteners& Rhino Additional fasteners at
Plates? (12 in corners, 9 at perimeter, ® Yes ❑ No perimeters and corners? ® Yes ❑ No
6 in the field)
Fasteners checked by technician? ®Yes❑ No Short insulation joints ® Yes ❑ No
staggered?
New/Existing Insulation joints tight? ®Yes❑ No All joints staggered between ® Yes ❑ No
layers?
Gaps filled with spray foam? ® Yes❑ No Drainage crickets installed per ® Yes ❑ No
plans and specifications?
Comments: The isocyanurate was fastened per the roofing manufacturer's specified fastener frequency.
SINGLE-PLY MEMBRANE APPLICATION (60 MIL REINFORCED JOHNS MANVILLE TPO)
Membrane allowed to relax prior to ® Yes ❑ No Membrane fully welded to Rhino ❑ Yes No
attachment? Plates?
Membrane/plate welds checked by
technician? 0 Yes ❑ No Membrane properly lapped? ® Yes ❑ No
Seams clean prior to welding? 0 Yes ❑ No Continuous weld achieved? 0 Yes ❑ No
Page2of4
PSI Project No:654137 Date: 5-24-13
SINGLE-PLY MEMBRANE APPLICATION (60 MIL REINFORCED JOHNS MANVILLE TPO) (CONT'D)
Membrane flow at lap welds? ® Yes ❑ No Seams probed by technician ®Yes ❑ No
• Cut edge sealant installed? ❑Yes ® No T-patches installed? ❑ Yes ® No
Primary field membrane termination ❑ Yes® No •
(T-bar) installed?
Comments: Not all induction welds were completed today (work in progress).
BASE FLASHING APPLICATION (60 MIL REINFORCED JOHNS MANVILLE TPO) •
Substrate clean and prepared? CI Yes❑ No Adhesive applied to substrate ❑ Yes ❑ No
and allowed to dry?
Adhesive applied to back of base • ❑ Yes ❑ No Adhesive allowed to flash off? ❑ Yes ❑ No
flashing?
Flashing pressed onto substrate to El Yes ❑ No Flashing properly lapped onto ❑ Yes ❑ No
promote adhesion? field membrane?
Seams cleaned prior to welding? ❑Yes❑ No Membrane flow at welds? ❑ Yes ❑ No
Continuous weld achieved? ❑ Yes ❑ No Manufacturer's approved corner ❑ Yes ❑ No
patches installed?
Seams probed by technician ❑ Yes ❑ No Cut edge sealant installed? ❑ Yes ❑ No
Termination bars installed? ❑Yes ❑ No Counterflashings installed? ❑ Yes ❑ No
Comments: None installed today.
NIGHT TIE-IN / DAMAGE/ SITE CLEANUP INSPECTION
•
Night seal installed? ®Yes❑ No Roofing appears watertight? ® Yes ❑ No
Roof drain fleshings completed? ❑Yes® No Damage to property? ❑ Yes 0 No
Damage to client's equipment? El Yes 0 No Site broom clean? ❑Yes ® No
All debris removed from roof? ❑Yes ® No Roof materials and equipment ® Yes ❑ No
appear secured?
Comments: Areas of new TPO roofing appear to be watertight. The roof needs to be cleaned off.
Page 3 of 4
• PSI Project No; 654137 Date: 5-24-13
DETAIL INSTALLATION (NOTE DRAWINGS USED AS REFERENCE)
Detail# Detail Name Construction Summary (Quantity/Description/Comment)
SUMMARY OF TODAY'S WORK/ DEVIATIONS /SPECIAL NOTES:
Summary Comments: Work completed today appeared to conform to project plans and specifications.
Unresolved EVOCO Deviation Number(s):0
Special Notes: None today.
Respectfully Submitted,
PROFESSIONAL SERVICE INDUSTRIES, INC.
•
PSI Roof Observer: Sam Stoner
CC: Portland, OR—One copy electronically
Reviewed By: Doug Roth, RRO
Page 4 of 4