DAILY OBSERVATION REPORT OF
SINGLE-PLY THERMOPLASTIC ROOFING
Date: 5/16/13
PROJECT INFORMATION
Client: Wal-Mart Stores, Inc. (Store#4178) Work Area: Various Areas
Project Name: Roofing Project Manufacturer Johns Manville 60 mil reinforced TPO
Location: Springfield, OR Insulation Type: JM Energy 3 Isocyanurate
PSI Report No.: 654137-48-04 Contractor: Central Oregon Roofing
PSI Hours Worked: 11.0 Approximate Contractor Hours Worked: 11.0
SIGNATURES
Sam Stoner Isaac Doug Roth, RRO
PSI Quality Assurance Observer Roofing Contractor Reviewed By:
Representative PSI Project Manager
PROJECT STATUS AT-A-GLANCE
Today's Performance Comment
Construction today? ® Yes ❑ No If No Construction, Inspection Done? ❑ Yes ❑ No
Contractor performance issues? ❑ Yes ® No
Schedule/scope issues? ❑ Yes ® No
DAILY PRODUCTION
Total Square Feet Completed To Date
Previously Today's Total Square Total Square
Roof Section Completed Square Feet Feet Feet in % Complete
Square Feet Completed Completed Section
Main Roof Area 11,200 0 11,200 39,049 28.6
39,049 28.6
Crew Size—6 Roofers—6
Sheet Metal Workers—0
Page 1 of 4
•
PSI Project No:654137 Date: 5-16-13
WEATHER CONDITIONS & EMERGENCY COVER
❑ Dry ❑ Sunny ® Cloudy ❑ Windy ® Rain ❑ Snow Temp Range (low-high) 52°to 62° F
Emergency cover/protection on-site? ®Yes ❑No Type of Protection -TPO & EPDM membrane
MATERIALS CONTROL & STORAGE
In original identified packaging? Z Yes ❑ No Off ground or deck? E Yes ❑ No
Covered and vented? ® Yes ❑ No Roll goods stored on side? ®Yes ❑ No
Adhesive storage temperature Unapproved, damaged, or wet ❑ Yes ® No
maintained? ❑ Yes ® No material? If Yes, how disposed?
Comments: Insulation stored on the ground is in original manufacturers wrappers and covered with
visqueen.
SUBSTRATE PREPARATION
Night tie-in removed? ❑ Yes ® No Substrate clean and debris Yes ❑ No
removed?
Substrate and penetrations ready? ® Yes ❑ No Substrate tested for dryness? Z Yes ❑ No
Comments: Substrates that received new roofing components were made clean and dry.
COVER BOARD APPLICATION (1" ENERGY 3)
Correct Number of fasteners& Rhino Additional fasteners at
Plates? (12 in corners, 9 at perimeter, ❑ Yes ❑ No perimeters and corners? ❑Yes ❑ No
6 in the field)
Fasteners checked by technician? ❑ Yes ❑ No Short insulation joints ❑ Yes ❑ No
staggered?
New/Existing Insulation joints tight? ❑ Yes ❑ No All joints staggered between ❑ Yes ❑ No
layers?
Gaps filled with spray foam? ❑ Yes❑ No Drainage crickets installed per ❑ Yes ❑ No
plans and specifications?
Comments: None installed today.
SINGLE-PLY MEMBRANE APPLICATION (60 MIL REINFORCED JOHNS MANVILLE TPO)
Membrane allowed to relax prior to ❑ Yes ❑ No Membrane fully welded to Rhino ❑ Yes ❑ No
attachment? Plates?
Membrane/plate welds checked by
technician? ❑Yes ❑ No Membrane properly lapped? ❑Yes ❑ No
Seams clean prior to welding? ❑ Yes ❑ No Continuous weld achieved? ❑ Yes ❑ No
Page 2 of 4
PSI Project No:654137 • Date: 5-16-13
SINGLE-PLY MEMBRANE APPLICATION (60 MIL REINFORCED JOHNS MANVILLE TPO) (CONT'D)
Membrane flow at lap welds? ❑ Yes❑ No Seams probed by technician ❑ Yes❑ No
Cut edge sealant installed? ❑Yes ❑ No T-patches installed? ❑ Yes❑ No
Primary field membrane termination ❑Yes❑ No
(T-bar) installed? •
Comments: None installed today.
BASE FLASHING APPLICATION (60 MIL REINFORCED JOHNS MANVILLE TPO)
Substrate clean and prepared? ❑ Yes ❑ No Adhesive applied to substrate ❑ Yes ❑ No
and allowed to dry?
Adhesive applied to back of base ❑ Yes ❑ No Adhesive allowed to flash off? ❑ Yes ❑ No
flashing?
Flashing pressed onto substrate to ❑Yes❑ No Flashing properly lapped onto ❑Yes ❑ No
promote adhesion? field membrane?
Seams cleaned prior to welding? • ❑ Yes ❑ No Membrane flow at welds? ❑ Yes ❑ No
Continuous weld achieved? ❑ Yes❑ No Manufacturer's approved corner ❑ Yes❑ No
patches installed?
Seams probed by technician ❑Yes ❑ No Cut edge sealant installed? ❑ Yes ❑ No
Termination bars installed? ❑ Yes ❑ No Counterflashings installed? ❑Yes ❑ No
Comments: None installed today.
NIGHT TIE-IN/ DAMAGE I SITE CLEANUP INSPECTION
Night seal installed? ® Yes ❑ No Roofing appears watertight? ® Yes ❑ No
Roof drain flashings completed? ❑Yes ® No Damage to property? ❑ Yes ® No
Damage to client's equipment? ❑ Yes ® No Site broom clean? ❑ Yes ® No
All debris removed from roof? ❑Yes ® No Roof materials and equipment ®Yes ❑ No
appear secured?
Comments: The completed areas of roofing appear watertight.
Page 3 of 4
PSI Project No:654137 Date: 5-16-13
DETAIL INSTALLATION (NOTE DRAWINGS USED AS REFERENCE)
Detail# Detail Name Construction Summary (Quantity/Description/Comment)
SUMMARY OF TODAY'S WORK I DEVIATIONS/SPECIAL NOTES:
Summary Comments: The RhinoBond induction welding of installed field membrane continues. T-patches
were installed and trash was removed from roof.
Unresolved EVOCO Deviation Number(s):0
Special Notes: Detail 1-A4.2 shows taper on top of the parapet wood blocking. The taper does not exist.
The General Contractor will seek direction from the AOR.
Respectfully Submitted,
PROFESSIONAL SERVICE INDUSTRIES, INC.
PSI Roof Observer: Sam Stoner
CC: Portland, OR—One copy electronically
Reviewed By: Doug Roth, RRO